Skip to content

Not on our price list yet

Possession 31 Dec 2023 · as the developer declared it to HARERA

About this project

Key facts

Location
Kurukshetra
Timeline
  1. 31 Dec 2023Possession, as declareddeclared to HARERA, read 29 Oct 2026
  2. 30 Sep 2026Registration valid toHARERA, read 3 Nov 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside60,690 m² in all, by use
  • Plots for sale25,935 m² · 43%
  • Roads17,046 m² · 28%
  • Land for community services, handed to the government6,069 m² · 10%
  • Parks and playgrounds5,705 m² · 9%
  • Green belts2,326 m² · 4%
  • Club house2,104 m² · 3%
  • Electricity sub-station987 m² · 2%
  • Sewage and waste treatment518 m² · under 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: VILLAGE NARKATARI, SEC.46, KURUKSHETRA

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Other register states: 1

Questions buyers ask

Is KRISHNA KUNJ registered with HARERA?From the records · HARERA, read 3 Nov 2026

HARERA lists it as HRERA-PKL-KUK-113-2019. The register’s record shows an end date of 30 Sep 2026. The register shows it as: Registration lapsed.

The source ↗
What is the possession timeline for KRISHNA KUNJ?From the records · HARERA, read 3 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Dec 2023. Its registration runs to 30 Sep 2026; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around KRISHNA KUNJ?From the records · HARERA, read 3 Nov 2026

KRISHNA KUNJ is in Kurukshetra; the site address declared to HARERA is Village Narkatari, Sec.46, Kurukshetra. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building KRISHNA KUNJ?From the records · HARERA, read 3 Nov 2026

KRISHNA KUNJ is a Antique India Pvt Ltd In Collaboration With Sultan Singh, Multan Singh, Kehar Singh project.

The source ↗Antique India Pvt Ltd In Collaboration With Sultan Singh, Multan Singh, Kehar Singh's projects and court record

The records

What the registers hold for KRISHNA KUNJ: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-KUK-113-2019: Registration lapsed. The register’s record shows an end date of 30 Sep 2026.HARERA, read 3 Nov 2026 · See it on HARERA ↗
  • Land licence 10 OF 2018 is on the DTCP register: Licence ends soon; the register prints its validity to 1 Feb 2027.DTCP, read 3 Nov 2026
The court record of Antique India Pvt Ltd In Collaboration With Sultan Singh, Multan Singh, Kehar Singh’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Registration lapsed

    The register’s record shows an end date of 30 Sep 2026. HARERA Panchkula, read 3 Nov 2026. Source

  • Amber flag: Licence 10 OF 2018 ends soon

    Named in this project’s application. Valid to 1 Feb 2027. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 15 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-KUK-113-2019
Registration valid till
30 Sept 2026
Declared possession
31 Dec 2023

Declared by the promoter to HARERA

Land area
15 (Acre) (60,702.85 sq m)
FAR
0 proposed
licence
10 of 2018
Estimated project cost
₹11.40 crore
Cost of land
₹2.25 crore
Construction to start
1 Jan 2019
Completion declared for
31 Dec 2023
Statutory approvals, as declared · 1

Statutory approvals, as declared

  • I. ALL THE STATUTORY APPROVAL HAVE BEEN APPLIED — declared: applied for but yet to receive
On file with HARERA · 15 files

On file with HARERA (15)

Plans

Site plan

1 file
Approved Site Plan5 Nov 2018

Layout plan

2 files
Revised Layout Plan Cum Demarcation Plan4 May 2022Latest Layout Plan28 Oct 2018

Zoning plan

1 file
Zoning Plan5 Nov 2018

Demarcation plan

1 file
Demarcation Plan5 Nov 2018

Services

Service plans

1 file
Service Plans on the Layout28 Oct 2018

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule28 Oct 2018

Land records

Land records

1 file
Revenue Record Entry of Licence and Collaboration8 Nov 2018

Money

Accounts and finance

3 files
Cash Flow Statement29 Oct 2018Non-Default Certificate from a CA28 Oct 2018CA Certificate on the Application’s Figures28 Oct 2018

HARERA’s orders

HARERA’s orders

3 files
Extension Uploaded1 Oct 2026Corrigendum Uploaded7 Apr 2026Extension upload30 Aug 2024

Other filings

Other filings

1 file
List of Plots4 May 2022

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

10 OF 2018 · ANTIQUE INDIA PVT. LTD. · Kurukshetra

Licence valid to 1 Feb 2027

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 19 Jul 2019 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 3 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

10 OF 2018: 24 parcels, 15 acres in all, in Narkatari (hadbast 386), tehsil Thanesar.

The licence register prints the same licensed area, 15 acres.

  • rectangle 268, kila 2683 kanal 12 marla
  • rectangle 269, kila 269/25 kanal 15 marla
  • rectangle 270, kila 2708 kanal
  • rectangle 271, kila 271/min3 kanal 14 marla
Show the other 20 parcels
  • rectangle 272, kila 2727 kanal 4 marla
  • rectangle 273, kila 2736 kanal
  • rectangle 275, kila 2753 kanal 8 marla
  • rectangle 285, kila 2857 kanal 8 marla
  • rectangle 286, kila 286/21 kanal 16 marla
  • rectangle 287, kila 287/26 kanal 9 marla
  • rectangle 296, kila 296/113 marla
  • rectangle 286, kila 286/11 kanal 8 marla
  • rectangle 296, kila 296/26 kanal 7 marla
  • rectangle 297, kila 2971 kanal
  • rectangle 299, kila 2992 kanal 8 marla
  • rectangle 300, kila 3008 kanal
  • rectangle 301, kila 3015 kanal 13 marla
  • rectangle 302, kila 3026 kanal 10 marla
  • rectangle 303, kila 303/25 kanal 16 marla
  • rectangle 307, kila 30710 kanal 13 marla
  • rectangle 308, kila 308/16 kanal 10 marla
  • rectangle 266, kila 2668 kanal
  • rectangle 269, kila 269/12 kanal 5 marla
  • rectangle 287, kila 287/11 kanal 11 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Kurukshetra, then the tehsil and the village: Narkatari (hadbast 386), tehsil Thanesar. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as rectangle 268, kila 268.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan5 Nov 2018

Layout plan

2 files
Revised Layout Plan Cum Demarcation Plan4 May 2022Latest Layout Plan28 Oct 2018

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (15 in all), none is a building plan, a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/107 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Antique India Pvt Ltd In Collaboration With Sultan Singh, Multan Singh, Kehar Singh

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.