Possession 1 Mar 2031 · as the developer declared it to HARERA
About this project
Key facts
- 2 Mar 2026Layout plan approveddeclared to HARERA, read 29 Oct 2026
- 1 Mar 2031Possession, as declareddeclared to HARERA, read 29 Oct 2026
Amenities and specifications
How the land is set aside and what comes in each home, as the developer declared them to HARERA.
- Roads1,886 m² · 46%
- Plots for sale1,332 m² · 33%
- Other usesas the form names them: Area under green belt and road widening729 m² · 18%
- Electricity sub-station100 m² · 2%
- Sewage and waste treatment50 m² · 1%
The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.
Location and connectivity
Where it is and what is near it. Every distance is a straight line, not a travel time.
Bhumiq holds no map point for this project yet.The site address declared to HARERA: VILLAGE BALDI SECTOR 29
The builder
- Registered, no OC or CC yet: 1
Questions buyers ask
Is KARNAL CITY CENTRE registered with HARERA?From the records · HARERA, read 4 Nov 2026
HARERA lists it as HRERA-PKL-KRL-919-2026. Valid to 1 Mar 2031.
The source ↗What is the possession timeline for KARNAL CITY CENTRE?From the records · HARERA, read 4 Nov 2026
When it registered the project, the developer declared that it would hand over homes by 1 Mar 2031. Its registration runs to 1 Mar 2031; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.
The source ↗How is the connectivity around KARNAL CITY CENTRE?From the records · HARERA, read 4 Nov 2026
KARNAL CITY CENTRE is in Karnal; the site address declared to HARERA is Village Baldi Sector 29. Bhumiq has not measured its distance to the main roads and metro lines yet.
The source ↗What will I pay on top of the price?General guidance
You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.
Work out the stamp dutyWho is building KARNAL CITY CENTRE?From the records · HARERA, read 4 Nov 2026
KARNAL CITY CENTRE is a Karnal City Centre project.
The source ↗Karnal City Centre's projects and court recordThe records
What the registers hold for KARNAL CITY CENTRE: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.
- HARERA registration HRERA-PKL-KRL-919-2026: Registered. Valid to 1 Mar 2031.HARERA, read 4 Nov 2026 · See it on HARERA ↗
- Land licence 36 OF 2026 is on the DTCP register, valid to 1 Mar 2031.DTCP, read 3 Nov 2026
- Plans approved, as the developer declared: layout plan 2 Mar 2026.Declared to HARERA, read 29 Oct 2026
Not checked yet: the land owner records (jamabandi) and complaints at HARERA.
Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 5 HARERA files, with the dates we read them
- Registration no.
- HRERA-PKL-KRL-919-2026
- Registration valid till
- 1 Mar 2031
- Declared possession
- 1 Mar 2031
Declared by the promoter to HARERA
- Land area
- 4097.436 (Sqr/mtrs)
- FAR
- 1.5 proposed of 1.5 permissible
- licence
- LICENCE NO. 36 OF 2026 GRANTED BY DTCP HARYANA ON DATED 02.03.2026 IS VALID UPTO 01 .03.2031
- Estimated project cost
- ₹15.39 crore
- Cost of land
- ₹8.30 crore
- Layout plan, declared approved (field 5a)
- 2 Mar 2026
- Construction to start
- 1 Jul 2026
- Completion declared for
- 1 Mar 2031
Statutory approvals, as declared · 2
Statutory approvals, as declared
- I. LAYOUT PLAN — declared: already been obtained (2 Mar 2026)
- II. STANDARD DESIGNS OF SCO'S COMMERCIAL SITE — declared: already been obtained (22 Apr 2026)
On file with HARERA · 5 files
On file with HARERA (5)
Plans
Site plan
1 fileLayout plan
1 fileApprovals and clearances
DTCP licence
1 fileMoney
Accounts and finance
1 fileThe promoter’s papers
Declarations and affidavits
1 fileThese are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.
The DTCP licence named on the application
36 OF 2026 · Karnal City Centre · KARNAL
Licence valid to 1 Mar 2031
From the Town & Country Planning department’s licence register, read 3 Nov 2026.
A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.
declared in the registration application (Form REP-I), Panchkula bench · submitted 13 May 2026 · read 29 Oct 2026 · not verified by Bhumiq
source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026
Land under the licence
36 OF 2026
DTCP’s page showed no land schedule for licence 36 OF 2026 when Bhumiq read it on 18 Oct 2026. verify at source
Layouts & payment plan
Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.
Site plan
1 fileLayout plan
1 fileAmong the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (5 in all), none is a building plan, a floor plan or a payment plan.
source: https://haryanarera.gov.in/view_project/project_preview_open/4102 · read 29 Oct 2026
The call is with the Bhumiq team. You need a free account so we can call you back.
Run due diligence on Karnal City Centre
Its court cases, its DTCP licences and the source of each fact, free once you sign in.
Open the developer profileAs of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.