Key facts

Location
Gurugram
Registered by
M V BUILDCON PRIVATE LIMITEDthe company that filed it, for V & M Realcon
Timeline
  1. 29 Dec 2023Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 25 Jul 2028Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside8.19 acres in all, by use
  • Plots for sale4.25 acres · 52%
  • Roads1.98 acres · 24%
  • Land for community services, handed to the government0.97 acres · 12%
  • Parks and playgrounds0.66 acres · 8%
  • Shops and offices0.33 acres · 4%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: SECTOR-7, SOHNA

The builder

Its 6 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 3
  • Registered, no OC or CC yet: 3

Questions buyers ask

Is PRECORE GREENS registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/894/626/2024/121. Valid to 25 Jul 2028.

The source ↗
What is the possession timeline for PRECORE GREENS?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 25 Jul 2028. Its registration runs to 25 Jul 2028; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around PRECORE GREENS?From the records · HARERA, read 4 Nov 2026

PRECORE GREENS is in Gurugram; the site address declared to HARERA is Sector-7, Sohna. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building PRECORE GREENS?From the records · HARERA, read 4 Nov 2026

PRECORE GREENS is a V & M Realcon project, registered by its company M V BUILDCON PRIVATE LIMITED.

The source ↗V & M Realcon's projects and court record

The records

What the registers hold for PRECORE GREENS: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/894/626/2024/121: Registered. Valid to 25 Jul 2028.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Plans approved, as the developer declared: layout plan 29 Dec 2023.Declared to HARERA, read 29 Oct 2026
The court record of V & M Realcon’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 47 HARERA files, with the dates we read them
Registration no.
GGM/894/626/2024/121
Registration valid till
25 Jul 2028
Declared possession
25 Jul 2028

Declared by the promoter to HARERA

Land area
8.19 (Acre) (33,143.75 sq m)
FAR
1 proposed of 1 permissible
licence
Memo No.DULB/CTP/TP/SOHNA/8922 dated 26.07.2023
Estimated project cost
₹56.26 crore
Cost of land
₹34.27 crore
Layout plan, declared approved (field 5a)
29 Dec 2023
Construction to start
1 Oct 2024
Completion declared for
25 Jul 2028
Statutory approvals, as declared · 4

Statutory approvals, as declared

  • I. LICENSE MEMO NO. DULB/CTP/TP/SOHNA/8922 DATED 26.07.2023 — declared: already been obtained (26 Jul 2023)
  • II. ZONING PLAN MEMO NO. DULB/CTP/TP/SOHNA/2023/11411 DATED 29.12.2023 — declared: already been obtained (29 Dec 2023)
  • III. DEMARCATION PLAN APPROVAL LETTER REFERENCE NO. MENTIONED IN ZONING PLAN APPROVAL LETTER VIDE MEMO NO. DULB/CTP/TP/SOHNA/2023/11411 DATED 29.12.2023 — declared: already been obtained (29 Dec 2023)
  • IV. SERVICE PLAN ESTIMATES — declared: already been obtained (21 Oct 2024)
On file with HARERA · 47 files

On file with HARERA (47)

Plans

Site plan

1 file
Approved Site Plan16 Jul 2024

Layout plan

1 file
Latest Layout Plan18 Dec 2024

Zoning plan

2 files
Zoning Plan Approval Letter20 Sept 2024Zoning Plan16 Jul 2024

Demarcation plan

1 file
Demarcation Plan22 Jul 2024

Services

Sewerage and drainage

2 files
Sewerage Network Plan18 Dec 2024Storm Water Drainage Plan18 Dec 2024

Water supply

2 files
Water Supply Plan18 Dec 2024Flushing Water Network18 Dec 2024

Electricity

1 file
Electric Load Sanction Letter18 Dec 2024

Roads

1 file
Road Network Plan18 Dec 2024

Service plans

2 files
Service Plan Estimate Approval18 Dec 2024Service Plans on the Layout20 Sept 2024

Approvals and clearances

DTCP licence

2 files
LOI18 Sept 2024Licence Copy with Land Schedule16 Jul 2024

Other NOCs and clearances

3 files
Forest NOC23 Sept 2024Affidivat for Tree Cutting, NCZ, Powerline21 Sept 2024Assurance/noc for Water, Sewerage and Storm20 Sept 2024

Land records

Land records

13 files
Land Title Search Report18 Dec 2024Sale Deed 123 Sept 2024Sale Deed 323 Sept 2024

Sales papers

Allotment and sale agreements

2 files
Revised BBA18 Dec 2024Revised Allotment Letter18 Dec 2024

Money

Accounts and finance

7 files
Non-Default Certificate from a CA18 Dec 2024CA Certificate for Inventory Details18 Dec 2024CA Certificate for Financial Details18 Dec 2024

Timeline and progress

Construction schedule

1 file
PERT Chart20 Sept 2024

The promoter’s papers

Declarations and affidavits

3 files
The Promoter’s Declaration on Affidavit21 Sept 2024Promoter Affidavit for RERA Bank Account21 Sept 2024Bank Undertaking20 Sept 2024

Company papers

3 files
BR Authorised Signatory23 Sept 2024TAN20 Sept 2024GST18 Sept 2024

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

The promoter declared Memo No.DULB/CTP/TP/SOHNA/8922 dated 26.07.2023. We could not read a licence number from that, so nothing is claimed about it here.

declared in the registration application (Form REP-I), Gurugram bench · submitted 24 Sept 2024 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan16 Jul 2024

Layout plan

1 file
Latest Layout Plan18 Dec 2024

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (47 in all), none is a building plan, a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/2891 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on V & M Realcon

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.