Key facts

Location
Fatehabad
Timeline
  1. 26 Aug 2022Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 31 Dec 2026Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside36.188 acres in all, by use
  • Plots for sale17.035 acres · 47%
  • Roads13.12 acres · 36%
  • Parks and playgrounds5.183 acres · 14%
  • Other uses0.702 acres · 2%
  • Sewage and waste treatment0.148 acres · under 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: SECTOR - 8, FATEHABAD

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 1

Questions buyers ask

Is ARUNODAYA registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as HRERA-PKL-FTB-371-2022. Valid to 31 Dec 2026.

The source ↗
What is the possession timeline for ARUNODAYA?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Dec 2026. Its registration runs to 31 Dec 2026; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around ARUNODAYA?From the records · HARERA, read 4 Nov 2026

ARUNODAYA is in Fatehabad; the site address declared to HARERA is Sector - 8, Fatehabad. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building ARUNODAYA?From the records · HARERA, read 4 Nov 2026

The records

What the registers hold for ARUNODAYA: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-FTB-371-2022: Registered. Valid to 31 Dec 2026.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 132 OF 2022 is on the DTCP register, valid to 25 Aug 2027.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 26 Aug 2022.Declared to HARERA, read 29 Oct 2026
The court record of Shiva Homes’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Registration ends soon

    Valid to 31 Dec 2026. HARERA Panchkula, read 4 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 5 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-FTB-371-2022
Registration valid till
31 Dec 2026
Declared possession
31 Dec 2026

Declared by the promoter to HARERA

Land area
36.1875 (Acre) (1,46,445.62 sq m)
FAR
the application prints 53.2, which is not a ratio
licence
132 of 2022
Estimated project cost
₹53.51 crore
Layout plan, declared approved (field 5a)
26 Aug 2022
Construction to start
1 Sept 2022
Completion declared for
31 Dec 2026
Statutory approvals, as declared · 4

Statutory approvals, as declared

  • I. LAYOUT PLAN — declared: already been obtained (26 Aug 2022)
  • II. DEMARCATION PLAN — declared: applied for but yet to receive
  • III. ZONING PLAN — declared: applied for but yet to receive
  • IV. SERVICE PLAN ESTIMATE — declared: yet to file for approval
On file with HARERA · 5 files

On file with HARERA (5)

Plans

Site plan

1 file
Approved Site Plan30 Aug 2022

Layout plan

1 file
Latest Layout Plan30 Aug 2022

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule30 Aug 2022

Money

Accounts and finance

1 file
Non-Default Certificate from a CA30 Aug 2022

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit30 Aug 2022

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

132 OF 2022 · Shiva Homes · Fatehabad

Licence valid to 25 Aug 2027

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 30 Aug 2022 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

132 OF 2022: 41 parcels, 36.1875 acres in all, in Matana (hadbast 192), tehsil Fatehabad.

The licence register prints the same licensed area, 36.1875 acres.

  • 244//211 kanal 8 marla
  • 262//17 kanal 12 marla
  • 262//107 kanal 12 marla
  • 262//117 kanal 12 marla
Show the other 37 parcels
  • 262//127 kanal 8 marla
  • 262//197 kanal 8 marla
  • 262//22 kanal 18 marla
  • 262//207 kanal 12 marla
  • 262//21/15 kanal 16 marla
  • 262//21/21 kanal 16 marla
  • 262//227 kanal 19 marla
  • 262//97 kanal 8 marla
  • 263//158 kanal
  • 263//168 kanal
  • 263//238 kanal
  • 263//248 kanal
  • 263//258 kanal
  • 263//58 kanal
  • 263//68 kanal
  • 281//14/26 kanal 5 marla
  • 281//158 kanal
  • 281//168 kanal
  • 281//38 kanal
  • 281//48 kanal
  • 281//58 kanal
  • 281//68 kanal
  • 281//77 kanal 18 marla
  • 281//87 kanal 7 marla
  • 282//18 kanal
  • 282//108 kanal
  • 282//118 kanal
  • 282//128 kanal
  • 282//138 kanal
  • 282//18/13 kanal 11 marla
  • 282//198 kanal
  • 282//28 kanal
  • 282//208 kanal
  • 282//37 kanal
  • 282//31 kanal
  • 282//88 kanal
  • 282//98 kanal

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Fatehabad, then the tehsil and the village: Matana (hadbast 192), tehsil Fatehabad. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 244//21.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan30 Aug 2022

Layout plan

1 file
Latest Layout Plan30 Aug 2022

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (5 in all), none is a building plan, a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/2099 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Shiva Homes

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.