Skip to content

SILVER COUNTY

by Ivory Buildtech · Gurugram

Not on our price list yet

Possession 5 Jan 2028 · as the developer declared it to HARERA

About this project

Key facts

Location
Gurugram
Registered by
IVORY BUILDTECH PVT. LTD.the company that filed it, for Ivory Buildtech
Timeline
  1. 9 Jan 2023Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 5 Jan 2028Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside5.025 acres in all, by use
  • Plots for sale2.495 acres · 50%
  • Roads1.456 acres · 29%
  • Land for community services, handed to the government0.503 acres · 10%
  • Parks and playgrounds0.377 acres · 8%
  • Shops and offices0.195 acres · 4%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: VILLAGE WAZIRPUR, SECTOR 95A, DISTRICT GURUGRAM, HARYANA

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 1

Questions buyers ask

Is SILVER COUNTY registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/729/461/2023/73. Valid to 5 Jan 2028.

The source ↗
What is the possession timeline for SILVER COUNTY?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 5 Jan 2028. Its registration runs to 5 Jan 2028; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around SILVER COUNTY?From the records · HARERA, read 4 Nov 2026

SILVER COUNTY is in Gurugram; the site address declared to HARERA is Village Wazirpur, Sector 95a, District Gurugram, Haryana. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building SILVER COUNTY?From the records · HARERA, read 4 Nov 2026

SILVER COUNTY is a Ivory Buildtech project, registered by its company IVORY BUILDTECH PVT. LTD..

The source ↗Ivory Buildtech's projects and court record

The records

What the registers hold for SILVER COUNTY: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/729/461/2023/73: Registered. Valid to 5 Jan 2028.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 03 OF 2023 is on the DTCP register, valid to 5 Jan 2028.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 9 Jan 2023.Declared to HARERA, read 29 Oct 2026
The court record of Ivory Buildtech’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 14 HARERA files, with the dates we read them
Registration no.
GGM/729/461/2023/73
Registration valid till
5 Jan 2028
Declared possession
5 Jan 2028

Declared by the promoter to HARERA

Land area
5.025 (Acre) (20,335.45 sq m)
FAR
1 proposed of 1 permissible
licence
Licence Number 03 of 2023 Dated 06.01.2023
Estimated project cost
₹36.22 crore
Cost of land
₹18.15 crore
Layout plan, declared approved (field 5a)
9 Jan 2023
Construction to start
15 Feb 2023
Completion declared for
5 Jan 2028
Statutory approvals, as declared · 3

Statutory approvals, as declared

  • I. 1. LICENCE NO. 03 OF 2023 — declared: already been obtained (6 Jan 2023)
  • II. LAYOUT PLAN — declared: already been obtained (9 Jan 2023)
  • III. ZONING PLAN — declared: already been obtained (5 May 2023)
On file with HARERA · 14 files

On file with HARERA (14)

Plans

Site plan

1 file
Approved Site Plan24 Jan 2023

Layout plan

1 file
Latest Layout Plan24 Jan 2023

Zoning plan

1 file
Zoning Plan19 Jul 2023

Demarcation plan

1 file
Demarcation Plan19 Jul 2023

Services

Sewerage and drainage

2 files
Service Plan- Sewerage System20 Jul 2023Service Plan- Strom Water Drainage System20 Jul 2023

Water supply

1 file
Service Plan- Water Supply Scheme20 Jul 2023

Roads

1 file
Service Plan- Roads20 Jul 2023

Service plans

1 file
Service Estimates19 Jul 2023

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule19 Jul 2023

Land records

Land records

1 file
Revenue Record Entry of Licence and Collaboration19 Jul 2023

Money

Accounts and finance

2 files
CA Certificate on the Application’s Figures19 Jul 2023Non-Default Certificate from a CA24 Apr 2023

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit24 Apr 2023

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

03 OF 2023 · Ivory Buildtech Pvt. Ltd. · GURGAON-MANESAR

Licence valid to 5 Jan 2028

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 24 Apr 2023 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

03 OF 2023: 16 parcels, 5.025 acres in all, in Wazirpur (hadbast 115), tehsil Harsaru.

The licence register prints the same licensed area, 5.025 acres.

  • 59//21/12 kanal 4 marla
  • 59//21/35 kanal
  • 59//22/13 kanal 8 marla
  • 59//22/23 kanal 8 marla
Show the other 12 parcels
  • 59//231 kanal
  • 60//25/2/2/28 marla
  • 65//15/2/1/12 kanal 7 marla
  • 66//1/1/21 kanal 15 marla
  • 66//10/12 kanal 8 marla
  • 66//11/1/24 kanal 12 marla
  • 66//2/13 kanal 8 marla
  • 66//2/24 kanal
  • 66//20/2/1/19 marla
  • 66//9/1/1/14 kanal
  • 66//9/1/1/25 marla
  • 66//9/21 kanal 12 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Wazirpur (hadbast 115), tehsil Harsaru. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 59//21/1.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan24 Jan 2023

Layout plan

1 file
Latest Layout Plan24 Jan 2023

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (14 in all), none is a building plan, a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/2327 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Ivory Buildtech

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.