About this project

Key facts

Location
Faridabad
Carpet area
about 8,551 sq ft
In m²about 794.4 m², the average flat, as declared
Registered by
MONNET PROJECT DEVELOPERS LTD.the company that filed it, for Monnet Projects Developers
Timeline
  1. 5 Jun 2014Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 31 Dec 2022Possession, as declareddeclared to HARERA, read 29 Oct 2026
  3. 30 Sep 2026Registration valid toHARERA, read 3 Nov 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

In each home
  • Air-conditioningCentrally AIR condition of common area and provision of chilled water supply only
  • LiftsAs per drawing: KONE / OTIS / schindler or equivalent
  • FloorsCommon area –vitrified tile / ceramic tile / indian marble internal- cement floor
  • WallsExternal: plaster with paint & structural glazing. common area : plaster with paint
  • BathroomsCommon toilets: • china WARE (hindware / parryware / or equivalent) • CP fittings: jaquar / ESS ESS / equivalent • wall : ceramic tiles • floor: vitrified tile / indian marble / indian granite tiles
  • WindowsAluminum with glass
  • Main doorBy occupier
  • Electrical fittingsCommon area (LED/CFL, efficient light fixtures)

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: SECTOR-37, VILLAGE ANANGPUR, BYPASS ROAD

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Other register states: 1

Questions buyers ask

Is 1.677 ACERS COMMERCIAL COLONY ("M1 TRADE TOWER) registered with HARERA?From the records · HARERA, read 3 Nov 2026

HARERA lists it as 226 OF 2017. The register’s record shows an end date of 30 Sep 2026. The register shows it as: Registration lapsed.

The source ↗
What is the possession timeline for 1.677 ACERS COMMERCIAL COLONY ("M1 TRADE TOWER)?From the records · HARERA, read 3 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Dec 2022. Its registration runs to 30 Sep 2026; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around 1.677 ACERS COMMERCIAL COLONY ("M1 TRADE TOWER)?From the records · HARERA, read 3 Nov 2026

1.677 ACERS COMMERCIAL COLONY ("M1 TRADE TOWER) is in Faridabad; the site address declared to HARERA is Sector-37, Village Anangpur, Bypass Road. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building 1.677 ACERS COMMERCIAL COLONY ("M1 TRADE TOWER)?From the records · HARERA, read 3 Nov 2026

1.677 ACERS COMMERCIAL COLONY ("M1 TRADE TOWER) is a Monnet Projects Developers project, registered by its company MONNET PROJECT DEVELOPERS LTD..

The source ↗Monnet Projects Developers's projects and court record

The records

What the registers hold for 1.677 ACERS COMMERCIAL COLONY ("M1 TRADE TOWER): registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration 226 OF 2017: Registration lapsed. The register’s record shows an end date of 30 Sep 2026.HARERA, read 3 Nov 2026 · See it on HARERA ↗
  • Land licence 68 OF 2009 is on the DTCP register: Licence lapsed; the register prints its validity to 18 Nov 2024.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 5 Jun 2014, building plans 5 Jun 2014.Declared to HARERA, read 29 Oct 2026
The court record of Monnet Projects Developers’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Licence 68 OF 2009 lapsed

    Named in this project’s application. Valid to 18 Nov 2024; no renewal on record. DTCP Haryana register, read 3 Nov 2026. Source

  • Amber flag: Registration lapsed

    The register’s record shows an end date of 30 Sep 2026. HARERA Panchkula, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 8 HARERA files, with the dates we read them
Registration no.
226 OF 2017
Registration valid till
30 Sept 2026
Declared possession
31 Dec 2022

Declared by the promoter to HARERA

Land area
1.6577 (Acre) (6,708.47 sq m)
FAR
the application prints 300, which is not a ratio
licence
68 of 2009 dated 19/11/2009
Estimated project cost
₹86.39 crore
Cost of land
₹15.28 crore
Layout plan, declared approved (field 5a)
5 Jun 2014
Building plans, declared approved
5 Jun 2014
Construction to start
15 Sept 2016
Completion declared for
31 Dec 2022
Declared inventory · 1 type

Declared inventory

  • Apartment/Shops/Other Buildings · 145 units · 1,15,190 sq m carpet · 1 tower · total for 145 flats, about 794.4 m² each
Statutory approvals, as declared · 6

Statutory approvals, as declared

  • I. LICENSE — declared: already been obtained (19 Nov 2009)
  • II. ZONING PLAN — declared: already been obtained (13 Mar 2013)
  • III. FOREST CLARIFICATION — declared: already been obtained (29 Nov 2016)
  • IV. FRESH WATER ASSURANCE — declared: already been obtained (26 Oct 2016)
  • V. CTE — declared: already been obtained (7 Dec 2016)
  • VI. MINING PERMISSION — declared: already been obtained (7 Aug 2015)
On file with HARERA · 8 files

On file with HARERA (8)

Plans

Site plan

1 file
Approved Site Plan2 Jul 2019

Layout plan

1 file
Latest Layout Plan2 Jul 2019

Zoning plan

1 file
Zoning Plan2 Jul 2019

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule2 Jul 2019

Money

Accounts and finance

1 file
Non-Default Certificate from a CA2 Jul 2019

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit2 Jul 2019

HARERA’s orders

HARERA’s orders

2 files
Extension Uploaded10 Feb 2026Certificate of Extension of Registration3 Oct 2022

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

68 OF 2009 · MONNET SUGAR · FARIDABAD

Licence valid to 18 Nov 2024

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 2 Jul 2019 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 3 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

68 OF 2009: 3 parcels, 1.6578 acres in all, in Anangpur (hadbast 2), tehsil Badkhal.

The licence register prints the same licensed area, 1.66 acres.

  • rectangle 1634, kila 1634/4 min2 bigha 3 biswa 15 biswansi
  • rectangle 1634, kila 1634/4 min5 biswa 6 biswansi
  • rectangle 1634, kila 1634/4 min4 biswa

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Faridabad, then the tehsil and the village: Anangpur (hadbast 2), tehsil Badkhal. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as rectangle 1634, kila 1634/4 min.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan2 Jul 2019

Layout plan

1 file
Latest Layout Plan2 Jul 2019

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (8 in all), none is a building plan, a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/731 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Monnet Projects Developers

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.