About this project

Key facts

Location
Gurugram
Registered by
VK & SONS BUILWELL PVT LTDthe company that filed it, for Vk And Sons Infratech
Timeline
  1. 5 Aug 2025Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 1 May 2030Registration valid toHARERA, read 4 Nov 2026
  3. 30 Oct 2030Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside8.35 acres in all, by use
  • Plots for sale4.618 acres · 55%
  • Roads1.845 acres · 22%
  • Land for community services, handed to the government0.835 acres · 10%
  • Parks and playgrounds0.633 acres · 8%
  • Shops and offices0.329 acres · 4%
  • Other usesas the form names them: Construction, Area0.089 acres · 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: SECTOR- 2 & 3 , PATAUDI

The builder

Its 3 projects in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 3

Questions buyers ask

Is PALM DRIVE 2 registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/1004/736/2025/107. Valid to 1 May 2030.

The source ↗
What is the possession timeline for PALM DRIVE 2?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 30 Oct 2030. Its registration runs to 1 May 2030; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around PALM DRIVE 2?From the records · HARERA, read 4 Nov 2026

PALM DRIVE 2 is in Gurugram; the site address declared to HARERA is Sector- 2 & 3 , Pataudi. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building PALM DRIVE 2?From the records · HARERA, read 4 Nov 2026

PALM DRIVE 2 is a Vk And Sons Infratech project, registered by its company VK & SONS BUILWELL PVT LTD.

The source ↗Vk And Sons Infratech's projects and court record

The records

What the registers hold for PALM DRIVE 2: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/1004/736/2025/107: Registered. Valid to 1 May 2030.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 134 OF 2025 is on the DTCP register, valid to 3 Aug 2030.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 5 Aug 2025.Declared to HARERA, read 29 Oct 2026
The court record of Vk And Sons Infratech’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 51 HARERA files, with the dates we read them
Registration no.
GGM/1004/736/2025/107
Registration valid till
1 May 2030
Declared possession
30 Oct 2030

Declared by the promoter to HARERA

Land area
8.3500 (Acre) (33,791.25 sq m)
FAR
the application prints 100, which is not a ratio
licence
134 of 2025 dated 4.8.2025
Estimated project cost
₹138.14 crore
Cost of land
₹87.56 crore
Layout plan, declared approved (field 5a)
5 Aug 2025
Construction to start
1 Nov 2025
Completion declared for
30 Oct 2030
Statutory approvals, as declared · 1

Statutory approvals, as declared

  • I. ZONING — declared: already been obtained (9 Sept 2025)
On file with HARERA · 51 files

On file with HARERA (51)

Plans

Site plan

1 file
Approved Site Plan12 Sept 2025

Layout plan

1 file
Latest Layout Plan20 Nov 2025

Zoning plan

1 file
Zoning Plan20 Nov 2025

Demarcation plan

2 files
Demarcation Plan20 Nov 2025Demarcation Plan Letter20 Nov 2025

Services

Sewerage and drainage

4 files
SPE Sewer System20 Nov 2025Assurance of Storm Water20 Nov 2025SPE Storm Water System20 Nov 2025Assurance of Sewerage20 Nov 2025

Water supply

3 files
SPE Flushing Water Supply20 Nov 2025Assurance for Construction Water20 Nov 2025Assurance of Water Supply20 Nov 2025

Electricity

1 file
Electrical Load Availability20 Nov 2025

Roads

1 file
SPE Road Layout20 Nov 2025

Service plans

2 files
Service Estimates20 Nov 2025Service Plans on the Layout20 Nov 2025

Approvals and clearances

DTCP licence

3 files
Licence Copy with Land Schedule20 Nov 2025LC-IV20 Nov 2025LOI20 Nov 2025

Other NOCs and clearances

2 files
Aravali NOC20 Nov 2025Forest NOC20 Nov 2025

Land records

Land records

8 files
Revenue Record Entry of Licence and Collaboration20 Nov 2025Aks-Shazra20 Nov 2025Non- Encumbrance Certificate20 Nov 2025

Sales papers

Allotment and sale agreements

3 files
Draft Allotment Letter20 Nov 2025Draft BBA20 Nov 2025Draft Conveyance Deed20 Nov 2025

Money

Accounts and finance

7 files
Non-Default Certificate from a CA20 Nov 2025CA Certificate Cost Incurred20 Nov 2025CA Certificate for Net Worth20 Nov 2025

Timeline and progress

Construction schedule

1 file
PERT Chart20 Nov 2025

Progress and photographs

1 file
Quarterly Fund Flow20 Nov 2025

The promoter’s papers

Declarations and affidavits

7 files
The Promoter’s Declaration on Affidavit20 Nov 2025Affidavit 4 2 L D20 Nov 2025Affidavit Non Applicability for Forest Land, Ncx, Powerline Shiftingand Tree Cutting20 Nov 2025

Company papers

1 file
BR for Authorisation of Bps for RERA Account Operation20 Nov 2025

HARERA’s orders

HARERA’s orders

1 file
Amendment in the Registration Certificate - Change of name of the Affordable Residential Plotted Colony under DDJAY Colony from "Palm Drive 2" to "VKS Pine Drive 2"7 May 2026

Other filings

Other filings

1 file
Auto Credit 10%20 Nov 2025

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

134 OF 2025 · VK AND SONS BUILDWELL PRIVATE LIMITED · PATAUDI

Licence valid to 3 Aug 2030

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 12 Sept 2025 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

134 OF 2025: 14 parcels, 8.35 acres in all, in Nerahera (hadbast 44), tehsil Pataudi.

The licence register prints the same licensed area, 8.35 acres.

  • 76//15/15 kanal 3 marla
  • 76//15/23 kanal 12 marla
  • 76//15/22 marla
  • 76//169 kanal 16 marla
Show the other 10 parcels
  • 76//25 min9 kanal 11 marla
  • 76//6/12 kanal 18 marla
  • 75//20/16 kanal 7 marla
  • 75//21/14 kanal
  • 77//15/14 kanal 16 marla
  • 77//5 min5 kanal 10 marla
  • 77//6 min7 kanal 18 marla
  • 78//1/1 min3 kanal 19 marla
  • 78//10/2/2 min1 kanal 9 marla
  • 78//11/1/1/11 kanal 15 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Nerahera (hadbast 44), tehsil Pataudi. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 76//15/1.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan12 Sept 2025

Layout plan

1 file
Latest Layout Plan20 Nov 2025

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (51 in all), none is a building plan, a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/3705 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Vk And Sons Infratech

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.