Key facts

Registered by
SAHIBA CONSTRUCTIONS PVT LTDthe company that filed it, for Sahiba Constructions
Timeline
  1. 6 Mar 2017Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 30 Jun 2022Registration valid toHARERA, read 4 Nov 2026

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: SECTOR 19

The builder

Its 2 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 1
  • Other register states: 1

Questions buyers ask

Is BASANT VIHAR registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as HRERA-PKL-JND-242-2021. The register’s record shows an end date of 30 Jun 2022. The register shows it as: Registration lapsed.

The source ↗
How is the connectivity around BASANT VIHAR?From the records · HARERA, read 4 Nov 2026

BASANT VIHAR is in Jind; the site address declared to HARERA is Sector 19. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building BASANT VIHAR?From the records · HARERA, read 4 Nov 2026

BASANT VIHAR is a Sahiba Constructions project, registered by its company SAHIBA CONSTRUCTIONS PVT LTD.

The source ↗Sahiba Constructions's projects and court record
What protections do I have as a buyer?General guidance

Under the RERA Act, a registered project has to keep most of the money buyers pay in a separate bank account for that project, sell by carpet area, and stick to the plans it registered unless enough buyers agree to a change. If possession is late, a buyer can ask HARERA for interest or a refund. How this applies to your own purchase depends on your agreement, so ask a lawyer before you sign.

The records

What the registers hold for BASANT VIHAR: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-JND-242-2021: Registration lapsed. The register’s record shows an end date of 30 Jun 2022.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 243 OF 2007 is on the DTCP register: Licence lapsed; the register prints its validity to 24 Oct 2024.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 6 Mar 2017.Declared to HARERA, read 29 Oct 2026
The court record of Sahiba Constructions’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Licence 243 OF 2007 lapsed

    Named in this project’s application. Valid to 24 Oct 2024; no renewal on record. DTCP Haryana register, read 3 Nov 2026. Source

  • Red flag: Licence 57 OF 2011 lapsed

    Named in this project’s application. Valid to 22 Jun 2024; the register’s note: “0.6185 acres migrated to DDJAY (43 OF 2017) dt. 10-07-2017”. DTCP Haryana register, read 3 Nov 2026. Source

  • Red flag: Licence 65 OF 2011 lapsed

    Named in this project’s application. Valid to 20 Jul 2024; the register’s note: “7.637 acres migrated to DDJAY (43 OF 2017) dt. 10-07-2017”. DTCP Haryana register, read 3 Nov 2026. Source

  • Amber flag: Registration lapsed

    The register’s record shows an end date of 30 Jun 2022. HARERA Panchkula, read 4 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 12 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-JND-242-2021
Registration valid till
30 Jun 2022

Declared by the promoter to HARERA

Land area
36.77925 (Acre) (1,48,840.34 sq m)
FAR
the application prints 51, which is not a ratio
licence
LICENSE NO 243 OF 2007, 57 OF 2011, 65 OF 2011
Estimated project cost
₹23.47 crore
Cost of land
₹3.24 crore
Layout plan, declared approved (field 5a)
6 Mar 2017
Statutory approvals, as declared · 1

Statutory approvals, as declared

  • I. COMPLETION OF THE PROJECT — declared: yet to file for approval
On file with HARERA · 12 files

On file with HARERA (12)

Plans

Site plan

1 file
Approved Site Plan14 Feb 2020

Layout plan

1 file
Latest Layout Plan14 Feb 2020

Zoning plan

1 file
Zoning Plan14 Feb 2020

Demarcation plan

1 file
Demarcation Plan14 Feb 2020

Building plans

1 file
Approved Building Plans, Full Set14 Feb 2020

Services

Service plans

1 file
Service Plans on the Layout14 Feb 2020

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule14 Feb 2020

Land records

Land records

1 file
Revenue Record Entry of Licence and Collaboration14 Feb 2020

Money

Accounts and finance

3 files
Cash Flow Statement14 Feb 2020CA Certificate on the Application’s Figures14 Feb 2020Non-Default Certificate from a CA14 Feb 2020

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit14 Feb 2020

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The 3 DTCP licences named on the application

243 OF 2007 · Sahiba Construction Pvt. Ltd. · Jind

Licence valid to 24 Oct 2024

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

57 OF 2011 · Sahiba Construction Pvt. Ltd. · Jind

Licence valid to 22 Jun 2024

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

65 OF 2011 · Sahiba Construction Pvt. Ltd. · Jind

Licence valid to 20 Jul 2024

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 14 Feb 2020 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Land under the 3 licences

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

243 OF 2007: 37 parcels, 25.2937 acres in all, in Narwana (hadbast 73), tehsil Narwana.

The licence register prints the same licensed area, 25.294 acres.

  • 297//15/24 kanal 13 marla
  • 297//168 kanal
  • 297//178 kanal
  • 297//247 kanal 11 marla
Show the other 33 parcels
  • 297//257 kanal 11 marla
  • 298//11/1/22 kanal 6 marla
  • 298//11/2/22 kanal 11 marla
  • 298//12/1/21 kanal 17 marla
  • 298//208 kanal
  • 298//217 kanal 11 marla
  • 302//18 kanal
  • 302//108 kanal
  • 303//15/14 kanal
  • 303//5/15 kanal 8 marla
  • 303//68 kanal
  • 303//48 kanal
  • 303//5/22 kanal 12 marla
  • 303//7/17 kanal 11 marla
  • 302//118 kanal
  • 302//19/21 kanal 13 marla
  • 302//207 kanal 15 marla
  • 303//15/24 kanal
  • 303//168 kanal
  • 303//17/14 kanal
  • 302//21/14 kanal 3 marla
  • 303//17/24 kanal
  • 303//188 kanal
  • 303//23/23 kanal 9 marla
  • 303//256 kanal 18 marla
  • 303//21/2 min1 kanal 16 marla
  • 303//23/13 kanal 9 marla
  • 303//22/5/2/23 kanal 18 marla
  • 303//148 kanal
  • 303//19/27 kanal 17 marla
  • 303//20/218 marla
  • 304//16/2 min2 marla
  • 303//246 kanal 18 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

57 OF 2011: 10 parcels, 7.2625 acres in all, in Narwana (hadbast 73), tehsil Narwana.

The licence register prints the same licensed area, 7.2625 acres.

  • 302//21/21 kanal 10 marla
  • 302//22 min2 kanal 2 marla
  • 336//4/21 kanal 12 marla
  • 336//58 kanal
Show the other 6 parcels
  • 336//68 kanal
  • 337//18 kanal
  • 337//28 kanal
  • 337//8/24 kanal 18 marla
  • 337//98 kanal
  • 337//108 kanal

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

65 OF 2011: 10 parcels, 4.225 acres in all, in Narwana (hadbast 73), tehsil Narwana.

The licence register prints the same licensed area, 4.225 acres.

  • 302//139 marla
  • 298//188 kanal
  • 298//193 kanal 18 marla
  • 298//222 kanal 15 marla
Show the other 6 parcels
  • 298//233 kanal 11 marla
  • 302//123 kanal 2 marla
  • 302//183 kanal 3 marla
  • 302//19/13 kanal 2 marla
  • 302//22 kanal 18 marla
  • 302//92 kanal 18 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Jind, then the tehsil and the village: Narwana (hadbast 73), tehsil Narwana. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 297//15/2.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan14 Feb 2020

Layout plan

1 file
Latest Layout Plan14 Feb 2020

Building plans

1 file
Approved Building Plans, Full Set14 Feb 2020

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (12 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1288 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Sahiba Constructions

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.