SAFFRON ESTATE

by Ansal Properties & Infrastructure · Sonipat

Not on our price list yet

Possession 30 Aug 2023 · as the developer declared it to HARERA

About this project

Key facts

Registered by
SAMYAK PROPERTIES AND INFRASTRUCTURE PRIVATE LIMITEDthe company that filed it, for Ansal Properties & Infrastructure
Timeline
  1. 1 Aug 2019Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 30 Aug 2023Possession, as declareddeclared to HARERA, read 29 Oct 2026
  3. 31 Aug 2023Registration valid toHARERA, read 4 Nov 2026

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: VILLAGE LIWAN SECTOR 35

The builder

Its 22 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 2
  • Registered, no OC or CC yet: 2
  • Other register states: 18

Questions buyers ask

Is SAFFRON ESTATE registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as HRERA-PKL-SNP-156-2019. Ended 31 Aug 2023. The register shows it as: Registration expired.

The source ↗
What is the possession timeline for SAFFRON ESTATE?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 30 Aug 2023. Its registration runs to 31 Aug 2023; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around SAFFRON ESTATE?From the records · HARERA, read 4 Nov 2026

SAFFRON ESTATE is in Sonipat; the site address declared to HARERA is Village Liwan Sector 35. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building SAFFRON ESTATE?From the records · HARERA, read 4 Nov 2026

SAFFRON ESTATE is a Ansal Properties & Infrastructure project, registered by its company SAMYAK PROPERTIES AND INFRASTRUCTURE PRIVATE LIMITED.

The source ↗Ansal Properties & Infrastructure's projects and court record

The records

What the registers hold for SAFFRON ESTATE: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-SNP-156-2019: Registration expired. Ended 31 Aug 2023.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 90 OF 2019 is on the DTCP register: Licence ended, LC-IX linked; the register prints its validity to 6 Aug 2024.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 1 Aug 2019.Declared to HARERA, read 29 Oct 2026
The court record of Ansal Properties & Infrastructure’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Registration expired

    Ended 31 Aug 2023. HARERA Panchkula, read 4 Nov 2026. Source

  • Amber flag: Licence 90 OF 2019 validity ended

    Named in this project’s application. Valid to 6 Aug 2024. The register links a completion certificate (LC-IX), dated 1 Aug 2023, against this licence. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 13 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-SNP-156-2019
Registration valid till
31 Aug 2023
Declared possession
30 Aug 2023

Declared by the promoter to HARERA

Land area
5.67361 (Acre) (22,960.29 sq m)
FAR
0 proposed of 0 permissible
licence
90 OF 2019
Estimated project cost
₹20.14 crore
Cost of land
₹6.43 crore
Layout plan, declared approved (field 5a)
1 Aug 2019
Construction to start
1 Oct 2019
Completion declared for
30 Aug 2023
Statutory approvals, as declared · 2

Statutory approvals, as declared

  • I. LICENSE — declared: already been obtained (7 Aug 2019)
  • II. LAYOUT PLAN — declared: already been obtained (1 Aug 2019)
On file with HARERA · 13 files

On file with HARERA (13)

Plans

Site plan

1 file
Approved Site Plan13 Aug 2019

Layout plan

1 file
Latest Layout Plan20 Aug 2019

Zoning plan

1 file
Zoning Plan20 Aug 2019

Demarcation plan

1 file
Demarcation Plan20 Aug 2019

Building plans

1 file
Approved Building Plans, Full Set13 Aug 2019

Services

Service plans

1 file
Service Plans on the Layout20 Aug 2019

Approvals and clearances

Completion certificate (CC)

1 file
completion certificate uploaded10 Sept 2024

DTCP licence

1 file
Licence Copy with Land Schedule20 Aug 2019

Land records

Land records

1 file
Revenue Record Entry of Licence and Collaboration13 Aug 2019

Money

Accounts and finance

3 files
CA Certificate on the Application’s Figures27 Aug 2019Non-Default Certificate from a CA27 Aug 2019Cash Flow Statement26 Aug 2019

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit20 Aug 2019

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

90 OF 2019 · Samyak Properties and Infrastructure Pvt. Ltd. · Sonipat

Licence valid to 6 Aug 2024

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 27 Aug 2019 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

90 OF 2019: 9 parcels, 5.6736 acres in all, in Liwan (hadbast 65), tehsil Sonipat.

The licence register prints the same licensed area, 5.674 acres.

  • 6//241 kanal 15 marla
  • 15//115 kanal 11 marla
  • 15//127 kanal 4 marla 7 sarsai
  • 15//312 marla
Show the other 5 parcels
  • 15//46 kanal 12 marla
  • 15//67 kanal 12 marla
  • 15//78 kanal
  • 15//86 kanal 10 marla
  • 15//91 kanal 11 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Sonipat, then the tehsil and the village: Liwan (hadbast 65), tehsil Sonipat. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 6//24.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan13 Aug 2019

Layout plan

1 file
Latest Layout Plan20 Aug 2019

Building plans

1 file
Approved Building Plans, Full Set13 Aug 2019

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (13 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/810 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Ansal Properties & Infrastructure

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.