AFFORDABLE RESIDENTIAL PLOTTED COLONY ON AREA 10.0375 ACRES

by Jbg Buildcon · Jhajjar

Not on our price list yet

About this project

Key facts

Registered by
JBG BUILCON PRIVATE LIMITEDthe company that filed it, for Jbg Buildcon
Timeline
  1. 22 Dec 2020Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 4 Jul 2024Registration valid toHARERA, read 4 Nov 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside10.046 acres in all, by use
  • Plots for sale5.118 acres · 51%
  • Other uses2.826 acres · 28%
  • Club house1.004 acres · 10%
  • Green belts0.873 acres · 9%
  • Roads0.225 acres · 2%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: SARAI AURANGABAD, SECTOR 3A TEHSIL BAHADURGARH

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 1

Questions buyers ask

Is AFFORDABLE RESIDENTIAL PLOTTED COLONY ON AREA 10.0375 ACRES registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as HRERA-PKL-JJR-18-2018. The register’s record shows an end date of 4 Jul 2024. The register shows it as: Registration lapsed.

The source ↗
How is the connectivity around AFFORDABLE RESIDENTIAL PLOTTED COLONY ON AREA 10.0375 ACRES?From the records · HARERA, read 4 Nov 2026

AFFORDABLE RESIDENTIAL PLOTTED COLONY ON AREA 10.0375 ACRES is in Jhajjar; the site address declared to HARERA is Sarai Aurangabad, Sector 3a Tehsil Bahadurgarh. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building AFFORDABLE RESIDENTIAL PLOTTED COLONY ON AREA 10.0375 ACRES?From the records · HARERA, read 4 Nov 2026

AFFORDABLE RESIDENTIAL PLOTTED COLONY ON AREA 10.0375 ACRES is a Jbg Buildcon project, registered by its company JBG BUILCON PRIVATE LIMITED.

The source ↗Jbg Buildcon's projects and court record
What protections do I have as a buyer?General guidance

Under the RERA Act, a registered project has to keep most of the money buyers pay in a separate bank account for that project, sell by carpet area, and stick to the plans it registered unless enough buyers agree to a change. If possession is late, a buyer can ask HARERA for interest or a refund. How this applies to your own purchase depends on your agreement, so ask a lawyer before you sign.

The records

What the registers hold for AFFORDABLE RESIDENTIAL PLOTTED COLONY ON AREA 10.0375 ACRES: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-JJR-18-2018: Registration lapsed. The register’s record shows an end date of 4 Jul 2024.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 68 OF 2017 is on the DTCP register: Licence lapsed; the register prints its validity to 21 Aug 2024.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 22 Dec 2020.Declared to HARERA, read 29 Oct 2026
The court record of Jbg Buildcon’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Licence 68 OF 2017 lapsed

    Named in this project’s application. Valid to 21 Aug 2024; the register’s note: “Migrated from LC-866 (271 of 2007)”. DTCP Haryana register, read 3 Nov 2026. Source

  • Amber flag: Registration lapsed

    The register’s record shows an end date of 4 Jul 2024. HARERA Panchkula, read 4 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 8 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-JJR-18-2018
Registration valid till
4 Jul 2024

Declared by the promoter to HARERA

Land area
10.0375 (Acre) (40,620.32 sq m)
FAR
1.51 proposed of 5.04 permissible
licence
68 of 2017 (22/08/2017)
Estimated project cost
₹3.50 crore
Cost of land
₹2.40 crore
Layout plan, declared approved (field 5a)
22 Dec 2020
Statutory approvals, as declared · 1

Statutory approvals, as declared

  • I. YES — declared: already been obtained (22 Aug 2017)
On file with HARERA · 8 files

On file with HARERA (8)

Plans

Site plan

1 file
Approved Site Plan21 Feb 2021

Layout plan

1 file
Latest Layout Plan21 Feb 2021

Zoning plan

1 file
Zoning Plan21 Feb 2021

Approvals and clearances

Completion certificate (CC)

1 file
Completion Certificate14 Sept 2026

DTCP licence

1 file
Licence Copy with Land Schedule20 Feb 2021

Money

Accounts and finance

1 file
Non-Default Certificate from a CA21 Feb 2021

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit21 Feb 2021

HARERA’s orders

HARERA’s orders

1 file
Extension Uploaded14 Sept 2026

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

68 OF 2017 · JBG Buildcon Pvt Ltd · Jhajjar

Licence valid to 21 Aug 2024

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 21 Feb 2021 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

68 OF 2017: 19 parcels, 10.0375 acres in all, in Sarai Aurangabad (hadbast 44), tehsil Bahadurgarh.

The licence register prints the same licensed area, 10.0375 acres.

  • 6//22/23 kanal 9 marla
  • 6//23/23 kanal 15 marla
  • 6//248 kanal
  • 6//257 kanal 8 marla
Show the other 15 parcels
  • 6//27/15 marla
  • 6//27/25 marla
  • 5//208 kanal
  • 5//21/13 kanal 10 marla
  • 11//27 kanal 8 marla
  • 11//38 kanal
  • 11//4/12 kanal 2 marla
  • 11//4/25 kanal 18 marla
  • 11//57 kanal 19 marla
  • 12//1/15 marla
  • 12//1/23 kanal 15 marla
  • 12//1/22 kanal
  • 12//10/12 kanal 7 marla
  • 12//2/15 kanal 10 marla
  • 12//2610 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Jhajjar, then the tehsil and the village: Sarai Aurangabad (hadbast 44), tehsil Bahadurgarh. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 6//22/2.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan21 Feb 2021

Layout plan

1 file
Latest Layout Plan21 Feb 2021

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (8 in all), none is a building plan, a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1560 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Jbg Buildcon

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.