Timeline
  1. 29 Dec 2014Building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 5 Jan 2019Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside5 acres in all, by use
  • Apartment buildings5 acres · 100%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: SECTOR 82

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 1

Questions buyers ask

Is FLORIDAA IN 5 ACRES registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as 244 OF 2017. Ended 5 Jan 2019. The register shows it as: Registration expired.

The source ↗
What is the possession timeline for FLORIDAA IN 5 ACRES?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 5 Jan 2019. Its registration runs to 5 Jan 2019; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around FLORIDAA IN 5 ACRES?From the records · HARERA, read 4 Nov 2026

FLORIDAA IN 5 ACRES is in Faridabad; the site address declared to HARERA is Sector 82. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building FLORIDAA IN 5 ACRES?From the records · HARERA, read 4 Nov 2026

FLORIDAA IN 5 ACRES is a S3 Buildwell project, registered by its company S3 BUILDWELL LLP.

The source ↗S3 Buildwell's projects and court record

The records

What the registers hold for FLORIDAA IN 5 ACRES: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration 244 OF 2017: Registration expired. Ended 5 Jan 2019.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 59 OF 2014 is on the DTCP register: Licence ended, LC-IX linked; the register prints its validity to 24 Jun 2019.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: building plans 29 Dec 2014.Declared to HARERA, read 29 Oct 2026
The court record of S3 Buildwell’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Registration expired

    Ended 5 Jan 2019. HARERA Panchkula, read 4 Nov 2026. Source

  • Amber flag: Licence 59 OF 2014 validity ended

    Named in this project’s application. Valid to 24 Jun 2019. The register links a completion certificate (LC-IX), dated 30 Dec 2019, against this licence. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 6 HARERA files, with the dates we read them
Registration no.
244 OF 2017
Registration valid till
5 Jan 2019
Declared possession
5 Jan 2019

Declared by the promoter to HARERA

Land area
5.00 (Acre) (20,234.28 sq m)
FAR
2.25 proposed of 2.25 permissible
licence
LICENSE NO. 59 OF 2014 DATED 25.06.2014
Estimated project cost
₹122.00 crore
Cost of land
₹18.00 crore
Building plans, declared approved
29 Dec 2014
Construction to start
29 Dec 2014
Completion declared for
5 Jan 2019
Declared inventory · 1 type

Declared inventory

  • Apartment/Shops/Other Buildings · 783 units · 13 towers
Statutory approvals, as declared · 1

Statutory approvals, as declared

  • I. LICENSE NO. 59 OF 2014 — declared: already been obtained (26 Jun 2014)
On file with HARERA · 6 files

On file with HARERA (6)

Plans

Site plan

1 file
Approved Site Plan20 Feb 2020

Layout plan

1 file
Latest Layout Plan20 Feb 2020

Approvals and clearances

Completion certificate (CC)

1 file
Completion Certificate Dated 30-12-201931 Dec 2021

DTCP licence

1 file
Licence Copy with Land Schedule20 Feb 2020

Money

Accounts and finance

1 file
Non-Default Certificate from a CA20 Feb 2020

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit20 Feb 2020

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

59 OF 2014 · S3 Buildwell Pvt. Ltd. · Faridabad

Licence valid to 24 Jun 2019

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 20 Feb 2020 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

59 OF 2014: 7 parcels, 5.0062 acres in all, in Bhatola (hadbast 115), tehsil Faridabad.

The licence register prints the same licensed area, 5.01 acres.

  • 13//148 kanal
  • 13//15/11 kanal 5 marla
  • 13//4/26 kanal
  • 13//58 kanal
Show the other 3 parcels
  • 13//78 kanal
  • rectangle 13, kila 68 kanal
  • 12//1/1/1/116 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Faridabad, then the tehsil and the village: Bhatola (hadbast 115), tehsil Faridabad. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 13//14.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan20 Feb 2020

Layout plan

1 file
Latest Layout Plan20 Feb 2020

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (6 in all), none is a building plan, a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1307 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on S3 Buildwell

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.