Key facts

Location
Faridabad
Carpet area
511–517 sq ft
In m²about 47–48 m², as declared
Registered by
ADORE PROPINFRA LLPthe company that filed it, for Adore Propinfra
Timeline
  1. 24 Apr 2024Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 11 Nov 2028Registration valid toHARERA, read 3 Nov 2026
  3. 11 Dec 2028Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

1,380homes, 511 to 517 sq ft of carpet area
  • Under 1,000 sq ft511–517 sq ft1,380

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside9.038 acres in all, by use
  • Apartment buildings2.545 acres · 28%
  • Roads2.058 acres · 23%
  • Pavements2.058 acres · 23%
  • Parks and playgrounds1.656 acres · 18%
  • Shops and offices0.392 acres · 4%
  • Club house0.131 acres · 1%
  • Electricity sub-station0.103 acres · 1%
  • Other uses0.095 acres · 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • KitchenCounter top - marble top/ KOTA stone, tile up to 2 FEET height above the counter
  • Kitchen appliancesISI marked
  • Lifts2 lift in each tower
  • FloorsVitrified tiles/ ceramic tiles
  • WallsColour WASH/ dry distemper/ oil bound distemper (OBD)
  • BathroomsPPR pipes/ CPVC pipes, CP fitting OD ISI marked
  • WindowsMS Z- section / press steel / power coasted aluminum
  • Main doorFlush door painted with FLAT enamel paint

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: VILLAGE TIGAON, SECTOR 104, FARIDABAD

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 1

Questions buyers ask

Is ADORE LEGEND III registered with HARERA?From the records · HARERA, read 3 Nov 2026

HARERA lists it as HRERA-PKL-FBD-595-2024. Valid to 11 Nov 2028.

The source ↗
What is the possession timeline for ADORE LEGEND III?From the records · HARERA, read 3 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 11 Dec 2028. Its registration runs to 11 Nov 2028; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around ADORE LEGEND III?From the records · HARERA, read 3 Nov 2026

ADORE LEGEND III is in Faridabad; the site address declared to HARERA is Village Tigaon, Sector 104, Faridabad. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building ADORE LEGEND III?From the records · HARERA, read 3 Nov 2026

ADORE LEGEND III is a Adore Propinfra project, registered by its company ADORE PROPINFRA LLP.

The source ↗Adore Propinfra's projects and court record

The records

What the registers hold for ADORE LEGEND III: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-FBD-595-2024: Registered. Valid to 11 Nov 2028.HARERA, read 3 Nov 2026 · See it on HARERA ↗
  • Land licence 262 OF 2023 is on the DTCP register, valid to 11 Dec 2028.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 24 Apr 2024, building plans 24 Apr 2024.Declared to HARERA, read 29 Oct 2026
The court record of Adore Propinfra’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 10 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-FBD-595-2024
Registration valid till
11 Nov 2028
Declared possession
11 Dec 2028

Declared by the promoter to HARERA

Land area
9.0375 (Acre) (36,573.46 sq m)
FAR
1.78 proposed of 1.78 permissible
licence
License No 262 of 2023 dated 12.12.2023 (valid upto 11.12.2028)
Estimated project cost
₹339.30 crore
Cost of land
₹88.30 crore
Layout plan, declared approved (field 5a)
24 Apr 2024
Building plans, declared approved
24 Apr 2024
Construction to start
1 Aug 2024
Completion declared for
11 Dec 2028
Declared inventory · 3 types

Declared inventory

  • Apartment/Shops/Other Buildings · 1,122 units · 47.868 sq m carpet · 29 towers · one flat
  • Apartment/Shops/Other Buildings · 42 units · 48.007 sq m carpet · 2 towers · one flat
  • Apartment/Shops/Other Buildings · 216 units · 47.507 sq m carpet · 9 towers · one flat
Statutory approvals, as declared · 4

Statutory approvals, as declared

  • I. LICENSE NO 262 OF 2023 — declared: already been obtained (12 Dec 2023)
  • II. BUILDING PLAN — declared: already been obtained (24 Apr 2024)
  • III. DEMARCATION PLAN — declared: already been obtained (13 Oct 2023)
  • IV. ZONING PLAN — declared: already been obtained (13 Dec 2023)
On file with HARERA · 10 files

On file with HARERA (10)

Plans

Site plan

1 file
Approved Site Plan8 May 2024

Layout plan

1 file
Latest Layout Plan8 May 2024

Zoning plan

1 file
Zoning Plan8 May 2024

Demarcation plan

1 file
Demarcation Plan8 May 2024

Building plans

1 file
Approved Building Plans, Full Set8 May 2024

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule7 May 2024

Money

Accounts and finance

3 files
Change of bank account details updated12 Nov 2024Non-Default Certificate from a CA8 May 2024CA Certificate on the Application’s Figures8 May 2024

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit8 May 2024

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

262 OF 2023 · Adore Propinfra LLP · FARIDABAD

Licence valid to 11 Dec 2028

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 8 May 2024 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 3 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

262 OF 2023: 12 parcels, 9.0375 acres in all, in Tigaon (hadbast 095), tehsil Tigaon.

The licence register prints the same licensed area, 9.0375 acres.

  • 19//6/11 kanal 10 marla
  • 18//1/26 kanal 3 marla
  • 18//108 kanal
  • 18//118 kanal
Show the other 8 parcels
  • 18//12/15 kanal 7 marla
  • 18//28 kanal
  • 18//97 kanal 9 marla
  • 8//19/25 kanal 1 marla
  • 8//201 kanal 3 marla
  • 8//21/25 kanal 13 marla
  • 8//228 kanal
  • 8//238 kanal

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Faridabad, then the tehsil and the village: Tigaon (hadbast 095), tehsil Tigaon. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 19//6/1.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan8 May 2024

Layout plan

1 file
Latest Layout Plan8 May 2024

Building plans

1 file
Approved Building Plans, Full Set8 May 2024

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (10 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/2929 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Adore Propinfra

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.