Not on our price list yet

Possession 31 Dec 2026 · as the developer declared it to HARERA

About this project

Key facts

Registered by
SANKALPINFRALINE LLPthe company that filed it, for Sankalpinfraline
Timeline
  1. 20 Jan 2022Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 31 Dec 2026Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside5.7 acres in all, by use
  • Plots for sale2.913 acres · 51%
  • Roads1.779 acres · 31%
  • Land for community services, handed to the government0.571 acres · 10%
  • Shops and offices0.225 acres · 4%
  • Sewage and waste treatment0.111 acres · 2%
  • Other usesas the form names them: UGT (underground water tank), Milk0.056 acres · under 1%
  • Parks and playgrounds0.043 acres · under 1%
  • Electricity sub-station0.002 acres · under 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: SECTOR 15

The builder

Its 2 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 1
  • Registered, no OC or CC yet: 1

Questions buyers ask

Is SANKALP CITY registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as HRERA-PKL-JND-307-2022. Valid to 31 Dec 2026.

The source ↗
What is the possession timeline for SANKALP CITY?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Dec 2026. Its registration runs to 31 Dec 2026; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around SANKALP CITY?From the records · HARERA, read 4 Nov 2026

SANKALP CITY is in Jind; the site address declared to HARERA is Sector 15. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building SANKALP CITY?From the records · HARERA, read 4 Nov 2026

SANKALP CITY is a Sankalpinfraline project, registered by its company SANKALPINFRALINE LLP.

The source ↗Sankalpinfraline's projects and court record

The records

What the registers hold for SANKALP CITY: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-JND-307-2022: Registered. Valid to 31 Dec 2026.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 8 OF 2022 is on the DTCP register: Licence ends soon; the register prints its validity to 19 Jan 2027.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 20 Jan 2022.Declared to HARERA, read 29 Oct 2026
The court record of Sankalpinfraline’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Registration ends soon

    Valid to 31 Dec 2026. HARERA Panchkula, read 4 Nov 2026. Source

  • Amber flag: Licence 8 OF 2022 ends soon

    Named in this project’s application. Valid to 19 Jan 2027. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 14 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-JND-307-2022
Registration valid till
31 Dec 2026
Declared possession
31 Dec 2026

Declared by the promoter to HARERA

Land area
5.70 (Acre) (23,067.08 sq m)
FAR
0 proposed of 2 permissible
licence
08 of 2022
Estimated project cost
₹14.57 crore
Cost of land
₹11.57 crore
Layout plan, declared approved (field 5a)
20 Jan 2022
Construction to start
1 Apr 2022
Completion declared for
31 Dec 2026
Statutory approvals, as declared · 2

Statutory approvals, as declared

  • I. LAYOUT PLAN — declared: already been obtained (20 Jan 2022)
  • II. DEMARCATION PLAN — declared: applied for but yet to receive (15 Feb 2022)
On file with HARERA · 14 files

On file with HARERA (14)

Plans

Site plan

1 file
Approved Site Plan4 Jan 2022

Layout plan

1 file
Latest Layout Plan1 Feb 2022

Zoning plan

1 file
Zoning Plan31 Mar 2022

Demarcation plan

1 file
Demarcation Plan31 Mar 2022

Building plans

2 files
Standard Design of SCO20 Mar 2026Approved Building Plans, Full Set4 Jan 2022

Services

Service plans

1 file
Service Plans on the Layout1 Feb 2022

Approvals and clearances

Completion certificate (CC)

1 file
Completion Certificate20 Mar 2026

DTCP licence

1 file
Licence Copy with Land Schedule1 Feb 2022

Land records

Land records

1 file
Revenue Record Entry of Licence and Collaboration11 Mar 2022

Money

Accounts and finance

3 files
CA Certificate on the Application’s Figures4 Mar 2022Non-Default Certificate from a CA4 Mar 2022Cash Flow Statement4 Jan 2022

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit31 Mar 2022

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

8 OF 2022 · Sankalp Infraline LLP · Jind

Licence valid to 19 Jan 2027

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 31 Mar 2022 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

8 OF 2022: 12 parcels, 5.7 acres in all, in Jind (hadbast 79), tehsil Jind.

The licence register prints the same licensed area, 5.7 acres.

  • 282//10/38 marla
  • 282//11/25 kanal
  • 282//125 kanal 9 marla
  • 282//131 kanal 5 marla
Show the other 8 parcels
  • 282//18/1/210 marla
  • 282//2/27 kanal 2 marla
  • 282//20/14 marla
  • 282//3/27 kanal 2 marla
  • 282//4/24 kanal 3 marla
  • 282//76 marla
  • 282//86 kanal 3 marla
  • 282//98 kanal

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 23 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Jind, then the tehsil and the village: Jind (hadbast 79), tehsil Jind. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 282//10/3.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan4 Jan 2022

Layout plan

1 file
Latest Layout Plan1 Feb 2022

Building plans

2 files
Standard Design of SCO20 Mar 2026Approved Building Plans, Full Set4 Jan 2022

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (14 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1822 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Sankalpinfraline

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.