Key facts

Carpet area
947 sq ft
In m²about 88–88 m², as declared
Timeline
  1. 21 Dec 2020Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 14 Aug 2026Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

16homes, 947 to 947 sq ft of carpet area
  • Under 1,000 sq ft947 sq ft16

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft. Left out: 1 row of a single unit, because the form lists homes, shops and other buildings in one table.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside1.08 acres in all, by use
  • Roads0.702 acres · 65%
  • Apartment buildings0.378 acres · 35%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • FloorsStaircase area - local stone basement - RAW floor (unfinished) corridors - local stone plaza - commercial tile/pavar tiles/local stone
  • WallsBasement - unfinished block WORK internal wall - unfinished block WORK outer wall - painted (acrylic emulsion)
  • WindowsUPVC/power coated with 12 MM thick toughened glass
  • Main doorFlush/SKIN molded/toughened glass doors
  • Electrical fittingsModular switched - anchor ROMA/legrand/havells common area/corridor LED lights
  • Water storageUnder ground tanks

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: B-BLOCK, SUSHANT CITY, SECTOR 19, PANIPAT

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Other register states: 1

Questions buyers ask

Is PANIPAT HI-STREET registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as HRERA-PKL-PNP-263-2021. The register’s record shows an end date of 14 Aug 2026. The register shows it as: Registration lapsed.

The source ↗
What is the possession timeline for PANIPAT HI-STREET?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 14 Aug 2026. Its registration runs to 14 Aug 2026; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around PANIPAT HI-STREET?From the records · HARERA, read 4 Nov 2026

PANIPAT HI-STREET is in Panipat; the site address declared to HARERA is B-Block, Sushant City, Sector 19, Panipat. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building PANIPAT HI-STREET?From the records · HARERA, read 4 Nov 2026

PANIPAT HI-STREET is a Bawa Kapoor project.

The source ↗Bawa Kapoor's projects and court record

The records

What the registers hold for PANIPAT HI-STREET: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-PNP-263-2021: Registration lapsed. The register’s record shows an end date of 14 Aug 2026.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Plans approved, as the developer declared: layout plan 21 Dec 2020, building plans 21 Dec 2020.Declared to HARERA, read 29 Oct 2026
The court record of Bawa Kapoor’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Registration lapsed

    The register’s record shows an end date of 14 Aug 2026. HARERA Panchkula, read 4 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 6 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-PNP-263-2021
Registration valid till
14 Aug 2026
Declared possession
14 Aug 2026

Declared by the promoter to HARERA

Land area
1.08 (Acre) (4,370.6 sq m)
FAR
1.05 proposed of 1.05 permissible
licence
Commercial Site in Licensed Colony Sushant City Sector 19 Panipat Haryana
Estimated project cost
₹8.57 crore
Cost of land
₹0.22 crore
Layout plan, declared approved (field 5a)
21 Dec 2020
Building plans, declared approved
21 Dec 2020
Construction to start
15 Aug 2021
Completion declared for
14 Aug 2026
Declared inventory · 2 types

Declared inventory

  • Apartment/Shops/Other Buildings · 16 units · 88 sq m carpet · one flat
  • Apartment/Shops/Other Buildings · 1 unit · 104 sq m carpet · one flat
Statutory approvals, as declared · 1

Statutory approvals, as declared

  • I. APPROVAL OF STANDARD DESIGN OF COMMERCIAL SITE OF 1.08 ACRES — declared: already been obtained (21 Dec 2020)
On file with HARERA · 6 files

On file with HARERA (6)

Plans

Site plan

1 file
Approved Site Plan5 Aug 2021

Layout plan

1 file
Latest Layout Plan5 Aug 2021

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule5 Aug 2021

Land records

Land records

1 file
Sale Deed5 Aug 2021

Money

Accounts and finance

1 file
Non-Default Certificate from a CA5 Aug 2021

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit5 Aug 2021

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

The promoter declared Commercial Site in Licensed Colony Sushant City Sector 19 Panipat Haryana. We could not read a licence number from that, so nothing is claimed about it here.

declared in the registration application (Form REP-I), Panchkula bench · submitted 10 Aug 2021 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan5 Aug 2021

Layout plan

1 file
Latest Layout Plan5 Aug 2021

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (6 in all), none is a building plan, a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1658 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Bawa Kapoor

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.