Skip to content

BODH 79

by Top Haven Developers · Gurugram

Not on our price list yet

Possession 9 Nov 2026 · as the developer declared it to HARERA

About this project

Key facts

Location
Gurugram
Carpet area
533–644 sq ft
In m²about 50–60 m², as declared
Registered by
TOP HAVEN DEVELOPERS PRIVATE LIMITEDthe company that filed it, for Top Haven Developers
Timeline
  1. 21 Mar 2022Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 9 Nov 2026Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

595homes, 533 to 644 sq ft of carpet area
  • Under 1,000 sq ft533–644 sq ft595

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft. Left out: 3 rows of a single unit and 112 units under 25 m², because the form lists homes, shops and other buildings in one table.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

In each home
  • KitchenOBD
  • LiftsRequired capacity with metaled frame & shutter
  • FloorsGlazed/ceramic/vitrified
  • WallsOBD
  • BathroomsISI marked
  • WindowsISI marked
  • Main door30 to 35 MM flush door shutter with one side laminates & other painted
  • Electrical fittingsISI marked

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: VILLAGE NAURANGPUR, SECTOR-79, DISTRICT GURGAON

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 1

Questions buyers ask

Is BODH 79 registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/548/280/2022/23. Valid to 9 Nov 2026.

The source ↗
What is the possession timeline for BODH 79?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 9 Nov 2026. Its registration runs to 9 Nov 2026; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around BODH 79?From the records · HARERA, read 4 Nov 2026

BODH 79 is in Gurugram; the site address declared to HARERA is Village Naurangpur, Sector-79, District Gurgaon. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building BODH 79?From the records · HARERA, read 4 Nov 2026

BODH 79 is a Top Haven Developers project, registered by its company TOP HAVEN DEVELOPERS PRIVATE LIMITED.

The source ↗Top Haven Developers's projects and court record

The records

What the registers hold for BODH 79: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/548/280/2022/23: Registered. Valid to 9 Nov 2026.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 91 OF 2021 is on the DTCP register: Licence ends soon; the register prints its validity to 9 Nov 2026.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 21 Mar 2022, building plans 21 Mar 2022.Declared to HARERA, read 29 Oct 2026
The court record of Top Haven Developers’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Registration ends soon

    Valid to 9 Nov 2026. HARERA Gurugram, read 4 Nov 2026. Source

  • Amber flag: Licence 91 OF 2021 ends soon

    Named in this project’s application. Valid to 9 Nov 2026. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 28 HARERA files, with the dates we read them
Registration no.
GGM/548/280/2022/23
Registration valid till
9 Nov 2026
Declared possession
9 Nov 2026

Declared by the promoter to HARERA

Land area
4.30625 (Acre) (17,426.78 sq m)
FAR
2.37 proposed of 2.37 permissible
licence
91 of 2021 (10.11.2021)
Estimated project cost
₹166.37 crore
Cost of land
₹27.85 crore
Layout plan, declared approved (field 5a)
21 Mar 2022
Building plans, declared approved
21 Mar 2022
Construction to start
1 May 2022
Completion declared for
9 Nov 2026
Declared inventory · 28 types

Declared inventory — 28 types declared, first 8 shown

  • Apartment/Shops/Other Buildings · 295 units · 59.83 sq m carpet · 6 towers · one flat
  • Apartment/Shops/Other Buildings · 94 units · 59.19 sq m carpet · 6 towers · one flat
  • Apartment/Shops/Other Buildings · 206 units · 49.51 sq m carpet · 6 towers · one flat
  • Apartment/Shops/Other Buildings · 10 units · 21.6 sq m carpet · 2 towers · under 25 m²: a shop or service unit the form does not label
  • Apartment/Shops/Other Buildings · 1 unit · 33.84 sq m carpet · 2 towers · one flat
  • Apartment/Shops/Other Buildings · 1 unit · 35.28 sq m carpet · 2 towers · one flat
  • Apartment/Shops/Other Buildings · 2 units · 21.24 sq m carpet · 2 towers · under 25 m²: a shop or service unit the form does not label
  • Apartment/Shops/Other Buildings · 1 unit · 21.87 sq m carpet · 2 towers · under 25 m²: a shop or service unit the form does not label
Statutory approvals, as declared · 3

Statutory approvals, as declared

  • I. LICENSE — declared: already been obtained (10 Nov 2021)
  • II. ZONING PLAN — declared: already been obtained (10 Nov 2021)
  • III. BUILDING PLAN — declared: already been obtained (21 Mar 2022)
On file with HARERA · 28 files

On file with HARERA (28)

Plans

Site plan

2 files
Demarcation Superimpose on Site Plan8 Apr 2022Approved Site Plan31 Dec 2021

Layout plan

1 file
Latest Layout Plan31 Dec 2021

Zoning plan

1 file
Zoning Plan31 Dec 2021

Demarcation plan

1 file
Demarcation Plan8 Apr 2022

Building plans

2 files
Final Scan Drawing Sector-79- 1-298 Apr 2022Approved Building Plans, Full Set31 Dec 2021

Services

Electricity

1 file
DHBVN Assurance8 Apr 2022

Service plans

1 file
Service Plans on the Layout31 Dec 2021

Approvals and clearances

DTCP licence

4 files
License Order8 Apr 2022LC IV8 Apr 2022LC IV A8 Apr 2022Licence Copy with Land Schedule31 Dec 2021

Other NOCs and clearances

3 files
NOC Forest8 Apr 2022Height Clearance8 Apr 2022Aravali NOC8 Apr 2022

Land records

Land records

4 files
Revenue Record Entry of Licence and Collaboration8 Apr 2022Jamabandi8 Apr 2022Land Title Search Report8 Apr 2022Mutation (Intkal)8 Apr 2022

Money

Accounts and finance

4 files
Cash Flow Statement8 Apr 2022CA Certificate on the Application’s Figures8 Apr 2022Service Estimate Receipt8 Apr 2022Non-Default Certificate from a CA31 Dec 2021

The promoter’s papers

Declarations and affidavits

3 files
The Promoter’s Declaration on Affidavit8 Apr 2022EC Undertaking8 Apr 2022Bank Undertaking8 Apr 2022

Other filings

Other filings

1 file
Sazara8 Apr 2022

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

91 OF 2021 · Top Haven Developers Pvt. Ltd. · GURGAON-MANESAR

Licence valid to 9 Nov 2026

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 2 Feb 2022 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

91 OF 2021: 12 parcels, 4.3063 acres in all, in Nurangpur (hadbast 157), tehsil Manesar.

The licence register prints the same licensed area, 4.3063 acres.

  • rectangle 48, kila 24/22 kanal
  • rectangle 58, kila 3/1/23 kanal 1 marla
  • 58//3/21 kanal
  • 58//12/213 marla
Show the other 8 parcels
  • 58//12/3/1/14 kanal 12 marla
  • 58//13/117 marla
  • 58//13/2/15 kanal 18 marla
  • 58//3/316 marla
  • 58//4/14 kanal
  • 58//8/12 kanal 8 marla
  • 58//8/25 kanal 4 marla
  • 58//9/14 kanal

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Nurangpur (hadbast 157), tehsil Manesar. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as rectangle 48, kila 24/2.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Lenders that list this project

  • PNB Housing Finance’s approved-projects list carries “Bodh 79”, by M/s Top Haven Developers Pvt. Ltd., code Gurgaon-0522-002645, approved 2022.

    PNB Housing Finance’s own page · read 26 Oct 2026 · www.pnbhousing.com ↗

A lender’s list prints no HARERA registration or licence number, so the Bhumiq team matched it to this project by its name and builder. A listing is the lender’s record of a project it has approved for home loans, not a loan offer.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

2 files
Demarcation Superimpose on Site Plan8 Apr 2022Approved Site Plan31 Dec 2021

Layout plan

1 file
Latest Layout Plan31 Dec 2021

Building plans

2 files
Final Scan Drawing Sector-79- 1-298 Apr 2022Approved Building Plans, Full Set31 Dec 2021

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (28 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1802 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Top Haven Developers

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.