SH. AMIT KUMAR, ESTATE OFFICER, HSVP FARIDABADHSVP COMPLEX SECTOR 12, FARIDABADthe company that filed it, for Estate Officer
Timeline
  1. 14 Apr 2019Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 14 Jan 2022Possession, as declareddeclared to HARERA, read 29 Oct 2026

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: SECTOR 11 TAORU

The builder

Its 6 projects in Bhumiq’s records, by what HARERA’s record shows
  • Other register states: 6

Questions buyers ask

Is DEVELOPMENT OF POCKET AT SECTOR 11 TAORU DISTT NUH registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as HRERA-PKL-NUH-352-2022. The register’s record shows an end date of 14 Jan 2022. The register shows it as: Registration lapsed.

The source ↗
What is the possession timeline for DEVELOPMENT OF POCKET AT SECTOR 11 TAORU DISTT NUH?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 14 Jan 2022. Its registration runs to 14 Jan 2022; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around DEVELOPMENT OF POCKET AT SECTOR 11 TAORU DISTT NUH?From the records · HARERA, read 4 Nov 2026

DEVELOPMENT OF POCKET AT SECTOR 11 TAORU DISTT NUH is in Nuh; the site address declared to HARERA is Sector 11 Taoru. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building DEVELOPMENT OF POCKET AT SECTOR 11 TAORU DISTT NUH?From the records · HARERA, read 4 Nov 2026

DEVELOPMENT OF POCKET AT SECTOR 11 TAORU DISTT NUH is a Estate Officer project, registered by its company SH. AMIT KUMAR, ESTATE OFFICER, HSVP FARIDABADHSVP COMPLEX SECTOR 12, FARIDABAD.

The source ↗Estate Officer's projects and court record

The records

What the registers hold for DEVELOPMENT OF POCKET AT SECTOR 11 TAORU DISTT NUH: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-NUH-352-2022: Registration lapsed. The register’s record shows an end date of 14 Jan 2022.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Plans approved, as the developer declared: layout plan 14 Apr 2019, building plans 14 Apr 2019.Declared to HARERA, read 29 Oct 2026
The court record of Estate Officer’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Registration lapsed

    The register’s record shows an end date of 14 Jan 2022. HARERA Panchkula, read 4 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 12 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-NUH-352-2022
Registration valid till
14 Jan 2022
Declared possession
14 Jan 2022

Declared by the promoter to HARERA

Land area
31.37 (Acre) (1,26,949.89 sq m)
FAR
2.64 proposed of 2.64 permissible
licence
Drawing No DTP(NUH)86/2019 Dated 14.01.2019/14.04.2019
Estimated project cost
₹8.67 crore
Cost of land
₹17.65 crore
Layout plan, declared approved (field 5a)
14 Apr 2019
Building plans, declared approved
14 Apr 2019
Construction to start
15 Jul 2021
Completion declared for
14 Jan 2022
Statutory approvals, as declared · 1

Statutory approvals, as declared

  • I. NO — declared: already been obtained
On file with HARERA · 12 files

On file with HARERA (12)

Plans

Site plan

1 file
Approved Site Plan16 Jul 2021

Layout plan

1 file
Latest Layout Plan16 Jul 2021

Zoning plan

1 file
Zoning Plan16 Jul 2021

Demarcation plan

1 file
Demarcation Plan16 Jul 2021

Building plans

1 file
Approved Building Plans, Full Set16 Jul 2021

Services

Service plans

1 file
Service Plans on the Layout16 Jul 2021

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule16 Jul 2021

Land records

Land records

1 file
Revenue Record Entry of Licence and Collaboration16 Jul 2021

Money

Accounts and finance

3 files
Cash Flow Statement16 Jul 2021CA Certificate on the Application’s Figures16 Jul 2021Non-Default Certificate from a CA16 Jul 2021

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit16 Jul 2021

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

The promoter declared Drawing No DTP(NUH)86/2019 Dated 14.01.2019/14.04.2019. We could not read a licence number from that, so nothing is claimed about it here.

declared in the registration application (Form REP-I), Panchkula bench · submitted 27 Jun 2022 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan16 Jul 2021

Layout plan

1 file
Latest Layout Plan16 Jul 2021

Building plans

1 file
Approved Building Plans, Full Set16 Jul 2021

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (12 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1653 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Estate Officer

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.