Not on our price list yet

Possession 31 Mar 2026 · as the developer declared it to HARERA

About this project

Key facts

Location
Faridabad
Carpet area
318–646 sq ft
In m²about 30–60 m², as declared
Registered by
ADORE BUILDTECH LLPthe company that filed it, for Adore Buildtech
Timeline
  1. 31 Mar 2026Possession, as declareddeclared to HARERA, read 29 Oct 2026
  2. 29 Aug 2026Registration valid toHARERA, read 3 Nov 2026

Homes on offer

The homes the developer declared to HARERA, by size.

854homes, 318 to 646 sq ft of carpet area
  • Under 1,000 sq ft318–646 sq ft854

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside6.088 acres in all, by use
  • Apartment buildings5.601 acres · 92%
  • Shops and offices0.487 acres · 8%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • KitchenCounter top- marble top/ KOTA stone, tiles up to 2 FT height above counter
  • Lifts2 lifts in each tower
  • FloorsVitrified tiles/ ceramic tiles
  • WallsColour WASH/ dry distemper/ oil bound distemper (OBD)
  • BathroomsPPR pipes/ CPVC pipes, CP fittings of ISI marked
  • WindowsMS- Z section/ press steel/ power coated aluminium
  • Main doorFlush doors painted with FLAT enamel paint
  • Electrical fittingsISI marked

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: SECTOR 64, VILLAGE CHANDAWALI, BALLABGARH

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Other register states: 1

Questions buyers ask

Is ADORE ANANDA registered with HARERA?From the records · HARERA, read 3 Nov 2026

HARERA lists it as HRERA-PKL-FBD-264-2021. The register’s record shows an end date of 29 Aug 2026. The register shows it as: Registration lapsed.

The source ↗
What is the possession timeline for ADORE ANANDA?From the records · HARERA, read 3 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Mar 2026. Its registration runs to 29 Aug 2026; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around ADORE ANANDA?From the records · HARERA, read 3 Nov 2026

ADORE ANANDA is in Faridabad; the site address declared to HARERA is Sector 64, Village Chandawali, Ballabgarh. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building ADORE ANANDA?From the records · HARERA, read 3 Nov 2026

ADORE ANANDA is a Adore Buildtech project, registered by its company ADORE BUILDTECH LLP.

The source ↗Adore Buildtech's projects and court record

The records

What the registers hold for ADORE ANANDA: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-FBD-264-2021: Registration lapsed. The register’s record shows an end date of 29 Aug 2026.HARERA, read 3 Nov 2026 · See it on HARERA ↗
  • Land licence 20 OF 2021 is on the DTCP register: Licence ends soon; the register prints its validity to 29 Apr 2027.DTCP, read 3 Nov 2026
The court record of Adore Buildtech’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Registration lapsed

    The register’s record shows an end date of 29 Aug 2026. HARERA Panchkula, read 3 Nov 2026. Source

  • Amber flag: Licence 20 OF 2021 ends soon

    Named in this project’s application. Valid to 29 Apr 2027. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 11 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-FBD-264-2021
Registration valid till
29 Aug 2026
Declared possession
31 Mar 2026

Declared by the promoter to HARERA

Land area
6.0875 (Acre) (24,635.24 sq m)
FAR
2.28 proposed of 2.28 permissible
licence
20 of 2021 dated 30/04/2021
Estimated project cost
₹223.00 crore
Cost of land
₹30.00 crore
Construction to start
31 Dec 2021
Completion declared for
31 Mar 2026
Declared inventory · 3 types

Declared inventory

  • Apartment/Shops/Other Buildings · 112 units · 43.1 sq m carpet · 2 towers · one flat
  • Apartment/Shops/Other Buildings · 672 units · 60 sq m carpet · 12 towers · one flat
  • Apartment/Shops/Other Buildings · 70 units · 29.56 sq m carpet · 1 tower · one flat
Statutory approvals, as declared · 1

Statutory approvals, as declared

  • I. LICENSE NO 20 OF 2021 — declared: already been obtained (30 Apr 2021)
On file with HARERA · 11 files

On file with HARERA (11)

Plans

Site plan

1 file
Approved Site Plan2 Jul 2021

Layout plan

1 file
Latest Layout Plan2 Jul 2021

Building plans

1 file
Approved Building Plans, Full Set2 Jul 2021

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule10 Jun 2021

Fire safety

1 file
Upload Fire Fighting Scheme28 Nov 2024

Land records

Land records

1 file
Revenue Record Entry of Licence and Collaboration2 Jul 2021

Money

Accounts and finance

3 files
Non-Default Certificate from a CA2 Jul 2021CA Certificate on the Application’s Figures2 Jul 2021Cash Flow Statement2 Jul 2021

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit2 Jul 2021

HARERA’s orders

HARERA’s orders

1 file
Extension Uploaded22 Apr 2026

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

20 OF 2021 · ADORE BUILDTECH LLP · FARIDABAD

Licence valid to 29 Apr 2027

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 3 Jul 2021 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 3 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

20 OF 2021: 13 parcels, 6.0875 acres in all, in Chandawali (hadbast 82), tehsil Ballabgarh.

The licence register prints the same licensed area, 6.0875 acres.

  • 13//223 marla
  • 13//23/1/210 marla
  • 13//23/2/116 marla
  • 13//23/2/210 marla
Show the other 9 parcels
  • 14//13/17 kanal 13 marla
  • 14//18/27 kanal 13 marla
  • 14//22 kanal 10 marla
  • 14//23/17 kanal 4 marla
  • 14//3/17 kanal 13 marla
  • 14//8/27 kanal 13 marla
  • 14//91 kanal
  • 14//94 kanal 10 marla
  • 25//3/3/119 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Faridabad, then the tehsil and the village: Chandawali (hadbast 82), tehsil Ballabgarh. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 13//22.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan2 Jul 2021

Layout plan

1 file
Latest Layout Plan2 Jul 2021

Building plans

1 file
Approved Building Plans, Full Set2 Jul 2021

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (11 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1637 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Adore Buildtech

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.