Skip to content

FORTEASIA-THE GRAND

by True Villas Developers Pvt.ltd · Jhajjar

Not on our price list yet

Possession 5 Feb 2023 · as the developer declared it to HARERA

About this project

Key facts

Carpet area
540–856 sq ft
In m²about 50–80 m², as declared
Registered by
TRUE VILLAS DEVELOPERS PRIVATE LIMITEDthe company that filed it, for True Villas Developers Pvt.ltd
Timeline
  1. 21 Dec 2017Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 5 Feb 2023Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

96homes, 540 to 856 sq ft of carpet area
  • Under 1,000 sq ft540–856 sq ft96

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside14.152 acres in all, by use
  • Plots for sale4.59 acres · 32%
  • Roads4.14 acres · 29%
  • Apartment buildings2.05 acres · 14%
  • Land for community services, handed to the government1.415 acres · 10%
  • Parks and playgrounds1.406 acres · 10%
  • Shops and offices0.469 acres · 3%
  • Other usesas the form names them: Road widening0.082 acres · under 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: VILLAGE- KHERKA MUSALMAN, SECTOR-35, BAHADURGARH

The builder

Its 6 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 3
  • Registered, no OC or CC yet: 3

Questions buyers ask

Is FORTEASIA-THE GRAND registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as HRERA-PKL-JJR-69-2018. Ended 5 Feb 2023. The register shows it as: Registration expired.

The source ↗
What is the possession timeline for FORTEASIA-THE GRAND?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 5 Feb 2023. Its registration runs to 5 Feb 2023; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around FORTEASIA-THE GRAND?From the records · HARERA, read 4 Nov 2026

FORTEASIA-THE GRAND is in Jhajjar; the site address declared to HARERA is Village- Kherka Musalman, Sector-35, Bahadurgarh. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building FORTEASIA-THE GRAND?From the records · HARERA, read 4 Nov 2026

FORTEASIA-THE GRAND is a True Villas Developers Pvt.ltd project, registered by its company TRUE VILLAS DEVELOPERS PRIVATE LIMITED.

The source ↗True Villas Developers Pvt.ltd's projects and court record

The records

What the registers hold for FORTEASIA-THE GRAND: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-JJR-69-2018: Registration expired. Ended 5 Feb 2023.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 11 OF 2018 is on the DTCP register: Licence lapsed; the register prints its validity to 5 Feb 2023.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 21 Dec 2017.Declared to HARERA, read 29 Oct 2026
The court record of True Villas Developers Pvt.ltd’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Registration expired

    Ended 5 Feb 2023. HARERA Panchkula, read 4 Nov 2026. Source

  • Red flag: Licence 11 OF 2018 lapsed

    Named in this project’s application. Valid to 5 Feb 2023; no renewal on record. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 24 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-JJR-69-2018
Registration valid till
5 Feb 2023
Declared possession
5 Feb 2023

Declared by the promoter to HARERA

Land area
14.15 (Acre) (57,263.02 sq m)
FAR
the application prints 50.54, which is not a ratio
licence
11 of 2018 , Transfer of license vide Memo No. LC-3275-JE(MK)-2018/30805 dated 31.10.2018
Estimated project cost
₹20.21 crore
Cost of land
₹6.42 crore
Layout plan, declared approved (field 5a)
21 Dec 2017; Part E of the same form gives 6 Feb 2018
Construction to start
1 Dec 2018
Completion declared for
5 Feb 2023
Declared inventory · 2 types

Declared inventory

  • Apartment/Shops/Other Buildings · 78 units · 79.52 sq m carpet · 26 towers · one flat
  • Apartment/Shops/Other Buildings · 18 units · 50.16 sq m carpet · 18 towers · one flat
Statutory approvals, as declared · 3

Statutory approvals, as declared

  • I. LICENSE — declared: already been obtained (6 Feb 2018)
  • II. TRANSFER OF LICENSE ORDER — declared: already been obtained (31 Oct 2018)
  • III. LAYOUT PLAN — declared: already been obtained (6 Feb 2018)
On file with HARERA · 24 files

On file with HARERA (24)

Plans

Site plan

1 file
Approved Site Plan3 Nov 2018

Layout plan

1 file
Latest Layout Plan1 Nov 2018

Zoning plan

1 file
Zoning Plan3 Nov 2018

Demarcation plan

1 file
Demarcation Plan3 Nov 2018

Building plans

1 file
Approved Building Plans, Full Set3 Nov 2018

Services

Service plans

1 file
Service Plans on the Layout1 Nov 2018

Approvals and clearances

Completion certificate (CC)

1 file
Completion Certificate Uploaded20 Aug 2024

DTCP licence

2 files
Licence Copy with Land Schedule2 Nov 2018LC-IV1 Nov 2018

Land records

Land records

5 files
Jamabandi2 Nov 2018Jamabandi2 Nov 2018Power of Attorney1 Nov 2018

Sales papers

Allotment and sale agreements

1 file
Draft Allotment Letter1 Nov 2018

Money

Accounts and finance

3 files
Cash Flow Statement3 Nov 2018DD2 Nov 2018Non-Default Certificate from a CA1 Nov 2018

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit1 Nov 2018

Company papers

1 file
Directors2 Nov 2018

HARERA’s orders

HARERA’s orders

1 file
Corrigendum Issued9 Apr 2021

Other filings

Other filings

3 files
Transfer Order2 Nov 2018Bilateral Agreement1 Nov 2018Pancard of Company1 Nov 2018

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

11 OF 2018 · MANIK BUILDCON PVT. LTD. · BAHADURGARH

Licence valid to 5 Feb 2023

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 3 Nov 2018 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

11 OF 2018: 29 parcels, 14.15 acres in all, in KHERKA MUSALMAN (hadbast 45), tehsil Bahadurgarh.

The licence register prints the same licensed area, 14.15 acres.

  • 2//23/2/2/13 kanal 10 marla
  • 2//23/2/2/216 marla
  • 2//19/2/12 marla
  • 2//19/2/21 kanal 3 marla
Show the other 25 parcels
  • 2//20/15 kanal 8 marla
  • 2//20/21 kanal 14 marla
  • 2//21/13 kanal 17 marla
  • 2//21/24 kanal 3 marla
  • 2//22/116 marla
  • 2//22/26 kanal 12 marla
  • 8//1/21 kanal
  • 8//107 kanal 12 marla
  • 8//11/16 kanal 5 marla
  • 8//12/15 kanal 19 marla
  • 8//13/15 kanal 13 marla
  • 8//178 kanal
  • 8//2/12 kanal 8 marla
  • 8//2/24 kanal 18 marla
  • 8//3/1/11 marla
  • 8//3/1/27 kanal 7 marla
  • 8//8/27 kanal 8 marla
  • 8//9/12 kanal 5 marla
  • 8//9/25 kanal 3 marla
  • rectangle 8, kila 35/1/114 kanal
  • rectangle 8, kila 35/4/23 kanal 18 marla
  • rectangle 8, kila 42/1 MIN1 kanal 4 marla
  • rectangle 8, kila 42/1 MIN WEST1 marla
  • rectangle 8, kila 58/11 kanal 11 marla
  • 59//210 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Jhajjar, then the tehsil and the village: KHERKA MUSALMAN (hadbast 45), tehsil Bahadurgarh. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 2//23/2/2/1.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan3 Nov 2018

Layout plan

1 file
Latest Layout Plan1 Nov 2018

Building plans

1 file
Approved Building Plans, Full Set3 Nov 2018

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (24 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/272 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on True Villas Developers Pvt.ltd

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.