Skip to content

ADORE ARPANAM

by Adore Buildinfra · Faridabad

Not on our price list yet

Possession 30 Jan 2030 · as the developer declared it to HARERA

About this project

Key facts

Location
Faridabad
Carpet area
1,255–1,259 sq ft
In m²about 117–117 m², as declared
Registered by
ADORE BUILDINFRA LLPthe company that filed it, for Adore Buildinfra
Timeline
  1. 19 Sep 2025Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 30 Jan 2030Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

238homes, 1,255 to 1,259 sq ft of carpet area
  • 1,000–1,500 sq ft1,255–1,259 sq ft238

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside3.53 acres in all, by use
  • Roads0.99 acres · 28%
  • Parks and playgrounds0.97 acres · 27%
  • Other usesas the form names them: Shopping0.41 acres · 12%
  • Parking0.26 acres · 7%
  • Apartment buildings0.21 acres · 6%
  • Land for community services, handed to the government0.2 acres · 6%
  • Green belts0.17 acres · 5%
  • Pavements0.12 acres · 3%
  • Electricity sub-station0.09 acres · 3%
  • Club house0.06 acres · 2%
  • Sewage and waste treatment0.05 acres · 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • KitchenVitrified tiles (4*6) (equivalent to kajaria)
  • Lifts3 lift in each tower equivalent to johnson
  • FloorsVitrified tiles (4*6) (equivalent to kajaria)
  • WallsPOP punning with acrylic emulsion paint
  • BathroomsBranded CP fitting, WASH basin with vanity, wall-hung WCS + concealed cistern
  • WindowsUPVC or aluminium / clear glass in windows-shutters and UPVC or aluminium with frosted glass in toilets.
  • Main doorLaminated flush door (ISI marked)
  • Electrical fittingsModular switches with branded copper wiring, ceiling light, adequate lighting in all rooms/living dining and toilets dedicated space for wardrobes.DG capacity shall be at 70% of LOAD factor of individual apartment and 70 % overall diversity for total diversified LOAD of apartments as well as diversified LOAD of common areas (equivalent to anchor)

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: VILLAGE BHATOLA, SECTOR 83, FARIDABAD

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 1

Questions buyers ask

Is ADORE ARPANAM registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as HRERA-PKL-FBD-781-2025. Valid to 30 Jan 2030.

The source ↗
What is the possession timeline for ADORE ARPANAM?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 30 Jan 2030. Its registration runs to 30 Jan 2030; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around ADORE ARPANAM?From the records · HARERA, read 4 Nov 2026

ADORE ARPANAM is in Faridabad; the site address declared to HARERA is Village Bhatola, Sector 83, Faridabad. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building ADORE ARPANAM?From the records · HARERA, read 4 Nov 2026

ADORE ARPANAM is a Adore Buildinfra project, registered by its company ADORE BUILDINFRA LLP.

The source ↗Adore Buildinfra's projects and court record

The records

What the registers hold for ADORE ARPANAM: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-FBD-781-2025: Registered. Valid to 30 Jan 2030.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 71 OF 2025 is on the DTCP register, valid to 21 May 2030.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 19 Sep 2025, building plans 19 Sep 2025.Declared to HARERA, read 29 Oct 2026
The court record of Adore Buildinfra’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 10 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-FBD-781-2025
Registration valid till
30 Jan 2030
Declared possession
30 Jan 2030

Declared by the promoter to HARERA

Land area
3.53125 (Acre) (14,290.46 sq m)
FAR
2.25 proposed of 2.25 permissible
licence
71 OF 2025 DATED 22.05.2025
Estimated project cost
₹297.75 crore
Cost of land
₹100.75 crore
Layout plan, declared approved (field 5a)
19 Sept 2025
Building plans, declared approved
19 Sept 2025
Construction to start
31 Jan 2026
Completion declared for
30 Jan 2030
Declared inventory · 2 types

Declared inventory

  • Apartment/Shops/Other Buildings · 94 units · 116.92 sq m carpet · 2 towers · one flat
  • Apartment/Shops/Other Buildings · 144 units · 116.627 sq m carpet · 2 towers · one flat
Statutory approvals, as declared · 1

Statutory approvals, as declared

  • I. LICENSE NO. 71 OF 2015 — declared: already been obtained (22 May 2025)
On file with HARERA · 10 files

On file with HARERA (10)

Plans

Site plan

1 file
Approved Site Plan23 Sept 2025

Layout plan

1 file
Latest Layout Plan23 Sept 2025

Zoning plan

1 file
Zoning Plan23 Sept 2025

Demarcation plan

1 file
Demarcation Plan23 Sept 2025

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule23 Sept 2025

Money

Accounts and finance

3 files
CA Certificate on the Application’s Figures24 Sept 2025Cash Flow Statement24 Sept 2025Non-Default Certificate from a CA24 Sept 2025

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit23 Sept 2025

HARERA’s orders

HARERA’s orders

1 file
Corrigendum of Bank Account Details17 Feb 2026

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The 2 DTCP licences named on the application

71 OF 2025 · Adore Buildinfra LLP · FARIDABAD

Licence valid to 21 May 2030

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

The promoter declared 71 OF 2015. We could not match that to exactly one row on the department’s register, so nothing is claimed about it here.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 24 Sept 2025 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

71 OF 2025: 6 parcels, 3.5313 acres in all, in Bhatola (hadbast 115), tehsil Faridabad.

The licence register prints the same licensed area, 3.5313 acres.

  • 20//11/35 kanal 3 marla
  • 20//128 kanal
  • 20//131 kanal 15 marla
  • 20//198 kanal
Show the other 2 parcels
  • 20//20/14 kanal
  • 20//20/2/1/11 kanal 7 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Faridabad, then the tehsil and the village: Bhatola (hadbast 115), tehsil Faridabad. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 20//11/3.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Lenders that list this project

  • PNB Housing Finance’s approved-projects list carries “Adore Arpanam”, by M/s Adore Buildinfra LLP, code Faridabad-0526-007283, approved 2026.

    PNB Housing Finance’s own page · read 26 Oct 2026 · www.pnbhousing.com ↗

A lender’s list prints no HARERA registration or licence number, so the Bhumiq team matched it to this project by its name and builder. A listing is the lender’s record of a project it has approved for home loans, not a loan offer.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan23 Sept 2025

Layout plan

1 file
Latest Layout Plan23 Sept 2025

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (10 in all), none is a building plan, a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/3697 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Adore Buildinfra

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.