Timeline
  1. 12 Jan 2017Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 10 Mar 2017Building plans approveddeclared to HARERA, read 29 Oct 2026
  3. 21 Aug 2017Registered with HARERAHARERA, read 4 Nov 2026
  4. 18 Feb 2020Possession, as declareddeclared to HARERA, read 29 Oct 2026
  5. 31 Jul 2021Registration valid toHARERA, read 4 Nov 2026

Homes on offer

The homes the developer declared to HARERA, by size.

776homes, 304 to 1,994 sq ft of carpet area
  • Under 1,000 sq ft304–619 sq ft774
  • 1,500–2,000 sq ft1,994 sq ft2

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft. Left out: 1 row of a single unit and 6 units under 25 m², because the form lists homes, shops and other buildings in one table.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside5.413 acres in all, by use
  • Parking2.427 acres · 45%
  • Apartment buildings1.077 acres · 20%
  • Parks and playgrounds0.793 acres · 15%
  • Other uses0.321 acres · 6%
  • Roads0.251 acres · 5%
  • Green belts0.247 acres · 5%
  • Pavements0.198 acres · 4%
  • Electricity sub-station0.049 acres · under 1%
  • Sewage and waste treatment0.049 acres · under 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • KitchenFitting fixture ISI marked CP fitting
  • LiftsOTIS
  • FloorsCeramic tiles
  • WallsCeramic tiles upto 2 FEET above the counter
  • BathroomsFitting fixture ISI marked CP fitting & china WARE
  • WindowsPainted hardwood frame, flush doors, MS-Z section frame as per is CODE
  • Main doorPainted hardwood frame, flush doors
  • Electrical fittingsISI marked switches & sockets

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: P-903-905, 9TH FLOOR, C WING, JMD MEGAPOLIS, SECTOR-48, SOHNA ROAD

The builder

Its 2 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 1
  • Other register states: 1

Questions buyers ask

Is Global Hill View registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as 84 OF 2017, registered on 21 Aug 2017. Ended 31 Jul 2021. The register shows it as: Registration expired.

The source ↗
What is the possession timeline for Global Hill View?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 18 Feb 2020. Its registration runs to 31 Jul 2021; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around Global Hill View?From the records · HARERA, read 4 Nov 2026

Global Hill View is in Gurugram; the site address declared to HARERA is P-903-905, 9th Floor, C Wing, Jmd Megapolis, Sector-48, Sohna Road. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building Global Hill View?From the records · HARERA, read 4 Nov 2026

Global Hill View is a V K Motors project, registered by its company V K MOTORS PRIVATE LIMITED.

The source ↗V K Motors's projects and court record

The records

What the registers hold for Global Hill View: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration 84 OF 2017: Registration expired. Ended 31 Jul 2021.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 26 OF 2014 is on the DTCP register: Licence ended, LC-IX linked; the register prints its validity to 10 Jun 2024.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 12 Jan 2017, building plans 10 Mar 2017.Declared to HARERA, read 29 Oct 2026
The court record of V K Motors’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Registration expired

    Ended 31 Jul 2021. HARERA Gurugram, read 4 Nov 2026. Source

  • Amber flag: Licence 26 OF 2014 validity ended

    Named in this project’s application. Valid to 10 Jun 2024. The register links a completion certificate (LC-IX), dated 8 Feb 2024, against this licence. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 21 HARERA files, with the dates we read them
Registration no.
84 OF 2017
Registration date
21 Aug 2017
Registration valid till
31 Jul 2021
Declared possession
18 Feb 2020

Declared by the promoter to HARERA

Land area
5.4125 (Acre) (21,903.61 sq m)
FAR
the application prints 225, which is not a ratio
licence
26 of 2014
Estimated project cost
₹139.03 crore
Cost of land
₹14.40 crore
Layout plan, declared approved (field 5a)
12 Jan 2017
Building plans, declared approved
10 Mar 2017
Completion declared for
18 Feb 2020
Declared inventory · 14 types

Declared inventory — 14 types declared, first 8 shown

  • APARTMENT/SHOPS/OTHER BUILDINGS Type A · 376 units · 54.39 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type B · 338 units · 51.48 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type B1 · 38 units · 51.48 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type SHOPS · 4 units · 51.47 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type SHOPS · 2 units · 37.16 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type SHOPS · 2 units · 28.24 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type SHOPS · 2 units · 39.95 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type SHOPS · 4 units · 24.25 sq m carpet · under 25 m²: a shop or service unit the form does not label
Statutory approvals, as declared · 3

Statutory approvals, as declared

  • I. LICENSE — declared: already been obtained (11 Jun 2014)
  • II. BR-3 — declared: already been obtained (10 Mar 2017)
  • III. ENVIRONMENTAL CLEARANCE — declared: already been obtained (21 Jul 2017)
On file with HARERA · 21 files

On file with HARERA (21)

Plans

Site plan

1 file
Approved Site Plan29 Nov 2019

Layout plan

1 file
Latest Layout Plan29 Nov 2019

Zoning plan

1 file
Zoning Plan29 Nov 2019

Demarcation plan

1 file
Demarcation Plan29 Nov 2019

Building plans

1 file
Approved Building Plans, Full Set29 Nov 2019

Services

Service plans

1 file
Service Plans on the Layout29 Nov 2019

Approvals and clearances

Occupation certificate (OC)

1 file
OC uploaded4 Aug 2023

DTCP licence

2 files
Licence Copy with Land Schedule29 Nov 2019Licence Copy with Land Schedule23 Nov 2019

Land records

Land records

1 file
Revenue Record Entry of Licence and Collaboration29 Nov 2019

Sales papers

Allotment and sale agreements

2 files
BBA29 Nov 2019Allotment Letter29 Nov 2019

Money

Accounts and finance

6 files
CA Certificate on the Application’s Figures29 Nov 2019Non-Default Certificate from a CA29 Nov 2019Balance Sheet Fy 16-1729 Nov 2019

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit29 Nov 2019

Other filings

Other filings

2 files
Work Status as on 30 Sep 201929 Nov 2019Total Liability Against Project29 Nov 2019

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

26 OF 2014 · VK Motors Pvt. Ltd. · Sohna

Licence valid to 10 Jun 2024

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 30 Nov 2019 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

26 OF 2014: 10 parcels, 5.4125 acres in all, in Sohna (hadbast 187), tehsil Sohna.

The licence register prints the same licensed area, 5.41 acres.

  • 289//20/21 kanal 7 marla
  • 289//218 kanal
  • 290//16/21 kanal 6 marla
  • 290//233 kanal
Show the other 6 parcels
  • 290//247 kanal 6 marla
  • 290//258 kanal
  • rectangle 290, kila 172 kanal 4 marla
  • 293//56 kanal 18 marla
  • 294//13 kanal 2 marla
  • 290//18/22 kanal 3 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Sohna (hadbast 187), tehsil Sohna. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 289//20/2.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan29 Nov 2019

Layout plan

1 file
Latest Layout Plan29 Nov 2019

Building plans

1 file
Approved Building Plans, Full Set29 Nov 2019

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (21 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/963 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on V K Motors

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.