Timeline
  1. 9 Sep 2024Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 30 Nov 2025Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside3,393 m² in all, by use
  • Plots for sale1,997 m² · 59%
  • Roads1,129 m² · 33%
  • Parks and playgrounds266 m² · 8%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: OWNERSHIP NO 20(PART) AND 21(PART) KALINDI HILLS SECTOR 49

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Other register states: 1

Questions buyers ask

Is ACHIEVERS ELITE ENCLAVE registered with HARERA?From the records · HARERA, read 3 Nov 2026

HARERA lists it as HRERA-PKL-FBD-717-2025. The register’s record shows an end date of 30 Nov 2025. The register shows it as: Registration lapsed.

The source ↗
What is the possession timeline for ACHIEVERS ELITE ENCLAVE?From the records · HARERA, read 3 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 30 Nov 2025. Its registration runs to 30 Nov 2025; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around ACHIEVERS ELITE ENCLAVE?From the records · HARERA, read 3 Nov 2026

ACHIEVERS ELITE ENCLAVE is in Faridabad; the site address declared to HARERA is Ownership No 20(Part) And 21(Part) Kalindi Hills Sector 49. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building ACHIEVERS ELITE ENCLAVE?From the records · HARERA, read 3 Nov 2026

ACHIEVERS ELITE ENCLAVE is a Achievers Builders project, registered by its company ACHIEVERS BUILDERS PVT LTD.

The source ↗Achievers Builders's projects and court record

The records

What the registers hold for ACHIEVERS ELITE ENCLAVE: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-FBD-717-2025: Registration lapsed. The register’s record shows an end date of 30 Nov 2025.HARERA, read 3 Nov 2026 · See it on HARERA ↗
  • Plans approved, as the developer declared: layout plan 9 Sep 2024.Declared to HARERA, read 29 Oct 2026
The court record of Achievers Builders’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Registration lapsed

    The register’s record shows an end date of 30 Nov 2025. HARERA Panchkula, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 7 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-FBD-717-2025
Registration valid till
30 Nov 2025
Declared possession
30 Nov 2025

Declared by the promoter to HARERA

Land area
3392.916 (Sqr/mtrs)
FAR
2.64 proposed of 2.64 permissible
licence
MCF/CTP/2025/137
Estimated project cost
₹1.70 crore
Layout plan, declared approved (field 5a)
9 Sept 2024
Construction to start
1 Jun 2025
Completion declared for
30 Nov 2025
Statutory approvals, as declared · 3

Statutory approvals, as declared

  • I. LAYOUT PLAN — declared: already been obtained (9 Sept 2024)
  • II. DEMARCATION PLAN — declared: already been obtained (1 Apr 2025)
  • III. LETTER OF INTENT — declared: already been obtained (29 Jan 2025)
On file with HARERA · 7 files

On file with HARERA (7)

Plans

Site plan

1 file
Approved Site Plan10 May 2025

Layout plan

1 file
Latest Layout Plan10 May 2025

Zoning plan

1 file
Zoning Plan10 May 2025

Demarcation plan

1 file
Demarcation Plan10 May 2025

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule10 May 2025

Money

Accounts and finance

1 file
Non-Default Certificate from a CA11 May 2025

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit11 May 2025

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

The promoter declared MCF/CTP/2025/137. We could not read a licence number from that, so nothing is claimed about it here.

declared in the registration application (Form REP-I), Panchkula bench · submitted 12 May 2025 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 3 Nov 2026

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan10 May 2025

Layout plan

1 file
Latest Layout Plan10 May 2025

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (7 in all), none is a building plan, a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/2985 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Achievers Builders

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.