Timeline
  1. 30 May 2013Building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 14 Jun 2028Registration valid toHARERA, read 4 Nov 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside20,910 m² in all, by use
  • Apartment buildings6,244 m² · 30%
  • Roads5,680 m² · 27%
  • Parks and playgrounds4,065 m² · 19%
  • Parking3,521 m² · 17%
  • Pavements824 m² · 4%
  • Club house401 m² · 2%
  • Electricity sub-station97 m² · under 1%
  • Sewage and waste treatment80 m² · under 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningNot provided (client'S scope)
  • Kitchen"1. granite marble counter mounted on frame or SLAB 2. SS single bowl sink 3. CP fittings 4. ceramic tiles upto two to two and a half FEET above counter. "
  • Kitchen appliancesNot provided (client'S scope)
  • LiftsPassenger lift WILL be provided of reputed make LIKE KONE, johnsons or equivalent.
  • WardrobesNot provided (client'S scope)
  • Floors"internal flooring of the FLAT living/dinning/bedrooms/passages vitrified tiles."
  • Walls"internal walls/ceilings of the FLAT OBD finish "
  • Bathrooms"1. taps fittings provided 2. WC'S and WASH basins"

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: SECTOR 32

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 1

Questions buyers ask

Is INR HEIGHTS registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as HRERA-PKL-KRL-553-2024. Valid to 14 Jun 2028.

The source ↗
How is the connectivity around INR HEIGHTS?From the records · HARERA, read 4 Nov 2026

INR HEIGHTS is in Karnal; the site address declared to HARERA is Sector 32. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building INR HEIGHTS?From the records · HARERA, read 4 Nov 2026

INR HEIGHTS is a Skyhigh Infraland project, registered by its company SKYHIGH INFRALAND PRIVATE LIMITED.

The source ↗Skyhigh Infraland's projects and court record
What protections do I have as a buyer?General guidance

Under the RERA Act, a registered project has to keep most of the money buyers pay in a separate bank account for that project, sell by carpet area, and stick to the plans it registered unless enough buyers agree to a change. If possession is late, a buyer can ask HARERA for interest or a refund. How this applies to your own purchase depends on your agreement, so ask a lawyer before you sign.

The records

What the registers hold for INR HEIGHTS: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-KRL-553-2024: Registered. Valid to 14 Jun 2028.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 109 OF 2011 is on the DTCP register: Licence lapsed; the register prints its validity to 10 Dec 2015.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: building plans 30 May 2013.Declared to HARERA, read 29 Oct 2026
The court record of Skyhigh Infraland’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Licence 109 OF 2011 lapsed

    Named in this project’s application. Valid to 10 Dec 2015; no renewal on record. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 8 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-KRL-553-2024
Registration valid till
14 Jun 2028

Declared by the promoter to HARERA

Land area
5.167 (Acre) (20,910.11 sq m)
FAR
1.74 proposed of 1.75 permissible
licence
License No. 109 of 2011 dated 11.12.2011 (Valid / Renewed upto 10.12.2024)
Estimated project cost
₹146.68 crore
Cost of land
₹39.00 crore
Building plans, declared approved
30 May 2013
Declared inventory · 3 types

Declared inventory

  • APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-A, A1, B, B1, · 338 units · 34,620.63 sq m carpet
  • APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-C EWS · 72 units · 1,780.02 sq m carpet
  • APARTMENT/SHOPS/OTHER BUILDINGS Type SHOPS · 1 unit · 101.23 sq m carpet · a unit for another use, left out of home sizes
Statutory approvals, as declared · 5

Statutory approvals, as declared

  • I. LICENSE NO. 109 OF 2011 — declared: already been obtained (11 Dec 2011)
  • II. BUILDING PLANS APPROVAL — declared: already been obtained (30 May 2013)
  • III. ZONING PLAN — declared: already been obtained (11 Dec 2013)
  • IV. RENEWAL OF LICENSE — declared: already been obtained (15 Jun 2023)
  • V. CHANGE IN BENEFICIAL INTEREST — declared: already been obtained (15 Jun 2023)
On file with HARERA · 8 files

On file with HARERA (8)

Plans

Site plan

1 file
Approved Site Plan2 Aug 2023

Layout plan

1 file
Latest Layout Plan2 Aug 2023

Zoning plan

1 file
Zoning Plan2 Aug 2023

Building plans

1 file
Approved Building Plans, Full Set2 Aug 2023

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule2 Aug 2023

Money

Accounts and finance

1 file
Non-Default Certificate from a CA2 Aug 2023

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit2 Aug 2023

HARERA’s orders

HARERA’s orders

1 file
Corrigendum Issued25 Jun 2024

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

109 OF 2011 · Sky High Landcon · KARNAL

Licence valid to 10 Dec 2015

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 2 Aug 2023 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

109 OF 2011: 11 parcels, 5.2 acres in all, in Budha khera (hadbast 1), tehsil Karnal.

The licence register prints the same licensed area, 5.2 acres.

  • 33//17 kanal
  • 33//106 kanal 12 marla
  • 33//11/15 kanal 17 marla
  • 33//12/16 kanal
Show the other 7 parcels
  • 33//12/2/113 marla
  • 33//2/17 kanal 4 marla
  • 33//2/216 marla
  • 33//2612 marla
  • 33//9/110 marla
  • 33//9/24 marla
  • 33//9/36 kanal 4 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Karnal, then the tehsil and the village: Budha khera (hadbast 1), tehsil Karnal. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 33//1.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan2 Aug 2023

Layout plan

1 file
Latest Layout Plan2 Aug 2023

Building plans

1 file
Approved Building Plans, Full Set2 Aug 2023

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (8 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/2572 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Skyhigh Infraland

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.