Possession 31 Dec 2025 · as the developer declared it to HARERA

About this project

Key facts

Registered by
ETERNAL SUNSHINE INFRA LLPthe company that filed it, for Eternal Sunshine Infra
Timeline
  1. 20 Oct 2022Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 12 Jan 2023Building plans approveddeclared to HARERA, read 29 Oct 2026
  3. 31 Dec 2025Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside11,812 m² in all, by use
  • Parking6,136 m² · 52%
  • Plots for sale3,941 m² · 33%
  • Roads1,458 m² · 12%
  • Green belts276 m² · 2%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: VILLAGE- BARKATABAD, SECTOR-40, BAHADURGARH,

The builder

Its 5 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 2
  • Registered, no OC or CC yet: 2
  • Other register states: 1

Questions buyers ask

Is ROYAL GREEN COURTYARD 40 registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as HRERA-PKL-JJR-413-2023. The register’s record shows an end date of 31 Dec 2025. The register shows it as: Registration lapsed.

The source ↗
What is the possession timeline for ROYAL GREEN COURTYARD 40?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Dec 2025. Its registration runs to 31 Dec 2025; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around ROYAL GREEN COURTYARD 40?From the records · HARERA, read 4 Nov 2026

ROYAL GREEN COURTYARD 40 is in Jhajjar; the site address declared to HARERA is Village- Barkatabad, Sector-40, Bahadurgarh,. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building ROYAL GREEN COURTYARD 40?From the records · HARERA, read 4 Nov 2026

ROYAL GREEN COURTYARD 40 is a Eternal Sunshine Infra project, registered by its company ETERNAL SUNSHINE INFRA LLP.

The source ↗Eternal Sunshine Infra's projects and court record

The records

What the registers hold for ROYAL GREEN COURTYARD 40: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-JJR-413-2023: Registration lapsed. The register’s record shows an end date of 31 Dec 2025.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 172 OF 2022 is on the DTCP register, valid to 21 Oct 2027.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 20 Oct 2022, building plans 12 Jan 2023.Declared to HARERA, read 29 Oct 2026
The court record of Eternal Sunshine Infra’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Registration lapsed

    The register’s record shows an end date of 31 Dec 2025. HARERA Panchkula, read 4 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 10 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-JJR-413-2023
Registration valid till
31 Dec 2025
Declared possession
31 Dec 2025

Declared by the promoter to HARERA

Land area
2.91875 (Acre) (11,811.76 sq m)
FAR
the application prints 104.99, which is not a ratio
licence
172 of 2022 (22-10-2022)
Estimated project cost
₹21.89 crore
Cost of land
₹10.62 crore
Layout plan, declared approved (field 5a)
20 Oct 2022
Building plans, declared approved
12 Jan 2023
Construction to start
23 Oct 2022
Completion declared for
31 Dec 2025
Statutory approvals, as declared · 2

Statutory approvals, as declared

  • I. ENVIRONMENTAL CLEARANCE — declared: yet to file for approval
  • II. FOREST NOC — declared: yet to file for approval
On file with HARERA · 10 files

On file with HARERA (10)

Plans

Site plan

1 file
Approved Site Plan16 Jan 2023

Layout plan

1 file
Latest Layout Plan16 Jan 2023

Zoning plan

1 file
Zoning Plan16 Jan 2023

Demarcation plan

1 file
Demarcation Plan16 Jan 2023

Services

Service plans

1 file
Service Plans on the Layout16 Jan 2023

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule16 Jan 2023

Money

Accounts and finance

3 files
Cash Flow Statement18 Jan 2023CA Certificate on the Application’s Figures16 Jan 2023Non-Default Certificate from a CA16 Jan 2023

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit18 Jan 2023

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

172 OF 2022 · Eternal Sunshine Infra LLP · BAHADURGARH

Licence valid to 21 Oct 2027

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 19 Jan 2023 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

172 OF 2022: 7 parcels, 2.8938 acres in all, in Barktabad (hadbast 63), tehsil Bahadurgarh.

The licence register prints the licensed area as 2.9188 acres.

  • 41//14/1 min4 kanal
  • 41//16/2 min1 kanal 13 marla
  • 41//17 min4 kanal 8 marla
  • 41//24/2 min4 kanal 8 marla
Show the other 3 parcels
  • 41//25/1 min18 marla
  • 41//25/2 min6 kanal 16 marla
  • 42//21 min1 kanal

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Jhajjar, then the tehsil and the village: Barktabad (hadbast 63), tehsil Bahadurgarh. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 41//14/1 min.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan16 Jan 2023

Layout plan

1 file
Latest Layout Plan16 Jan 2023

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (10 in all), none is a building plan, a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/2195 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Eternal Sunshine Infra

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.