Skip to content

NEAL CITY

by Soha Developers · Faridabad

Not on our price list yet

Possession 31 Dec 2023 · as the developer declared it to HARERA

About this project

Key facts

Location
Faridabad
Registered by
M/S SOHA DEVELOPERS PRIVATE LIMITEDthe company that filed it, for Soha Developers
Timeline
  1. 16 Aug 2019Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 31 Dec 2023Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside54,989 m² in all, by use
  • Plots for sale29,864 m² · 54%
  • Roads12,901 m² · 23%
  • Land for community services, handed to the government5,499 m² · 10%
  • Parks and playgrounds4,131 m² · 8%
  • Shops and offices2,157 m² · 4%
  • Sewage and waste treatment300 m² · under 1%
  • Other usesas the form names them: Under, Milk128 m² · under 1%
  • Electricity sub-station9 m² · under 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: VILLAGE BHUPANI, SECTOR-98, TEHSIL & DISTRICT FARIDABAD, HARYANA

The builder

Its 3 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 1
  • Registered, no OC or CC yet: 2

Questions buyers ask

Is NEAL CITY registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as HRERA-PKL-FBD-169-2019. Ended 31 Dec 2023. The register shows it as: Registration expired.

The source ↗
What is the possession timeline for NEAL CITY?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Dec 2023. Its registration runs to 31 Dec 2023; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around NEAL CITY?From the records · HARERA, read 4 Nov 2026

NEAL CITY is in Faridabad; the site address declared to HARERA is Village Bhupani, Sector-98, Tehsil & District Faridabad, Haryana. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building NEAL CITY?From the records · HARERA, read 4 Nov 2026

NEAL CITY is a Soha Developers project, registered by its company M/S SOHA DEVELOPERS PRIVATE LIMITED.

The source ↗Soha Developers's projects and court record

The records

What the registers hold for NEAL CITY: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-FBD-169-2019: Registration expired. Ended 31 Dec 2023.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 97 OF 2019 is on the DTCP register: Licence ended, LC-IX linked; the register prints its validity to 30 Aug 2024.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 16 Aug 2019.Declared to HARERA, read 29 Oct 2026
The court record of Soha Developers’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Registration expired

    Ended 31 Dec 2023. HARERA Panchkula, read 4 Nov 2026. Source

  • Amber flag: Licence 97 OF 2019 validity ended

    Named in this project’s application. Valid to 30 Aug 2024. The register links a completion certificate (LC-IX), dated 20 Apr 2022, against this licence. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 13 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-FBD-169-2019
Registration valid till
31 Dec 2023
Declared possession
31 Dec 2023

Declared by the promoter to HARERA

Land area
13.588 (Acre) (54,988.69 sq m)
FAR
0 proposed of 0 permissible
licence
97 OF 2019, DATED 31.08.2019
Estimated project cost
₹35.70 crore
Cost of land
₹5.65 crore
Layout plan, declared approved (field 5a)
16 Aug 2019
Construction to start
1 Oct 2019
Completion declared for
31 Dec 2023
Statutory approvals, as declared · 2

Statutory approvals, as declared

  • I. LICENSE — declared: already been obtained (31 Aug 2019)
  • II. LAYOUT PLAN — declared: already been obtained (16 Aug 2019)
On file with HARERA · 13 files

On file with HARERA (13)

Plans

Site plan

1 file
Approved Site Plan10 Sept 2019

Layout plan

1 file
Latest Layout Plan11 Sept 2019

Zoning plan

1 file
Zoning Plan14 Sept 2019

Demarcation plan

1 file
Demarcation Plan14 Sept 2019

Building plans

1 file
Approved Building Plans, Full Set10 Sept 2019

Services

Service plans

1 file
Service Plans on the Layout11 Sept 2019

Approvals and clearances

Completion certificate (CC)

1 file
Completion Certificate6 Jun 2022

DTCP licence

1 file
Licence Copy with Land Schedule11 Sept 2019

Land records

Land records

1 file
Revenue Record Entry of Licence and Collaboration10 Sept 2019

Money

Accounts and finance

3 files
CA Certificate on the Application’s Figures14 Sept 2019Non-Default Certificate from a CA14 Sept 2019Cash Flow Statement14 Sept 2019

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit14 Sept 2019

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

97 OF 2019 · Soha Developers Pvt. Ltd. · FARIDABAD

Licence valid to 30 Aug 2024

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 18 Sept 2019 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

97 OF 2019: 16 parcels, 13.5875 acres in all, in Bhupani (hadbast 143), tehsil Faridabad.

The licence register prints the same licensed area, 13.588 acres.

  • 100//4/25 kanal 2 marla
  • 100//58 kanal
  • 100//68 kanal
  • 100//7/17 kanal 8 marla
Show the other 12 parcels
  • 100//8/14 marla
  • 99//18 kanal
  • 99//108 kanal
  • 99//12/12 kanal 8 marla
  • 99//12/25 kanal 12 marla
  • 99//138 kanal
  • 99//148 kanal
  • 99//178 kanal
  • 99//188 kanal
  • 99//198 kanal
  • 99//28 kanal
  • 99//98 kanal

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Faridabad, then the tehsil and the village: Bhupani (hadbast 143), tehsil Faridabad. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 100//4/2.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan10 Sept 2019

Layout plan

1 file
Latest Layout Plan11 Sept 2019

Building plans

1 file
Approved Building Plans, Full Set10 Sept 2019

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (13 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/851 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Soha Developers

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.