About this project

Key facts

Location
Faridabad
Carpet area
545–550 sq ft
In m²about 51–51 m², as declared
Timeline
  1. 1 Apr 2022Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 31 Dec 2027Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

664homes, 545 to 550 sq ft of carpet area
  • Under 1,000 sq ft545–550 sq ft664

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside4.469 acres in all, by use
  • Apartment buildings4.111 acres · 92%
  • Shops and offices0.358 acres · 8%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • KitchenCounter top - marble top / KOTA stone, tiles up to 2 FT height above the counter
  • Lifts2 lifts in each tower
  • FloorsVitrified tiles / ceramic tiles
  • WallsColour WASH / dry distemper / oil bound distemper (OBD)
  • BathroomsPPR pipes / CPVC pipes, CP fittings OD ISI marked
  • WindowsMS Z- section / press steel / power coated aluminium
  • Main doorFlush door painted with FLAT enamel paint
  • Electrical fittingsISI marked

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: SECTOR 84 VILLAGE KHERIKALAN

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 1

Questions buyers ask

Is ADORE LEGEND registered with HARERA?From the records · HARERA, read 3 Nov 2026

HARERA lists it as HRERA-PKL-FBD-344-2022. Valid to 31 Dec 2027.

The source ↗
What is the possession timeline for ADORE LEGEND?From the records · HARERA, read 3 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Dec 2027. Its registration runs to 31 Dec 2027; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around ADORE LEGEND?From the records · HARERA, read 3 Nov 2026

ADORE LEGEND is in Faridabad; the site address declared to HARERA is Sector 84 Village Kherikalan. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building ADORE LEGEND?From the records · HARERA, read 3 Nov 2026

ADORE LEGEND is a Singhania Infratech project.

The source ↗Singhania Infratech's projects and court record

The records

What the registers hold for ADORE LEGEND: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-FBD-344-2022: Registered. Valid to 31 Dec 2027.HARERA, read 3 Nov 2026 · See it on HARERA ↗
  • Land licence 115 OF 2021 is on the DTCP register: Licence ends soon; the register prints its validity to 22 Dec 2026.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 1 Apr 2022, building plans 1 Apr 2022.Declared to HARERA, read 29 Oct 2026
The court record of Singhania Infratech’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Licence 115 OF 2021 ends soon

    Named in this project’s application. Valid to 22 Dec 2026. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 12 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-FBD-344-2022
Registration valid till
31 Dec 2027
Declared possession
31 Dec 2027

Declared by the promoter to HARERA

Land area
4.46875 (Acre) (18,084.39 sq m)
FAR
2.28 proposed of 2.28 permissible
licence
115 of 2021
Estimated project cost
₹170.00 crore
Cost of land
₹50.00 crore
Layout plan, declared approved (field 5a)
1 Apr 2022
Building plans, declared approved
1 Apr 2022
Construction to start
31 Aug 2022
Completion declared for
31 Dec 2027
Declared inventory · 5 types

Declared inventory

  • Apartment/Shops/Other Buildings · 56 units · 51.076 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 82 units · 50.595 sq m carpet · 6 towers · one flat
  • Apartment/Shops/Other Buildings · 82 units · 50.952 sq m carpet · 6 towers · one flat
  • Apartment/Shops/Other Buildings · 222 units · 50.615 sq m carpet · 11 towers · one flat
  • Apartment/Shops/Other Buildings · 222 units · 50.97 sq m carpet · 11 towers · one flat
Statutory approvals, as declared · 2

Statutory approvals, as declared

  • I. LICENSE NO 115 OF 2021 — declared: already been obtained (23 Dec 2021)
  • II. BUILDING PLAN — declared: already been obtained (1 Apr 2022)
On file with HARERA · 12 files

On file with HARERA (12)

Plans

Site plan

1 file
Approved Site Plan12 Apr 2022

Layout plan

1 file
Latest Layout Plan12 Apr 2022

Zoning plan

1 file
Zoning Plan12 Apr 2022

Demarcation plan

1 file
Demarcation Plan9 Apr 2022

Building plans

1 file
Approved Building Plans, Full Set12 Apr 2022

Services

Service plans

1 file
Service Plans on the Layout12 Apr 2022

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule12 Apr 2022

Land records

Land records

1 file
Revenue Record Entry of Licence and Collaboration12 Apr 2022

Money

Accounts and finance

3 files
Non-Default Certificate from a CA12 Apr 2022CA Certificate on the Application’s Figures12 Apr 2022Cash Flow Statement12 Apr 2022

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit13 Apr 2022

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

115 OF 2021 · Ms Singhania Ifratech · FARIDABAD

Licence valid to 22 Dec 2026

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 13 Apr 2022 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 3 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

115 OF 2021: 6 parcels, 4.4688 acres in all, in Kheri kalan (hadbast 113), tehsil Faridabad.

The licence register prints the same licensed area, 4.4688 acres.

  • 20//22/24 kanal
  • 20//23/24 kanal
  • 29//28 kanal
  • 29//38 kanal
Show the other 2 parcels
  • 29//88 kanal
  • 29//9/13 kanal 15 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Faridabad, then the tehsil and the village: Kheri kalan (hadbast 113), tehsil Faridabad. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 20//22/2.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan12 Apr 2022

Layout plan

1 file
Latest Layout Plan12 Apr 2022

Building plans

1 file
Approved Building Plans, Full Set12 Apr 2022

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (12 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1919 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Singhania Infratech

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.