How the land is set aside and what comes in each home, as the developer declared them to HARERA.
- Plots for sale6.743 acres · 56%
- Roads2.706 acres · 23%
- Land for community services, handed to the government1.2 acres · 10%
- Parks and playgrounds0.901 acres · 7%
- Shops and offices0.469 acres · 4%
The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.
Location and connectivity
Where it is and what is near it. Every distance is a straight line, not a travel time.
Bhumiq holds no map point for this project yet.The site address declared to HARERA: VILLAGE SULTANPUR AND AHMADPUR SECTOR-27
The builder
- Other register states: 1
Questions buyers ask
Is P. P. GREEN CITY registered with HARERA?From the records · HARERA, read 4 Nov 2026
HARERA lists it as HRERA-PKL-SNP-228-2021. The register’s record shows an end date of 9 Sep 2024. The register shows it as: Registration lapsed.
The source ↗What is the possession timeline for P. P. GREEN CITY?From the records · HARERA, read 4 Nov 2026
When it registered the project, the developer declared that it would hand over homes by 9 Sep 2024. Its registration runs to 9 Sep 2024; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.
The source ↗How is the connectivity around P. P. GREEN CITY?From the records · HARERA, read 4 Nov 2026
P. P. GREEN CITY is in Sonipat; the site address declared to HARERA is Village Sultanpur And Ahmadpur Sector-27. Bhumiq has not measured its distance to the main roads and metro lines yet.
The source ↗What will I pay on top of the price?General guidance
You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.
Work out the stamp dutyWho is building P. P. GREEN CITY?From the records · HARERA, read 4 Nov 2026
P. P. GREEN CITY is a A P Real Estates project.
The source ↗A P Real Estates's projects and court recordThe records
What the registers hold for P. P. GREEN CITY: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.
- HARERA registration HRERA-PKL-SNP-228-2021: Registration lapsed. The register’s record shows an end date of 9 Sep 2024.HARERA, read 4 Nov 2026 · See it on HARERA ↗
- Land licence 106 OF 2019 is on the DTCP register: Licence lapsed; the register prints its validity to 9 Sep 2024.DTCP, read 3 Nov 2026
Flagged on the record
These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.
Not checked yet: the land owner records (jamabandi) and complaints at HARERA.
Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 5 HARERA files, with the dates we read them
- Registration no.
- HRERA-PKL-SNP-228-2021
- Registration valid till
- 9 Sept 2024
- Declared possession
- 9 Sept 2024
Declared by the promoter to HARERA
- Land area
- 12.01875 (Acre) (48,638.16 sq m)
- FAR
- 1 proposed of 1 permissible
- licence
- License No. 106 of 2019 dated 10.09.2019 (Valid upto 09.09.2024)
- Estimated project cost
- ₹31.61 crore
- Cost of land
- ₹12.72 crore
- Construction to start
- 10 Jan 2021
- Completion declared for
- 9 Sept 2024
Statutory approvals, as declared · 6
Statutory approvals, as declared
- I. LICENSE NO. 106 OF 2019 — declared: already been obtained (10 Sept 2019)
- II. NOC FROM HSPCB (CTE) — declared: already been obtained (12 Dec 2020)
- III. APPROVAL OF TEMPORARY SITE OFFICE — declared: already been obtained (17 Dec 2020)
- IV. NOC FROM FOREST — declared: already been obtained (4 Dec 2020)
- V. APPLICATION FOR PERMISSION TO ABSTRACT GROUND WATER FOR INFRASTRUCTURAL USE — declared: already been obtained (20 Oct 2020)
- VI. APPLICATION FOR APPROVAL OF SERVICE PLAN & ESTIMATES — declared: applied for but yet to receive (2 Dec 2020)
On file with HARERA · 5 files
On file with HARERA (5)
Plans
Site plan
1 fileLayout plan
1 fileApprovals and clearances
DTCP licence
1 fileMoney
Accounts and finance
1 fileThe promoter’s papers
Declarations and affidavits
1 fileThese are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.
The DTCP licence named on the application
106 OF 2019 · AP Real Estate Pvt Ltd · Sonipat
Licence valid to 9 Sept 2024
From the Town & Country Planning department’s licence register, read 3 Nov 2026.
A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.
declared in the registration application (Form REP-I), Panchkula bench · submitted 8 Jan 2021 · read 29 Oct 2026 · not verified by Bhumiq
source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026
Land under the licence
The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.
106 OF 2019: 23 parcels, 12.0188 acres in all, in Sultanpur (hadbast 80) and Ahmadpur (hadbast 76), tehsil Sonipat.
The licence register prints the same licensed area, 12.018 acres.
- 30//12/13 kanal 6 marlaSultanpur (80)
- 30//12/2/21 kanalSultanpur (80)
- 30//16/1/22 kanal 16 marlaSultanpur (80)
- 30//17/14 kanalSultanpur (80)
Show the other 19 parcels
- 30//17/24 kanalSultanpur (80)
- 30//18/15 kanalSultanpur (80)
- 30//18/21 kanal 18 marlaSultanpur (80)
- 30//1915 marlaSultanpur (80)
- 30//2311 marlaSultanpur (80)
- 30//243 kanal 18 marlaSultanpur (80)
- 4//1211 marlaAhmadpur (76)
- 4//1817 marlaAhmadpur (76)
- 4//197 kanal 1 marlaAhmadpur (76)
- 4//228 kanalAhmadpur (76)
- 4//237 kanal 2 marlaAhmadpur (76)
- 4//24/12 kanal 6 marlaAhmadpur (76)
- 4//24/21 kanal 7 marlaAhmadpur (76)
- 9//28 kanalAhmadpur (76)
- 9//38 kanalAhmadpur (76)
- 9//4/1/11 kanal 15 marlaAhmadpur (76)
- 9//78 kanalAhmadpur (76)
- 9//88 kanalAhmadpur (76)
- 9//98 kanalAhmadpur (76)
The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.
From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source
Who owns this land today, or is it mortgaged?
The Bhumiq team checks it with you.
Check it yourself on jamabandi.nic.in
- Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
- Pick district Sonipat, then the tehsil and the village you want: Sultanpur (hadbast 80) or Ahmadpur (hadbast 76), tehsil Sonipat. The site lists villages in Hindi, so the hadbast number is the surer match.
- Pick the latest year, then a from the list here, such as 30//12/1.
- Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.
Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.
Layouts & payment plan
Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.
Site plan
1 fileLayout plan
1 fileAmong the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (5 in all), none is a building plan, a floor plan or a payment plan.
source: https://haryanarera.gov.in/view_project/project_preview_open/1522 · read 29 Oct 2026
The call is with the Bhumiq team. You need a free account so we can call you back.
Run due diligence on A P Real Estates
Its court cases, its DTCP licences and the source of each fact, free once you sign in.
Open the developer profileAs of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.