Skip to content

AFFORDABLE GROUP HOUSING COLONY TERRA LAVINIUM

by Iris Plaza · Faridabad

Not on our price list yet

Possession 3 Oct 2022 · as the developer declared it to HARERA

About this project

Key facts

Location
Faridabad
Carpet area
498–641 sq ft
In m²about 46–60 m², as declared
Registered by
IRIS PLAZA PRIVATE LIMITEDthe company that filed it, for Iris Plaza
Timeline
  1. 3 Oct 2022Possession, as declareddeclared to HARERA, read 29 Oct 2026
  2. 31 Mar 2024Registration valid toHARERA, read 3 Nov 2026

Homes on offer

The homes the developer declared to HARERA, by size.

764homes, 498 to 641 sq ft of carpet area
  • Under 1,000 sq ft498–641 sq ft764

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside24,129 m² in all, by use
  • Other usesas the form names them: Area under road widening7,624 m² · 32%
  • Apartment buildings4,547 m² · 19%
  • Roads3,608 m² · 15%
  • Parking3,039 m² · 13%
  • Pavements2,616 m² · 11%
  • Parks and playgrounds1,272 m² · 5%
  • Sewage and waste treatment600 m² · 2%
  • Green belts531 m² · 2%
  • Club house192 m² · under 1%
  • Electricity sub-station100 m² · under 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • KitchenAs per details given below
  • Lifts2 lifts in each tower
  • WardrobesNo cupboard
  • FloorsAs per details given below
  • WallsAs per details given below
  • BathroomsAs per details given below
  • Windows5 MM thick
  • Main doorFlush doors

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: SECTOR-75, VILLAGE BADOLI, FARIDABAD

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Other register states: 1

Questions buyers ask

Is AFFORDABLE GROUP HOUSING COLONY TERRA LAVINIUM registered with HARERA?From the records · HARERA, read 3 Nov 2026

HARERA lists it as HRERA-PKL-FBD- 8-2018. The register’s record shows an end date of 31 Mar 2024. The register shows it as: Registration lapsed.

The source ↗
What is the possession timeline for AFFORDABLE GROUP HOUSING COLONY TERRA LAVINIUM?From the records · HARERA, read 3 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 3 Oct 2022. Its registration runs to 31 Mar 2024; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around AFFORDABLE GROUP HOUSING COLONY TERRA LAVINIUM?From the records · HARERA, read 3 Nov 2026

AFFORDABLE GROUP HOUSING COLONY TERRA LAVINIUM is in Faridabad; the site address declared to HARERA is Sector-75, Village Badoli, Faridabad. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building AFFORDABLE GROUP HOUSING COLONY TERRA LAVINIUM?From the records · HARERA, read 3 Nov 2026

AFFORDABLE GROUP HOUSING COLONY TERRA LAVINIUM is a Iris Plaza project, registered by its company IRIS PLAZA PRIVATE LIMITED.

The source ↗Iris Plaza's projects and court record

The records

What the registers hold for AFFORDABLE GROUP HOUSING COLONY TERRA LAVINIUM: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-FBD- 8-2018: Registration lapsed. The register’s record shows an end date of 31 Mar 2024.HARERA, read 3 Nov 2026 · See it on HARERA ↗
  • Land licence 79 OF 2017 is on the DTCP register: Licence lapsed; the register prints its validity to 3 Mar 2025.DTCP, read 3 Nov 2026
The court record of Iris Plaza’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Licence 79 OF 2017 lapsed

    Named in this project’s application. Valid to 3 Mar 2025; no renewal on record. DTCP Haryana register, read 3 Nov 2026. Source

  • Amber flag: Registration lapsed

    The register’s record shows an end date of 31 Mar 2024. HARERA Panchkula, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 9 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-FBD- 8-2018
Registration valid till
31 Mar 2024
Declared possession
3 Oct 2022

Declared by the promoter to HARERA

Land area
5.9625 (Acre) (24,129.38 sq m)
FAR
2.25 proposed of 2.25 permissible
licence
79 of 2017
Estimated project cost
₹143.00 crore
Cost of land
₹11.02 crore
Construction to start
1 Jun 2018
Completion declared for
3 Oct 2022
Declared inventory · 2 types

Declared inventory

  • Apartment/Shops/Other Buildings · 372 units · 46.305 sq m carpet · 7 towers · one flat
  • Apartment/Shops/Other Buildings · 392 units · 59.521 sq m carpet · 7 towers · one flat
Statutory approvals, as declared · 3

Statutory approvals, as declared

  • I. ENVIORNMENT CLEARANCE — declared: already been obtained
  • II. NOC FROM AIRPORT AUTHORITY — declared: already been obtained
  • III. FIRE NOC — declared: already been obtained
On file with HARERA · 9 files

On file with HARERA (9)

Plans

Site plan

1 file
Approved Site Plan23 May 2019

Layout plan

1 file
Latest Layout Plan31 May 2019

Zoning plan

1 file
Zoning Plan23 May 2019

Demarcation plan

1 file
Demarcation Plan31 May 2019

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule7 May 2019

Money

Accounts and finance

2 files
Change of bank account details updated12 Nov 2024Non-Default Certificate from a CA7 Jun 2019

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit23 May 2019

HARERA’s orders

HARERA’s orders

1 file
Extension RC Uploaded1 Oct 2024

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

79 OF 2017 · Iris Plaza Pvt Ltd · FARIDABAD

Licence valid to 3 Mar 2025

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 28 Jun 2019 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 3 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

79 OF 2017: 15 parcels, 5.9625 acres in all, in Baroli (hadbast 116), tehsil Faridabad.

The licence register prints the same licensed area, 5.9625 acres.

  • 45//13/2/2/31 kanal 17 marla
  • 45//14/26 kanal 3 marla
  • 45//15/32 kanal 11 marla
  • 45//15/44 marla
Show the other 11 parcels
  • 45//16/15 kanal 7 marla
  • 45//16/22 kanal 6 marla
  • 45//16/37 marla
  • 45//17/11 kanal 1 marla
  • 45//17/26 kanal 19 marla
  • 45//18/1/13 kanal 2 marla
  • 45//23/1/2/21 kanal 17 marla
  • 45//23/212 marla
  • 45//247 kanal 9 marla
  • 45//25/16 marla
  • 45//25/27 kanal 13 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Faridabad, then the tehsil and the village: Baroli (hadbast 116), tehsil Faridabad. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 45//13/2/2/3.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan23 May 2019

Layout plan

1 file
Latest Layout Plan31 May 2019

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (9 in all), none is a building plan, a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/387 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Iris Plaza

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.