Skip to content

ANAND LOK (SONIPAT-11.45625 ACRES) DDJAY

by Ansal Properties & Infrastructure · Sonipat

Not on our price list yet

Possession 13 Sep 2024 · as the developer declared it to HARERA

About this project

Key facts

Registered by
ANSAL PROPERTIES AND INFRASTRUCTURE LIMITEDthe company that filed it, for Ansal Properties & Infrastructure
Timeline
  1. 14 Sep 2019Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 13 Sep 2024Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside11.456 acres in all, by use
  • Plots for sale6.421 acres · 56%
  • Roads2.565 acres · 22%
  • Land for community services, handed to the government1.15 acres · 10%
  • Parks and playgrounds0.87 acres · 8%
  • Shops and offices0.45 acres · 4%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: VILLAGE AKBARPUR BAROTA, JHATERI ROAD, SECTOR 35

The builder

Its 22 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 2
  • Registered, no OC or CC yet: 2
  • Other register states: 18

Questions buyers ask

Is ANAND LOK (SONIPAT-11.45625 ACRES) DDJAY registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as HRERA-PKL-SNP-201-2020. The register’s record shows an end date of 13 Sep 2024. The register shows it as: Registration lapsed.

The source ↗
What is the possession timeline for ANAND LOK (SONIPAT-11.45625 ACRES) DDJAY?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 13 Sep 2024. Its registration runs to 13 Sep 2024; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around ANAND LOK (SONIPAT-11.45625 ACRES) DDJAY?From the records · HARERA, read 4 Nov 2026

ANAND LOK (SONIPAT-11.45625 ACRES) DDJAY is in Sonipat; the site address declared to HARERA is Village Akbarpur Barota, Jhateri Road, Sector 35. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building ANAND LOK (SONIPAT-11.45625 ACRES) DDJAY?From the records · HARERA, read 4 Nov 2026

ANAND LOK (SONIPAT-11.45625 ACRES) DDJAY is a Ansal Properties & Infrastructure project, registered by its company ANSAL PROPERTIES AND INFRASTRUCTURE LIMITED.

The source ↗Ansal Properties & Infrastructure's projects and court record

The records

What the registers hold for ANAND LOK (SONIPAT-11.45625 ACRES) DDJAY: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-SNP-201-2020: Registration lapsed. The register’s record shows an end date of 13 Sep 2024.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 120 OF 2019 is on the DTCP register: Licence lapsed; the register prints its validity to 13 Sep 2024.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 14 Sep 2019.Declared to HARERA, read 29 Oct 2026
The court record of Ansal Properties & Infrastructure’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Licence 120 OF 2019 lapsed

    Named in this project’s application. Valid to 13 Sep 2024; no renewal on record. DTCP Haryana register, read 3 Nov 2026. Source

  • Amber flag: Registration lapsed

    The register’s record shows an end date of 13 Sep 2024. HARERA Panchkula, read 4 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 5 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-SNP-201-2020
Registration valid till
13 Sept 2024
Declared possession
13 Sept 2024

Declared by the promoter to HARERA

Land area
11.45625 (Acre) (46,361.8 sq m)
FAR
1 proposed of 1.75 permissible
licence
LICENSE NO. 120 OF 2019 DATED 14.09.2019 VALID UPTO 13.09.2024.
Estimated project cost
₹17.31 crore
Cost of land
₹1.91 crore
Layout plan, declared approved (field 5a)
14 Sept 2019
Construction to start
1 Oct 2020
Completion declared for
13 Sept 2024
Statutory approvals, as declared · 1

Statutory approvals, as declared

  • I. LICENSE NO. 120 OF 2019 — declared: already been obtained (14 Sept 2019)
On file with HARERA · 5 files

On file with HARERA (5)

Plans

Site plan

1 file
Approved Site Plan13 May 2020

Layout plan

1 file
Latest Layout Plan13 May 2020

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule13 May 2020

Money

Accounts and finance

1 file
Non-Default Certificate from a CA15 May 2020

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit16 May 2020

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

120 OF 2019 · Ansal Properties & Infrastructure Ltd · Sonipat

Licence valid to 13 Sept 2024

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 16 May 2020 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

120 OF 2019: 30 parcels, 11.4562 acres in all, in Akbarpur barota (hadbast 62), tehsil Rai.

The licence register prints the same licensed area, 11.4563 acres.

  • 10//15 MIN2 kanal 15 marla
  • 10//168 kanal
  • 10//17/12 kanal
  • 10//24/2/21 kanal 8 marla
Show the other 26 parcels
  • 10//24/3/24 kanal 9 marla
  • 10//258 kanal
  • 9//11 MIN1 marla
  • 9//19 MIN1 marla
  • 9//20 MIN6 kanal 15 marla
  • 9//21 MIN5 kanal 11 marla
  • 9//22 MIN2 marla
  • 16//12/2/2/12 marla
  • 16//12/2/2/21 kanal 13 marla
  • 16//13/2/1 MIN2 kanal
  • 16//13/2/2/1 MIN1 kanal
  • 16//13/2/2/2 MIN3 kanal 14 marla
  • 16//18/26 kanal 12 marla
  • 16//19/15 kanal 16 marla
  • 16//21/2/215 marla
  • 16//22/1/24 kanal
  • 16//23/1 MIN1 kanal 15 marla
  • 16//267 marla
  • 16//3/2/21 kanal 13 marla
  • 16//3/2/21 marla
  • 16//47 kanal 12 marla
  • 16//5 MIN3 kanal 10 marla
  • 16//6 MIN6 marla
  • 16//7 MIN3 kanal
  • 16//8/1 MIN5 kanal
  • 17//1/1 MIN3 kanal 15 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Sonipat, then the tehsil and the village: Akbarpur barota (hadbast 62), tehsil Rai. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 10//15 MIN.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan13 May 2020

Layout plan

1 file
Latest Layout Plan13 May 2020

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (5 in all), none is a building plan, a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1361 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Ansal Properties & Infrastructure

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.