MAK GREEN - TWIN TOWERS

by Raj Developers Through Proprietor Raj Kumari · Rohtak

Not on our price list yet

Possession 31 Dec 2028 · as the developer declared it to HARERA

About this project

Key facts

Carpet area
1,238–1,365 sq ft
In m²about 115–127 m², as declared
Timeline
  1. 12 Sep 2024Building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 31 Dec 2028Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

29homes, 1,238 to 1,365 sq ft of carpet area
  • 1,000–1,500 sq ft1,238–1,365 sq ft29

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft. Left out: 1 row of a single unit, because the form lists homes, shops and other buildings in one table.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside2,016 acres in all, by use
  • Apartment buildings705.6 acres · 35%
  • Roads547.52 acres · 27%
  • Parking440.58 acres · 22%
  • Parks and playgrounds322.3 acres · 16%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningNot provided (client'S scope)
  • Kitchen"1. granite marble counter mounted on frame or SLAB 2. SS single bowl sink 3. CP fittings 4. ceramic tiles upto two to two and a half FEET above counter. "
  • Kitchen appliancesNot provided (client'S scope)
  • LiftsPassenger lift WILL be provided of reputed make LIKE KONE, johnsons or equivalent.
  • WardrobesNot provided (client'S scope)
  • Floors"internal flooring of the FLAT living/dinning/bedrooms/passages vitrified tiles."
  • Walls"internal walls/ceilings of the FLAT OBD finish "
  • Bathrooms"1. taps fittings provided 2. WC'S and WASH basins"

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: PLOT NO. 2, GH-2, SECTOR-4 EXTENSION

The builder

Its 2 projects in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 2

Questions buyers ask

Is MAK GREEN - TWIN TOWERS registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as HRERA-PKL-ROH-634-2024. Valid to 31 Dec 2028.

The source ↗
What is the possession timeline for MAK GREEN - TWIN TOWERS?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Dec 2028. Its registration runs to 31 Dec 2028; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around MAK GREEN - TWIN TOWERS?From the records · HARERA, read 4 Nov 2026

MAK GREEN - TWIN TOWERS is in Rohtak; the site address declared to HARERA is Plot No. 2, Gh-2, Sector-4 Extension. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building MAK GREEN - TWIN TOWERS?From the records · HARERA, read 4 Nov 2026

MAK GREEN - TWIN TOWERS is a Raj Developers Through Proprietor Raj Kumari project.

The source ↗Raj Developers Through Proprietor Raj Kumari's projects and court record

The records

What the registers hold for MAK GREEN - TWIN TOWERS: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-ROH-634-2024: Registered. Valid to 31 Dec 2028.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Plans approved, as the developer declared: building plans 12 Sep 2024.Declared to HARERA, read 29 Oct 2026
The court record of Raj Developers Through Proprietor Raj Kumari’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 7 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-ROH-634-2024
Registration valid till
31 Dec 2028
Declared possession
31 Dec 2028

Declared by the promoter to HARERA

Land area
2016.00 (Acre) (81,58,462.55 sq m)
FAR
1.75 proposed of 1.75 permissible
licence
HSVP ALLOTMENT OF SITE VIDE MEMO NO. ZO005/EO010/UE018/GALOT/0000001226,Dated 10.01.2024.
Estimated project cost
₹21.08 crore
Cost of land
₹8.08 crore
Building plans, declared approved
12 Sept 2024
Construction to start
15 Sept 2024
Completion declared for
31 Dec 2028
Declared inventory · 4 types

Declared inventory

  • Apartment/Shops/Other Buildings · 23 units · 115.005 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 1 unit · 123.643 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 3 units · 116.6 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 3 units · 126.833 sq m carpet · 1 tower · one flat
Statutory approvals, as declared · 3

Statutory approvals, as declared

  • I. SITE ALLOTMENT LETTER FROM HSVP — declared: already been obtained (10 Jan 2024)
  • II. POSSESSION LETTER FROM HSVP — declared: already been obtained (26 Feb 2024)
  • III. BUILDING PLANS APPROVAL LETTER — declared: already been obtained (12 Sept 2024)
On file with HARERA · 7 files

On file with HARERA (7)

Plans

Site plan

1 file
Approved Site Plan30 Sept 2024

Layout plan

1 file
Latest Layout Plan30 Sept 2024

Zoning plan

1 file
Zoning Plan30 Sept 2024

Building plans

1 file
Approved Building Plans, Full Set30 Sept 2024

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule25 Sept 2024

Money

Accounts and finance

1 file
Non-Default Certificate from a CA25 Sept 2024

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit30 Sept 2024

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

The promoter declared HSVP ALLOTMENT OF SITE VIDE MEMO NO. ZO005/EO010/UE018/GALOT/0000001226,Dated 10.01.2024.. We could not read a licence number from that, so nothing is claimed about it here.

declared in the registration application (Form REP-I), Panchkula bench · submitted 30 Sept 2024 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan30 Sept 2024

Layout plan

1 file
Latest Layout Plan30 Sept 2024

Building plans

1 file
Approved Building Plans, Full Set30 Sept 2024

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (7 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/3125 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Raj Developers Through Proprietor Raj Kumari

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.