Skip to content

Skyz

by Ramprastha Promoters and Developers · Sector 37D, Gurugram

Not on our price list yet

About this project

Key facts

Location
Sector 37D, Gurugram0.8 km from Dwarka Expressway, in a straight line
Carpet area
1,396–1,680 sq ft
In m²about 130–156 m², as declared
Registered
17 Oct 2017
Registered by
RAMPRASTHA PROMOTERS AND DEVELOPERS PVT LTDthe company that filed it, for Ramprastha Promoters and Developers
Timeline
  1. 7 Jan 2011Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 29 Jun 2011Building plans approveddeclared to HARERA, read 29 Oct 2026
  3. 17 Oct 2017Registered with HARERAHARERA, read 3 Nov 2026
  4. 31 Dec 2023Registration valid toHARERA, read 3 Nov 2026

Homes on offer

The homes the developer declared to HARERA, by size.

684homes, 1,396 to 1,680 sq ft of carpet area
  • 1,000–1,500 sq ft1,396–1,434 sq ft532
  • 1,500–2,000 sq ft1,680 sq ft152

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside29,258 m² in all, by use
  • Apartment buildings20,283 m² · 69%
  • Parks and playgrounds2,258 m² · 8%
  • Other usesas the form names them: Water supply system, Strom water drainage, Electricity supply system, Street light, STP (sewage treatment plant), Underground water tank1,596 m² · 5%
  • Roads1,582 m² · 5%
  • Shops and offices931 m² · 3%
  • Parking925 m² · 3%
  • Pavements791 m² · 3%
  • Club house445 m² · 2%
  • Sewage and waste treatment407 m² · 1%
  • Electricity sub-station40 m² · under 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningSplit AC
  • KitchenSingle level CP fittings, stainless sink with drain board
  • Lifts3 lifts in each tower
  • FloorsMaster bedroom - laminated wooden flooring living / dining / lobby - vitrified tiles other bedrooms - vitrified tiles balcony / terraces - anti skid tiles kitchen / toilets - anti skid tiles servant room - ceramic tiles
  • WallsBedroom/living / dining / lobby - acrylic emulsion balcony / terraces - acrylic emulsion kitchen / toilets - combination of ceramic tiles servant room /utility - oil bound distemper
  • BathroomsSingle level CP fittings, white chinaware, shower partition only in master bath
  • WindowsUPVC windows
  • Main doorHardwood door frames veneered and polished/ SKIN moulded shutters / flush door shutter

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 37D, GurugramSector 37D, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Dwarka ExpresswayOpen, 17 Aug 20250.8 km
  • Delhi–Gurugram–SNB RRTS4.0 km
  • Sohna Elevated Corridor (NH-248A)6.3 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 4 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 2
  • Other register states: 2

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it; asking rates from the Bhumiq team price list, 16 Sep 2026.

Questions buyers ask

Is Skyz registered with HARERA?From the records · HARERA, read 3 Nov 2026

HARERA lists it as 320 OF 2017, registered on 17 Oct 2017. The register’s record shows an end date of 31 Dec 2023. The register shows it as: Registration lapsed.

The source ↗
How is the connectivity around Skyz?From the records · Map pin and road lines, read 6 Sep 2026

Skyz is in Sector 37D, Gurugram; the site address declared to HARERA is Ramprastha City, Sector-37 D, Gurugram. In a straight line it is about 0.8 km from Dwarka Expressway, 4.0 km from Delhi–Gurugram–SNB RRTS and 6.3 km from Sohna Elevated Corridor (NH-248A).

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building Skyz?From the records · HARERA, read 3 Nov 2026

Skyz is a Ramprastha Promoters and Developers project, registered by its company RAMPRASTHA PROMOTERS AND DEVELOPERS PVT LTD.

The source ↗Ramprastha Promoters and Developers's projects and court record
What protections do I have as a buyer?General guidance

Under the RERA Act, a registered project has to keep most of the money buyers pay in a separate bank account for that project, sell by carpet area, and stick to the plans it registered unless enough buyers agree to a change. If possession is late, a buyer can ask HARERA for interest or a refund. How this applies to your own purchase depends on your agreement, so ask a lawyer before you sign.

The records

What the registers hold for Skyz: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration 320 OF 2017: Registration lapsed. The register’s record shows an end date of 31 Dec 2023.HARERA, read 3 Nov 2026 · See it on HARERA ↗
  • Land licence 33 OF 2008 is on the DTCP register, valid to 18 Feb 2030.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 7 Jan 2011, building plans 29 Jun 2011.Declared to HARERA, read 29 Oct 2026
The court record of Ramprastha Promoters and Developers’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Registration lapsed

    The register’s record shows an end date of 31 Dec 2023. HARERA Gurugram, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 24 HARERA files, with the dates we read them
Registration no.
320 OF 2017
Registration date
17 Oct 2017
Registration valid till
31 Dec 2023

Declared by the promoter to HARERA

Land area
29262.82 (Sqr/mtrs)
FAR
the application prints 175, which is not a ratio
licence
33 of 2008(19-02-2008)
Estimated project cost
₹387.32 crore
Cost of land
₹5.02 crore
Layout plan, declared approved (field 5a)
7 Jan 2011
Building plans, declared approved
29 Jun 2011
Declared inventory · 5 types

Declared inventory

  • APARTMENT/SHOPS/OTHER BUILDINGS Type 3 BHK TYPE 1 · 228 units · 129.67 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type 3 BHK TYPE 2 · 228 units · 133.25 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type 3 BHK TYPE 3 · 38 units · 156.12 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type 3 BHK TYPE 4 · 114 units · 156.1 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type 3 BHK TYPE 5 · 76 units · 133.25 sq m carpet · one flat
Statutory approvals, as declared · 9

Statutory approvals, as declared

  • I. LICENCE RENEWAL — declared: already been obtained (18 Feb 2020)
  • II. ARAVALI NOC — declared: already been obtained (4 Apr 2011)
  • III. FOREST NOC — declared: already been obtained (18 Jan 2011)
  • IV. WATER ASSURANCE — declared: already been obtained (10 Jan 2018)
  • V. FIRE SCHEME APPROVAL RECEIPT — declared: already been obtained (31 Oct 2017)
  • VI. HEIGHT CLEARANCE — declared: already been obtained (5 May 2017)
  • VII. BUILDING PLAN BR III — declared: already been obtained (29 Jun 2011)
  • VIII. REVISED BUILDING PLAN APPROVAL BR III — declared: already been obtained (19 Aug 2021)
  • IX. ENVIRONMENTAL CLEARANCE — declared: applied for but yet to receive (31 Aug 2017)
On file with HARERA · 24 files

On file with HARERA (24)

Plans

Site plan

1 file
Approved Site Plan7 Dec 2019

Layout plan

1 file
Latest Layout Plan7 Dec 2019

Zoning plan

1 file
Zoning Plan7 Dec 2019

Demarcation plan

1 file
Demarcation Plan7 Dec 2019

Building plans

5 files
Approved Building Plans, Full Set7 Dec 2019Approved Building Plans, Full Set7 Dec 2019Approved Building Plans, Full Set7 Dec 2019

Services

Service plans

7 files
Service Plans on the Layout7 Dec 2019Service Plans on the Layout7 Dec 2019Service Plans on the Layout7 Dec 2019

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule7 Dec 2019

Land records

Land records

1 file
Revenue Record Entry of Licence and Collaboration7 Dec 2019

Money

Accounts and finance

3 files
Cash Flow Statement7 Dec 2019Non-Default Certificate from a CA7 Dec 2019CA Certificate on the Application’s Figures7 Dec 2019

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit7 Dec 2019

HARERA’s orders

HARERA’s orders

2 files
Extension No. 320 of 2017/7(3)/2021/4 Dated: 20.08.202122 Aug 2022Extension No. HARERA/GGM/REP/RC/320/ 2O17/EXT/122/2019 DATED-12.06.201928 May 2020

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

33 OF 2008 · RAMPRASTHA PROMOTERS DEVELOPERS PVT. LTD. · GURGAON-MANESAR

Licence valid to 18 Feb 2030

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 7 Dec 2019 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 3 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

33 OF 2008: 57 parcels, 60.511 acres in all, in Garauli kalan (hadbast 48), tehsil Kadipur.

The licence register prints the same licensed area, 60.51 acres.

  • rectangle 188, kila 188/14 biswa 4 biswansi
  • rectangle 188, kila 375/1893 biswa 7 biswansi
  • rectangle 188, kila 415/373/187/24 biswa 7 biswansi
  • rectangle 188, kila 416/374/187/18 biswa 5 biswansi
Show the other 53 parcels
  • rectangle 188, kila 377/2271 bigha 14 biswa
  • rectangle 188, kila 415/373/187/2/19 biswa 3 biswansi
  • rectangle 188, kila 417/374/187/2/213 biswa 10 biswansi
  • rectangle 188, kila 188/2 Min1 bigha 10 biswansi
  • rectangle 188, kila 375/189/2 Min4 biswa
  • rectangle 188, kila 1921 bigha 19 biswa
  • rectangle 188, kila 378/2271 bigha 15 biswa
  • rectangle 188, kila 379/229/12 biswa 14 biswansi
  • rectangle 188, kila 2222 bigha 15 biswa
  • rectangle 188, kila 2253 bigha 9 biswa
  • rectangle 188, kila 2262 biswa
  • rectangle 188, kila 2283 bigha 11 biswa
  • rectangle 188, kila 379/229/21 bigha 12 biswa 6 biswansi
  • rectangle 188, kila 2011 bigha 15 biswa
  • rectangle 188, kila 2031 bigha 5 biswa
  • rectangle 188, kila 2051 bigha 4 biswa
  • rectangle 188, kila 2312 bigha 11 biswa
  • rectangle 188, kila 2332 bigha 11 biswa
  • rectangle 188, kila 2353 bigha 7 biswa
  • rectangle 188, kila 74 min6 biswa 16 biswansi
  • rectangle 188, kila 75 min1 bigha 4 biswa
  • rectangle 188, kila 761 bigha 7 biswa
  • rectangle 188, kila 771 bigha 8 biswa
  • rectangle 188, kila 2041 bigha 4 biswa
  • rectangle 188, kila 781 bigha 10 biswa
  • rectangle 188, kila 2322 bigha 11 biswa
  • rectangle 188, kila 801 bigha 8 biswa
  • rectangle 188, kila 2021 bigha 12 biswa
  • rectangle 188, kila 2343 bigha 5 biswa
  • rectangle 188, kila 791 bigha 9 biswa
  • rectangle 188, kila 2302 bigha 10 biswa
  • rectangle 188, kila 1683 bigha 8 biswa
  • rectangle 188, kila 1713 bigha 11 biswa
  • rectangle 188, kila 1673 bigha 14 biswa
  • rectangle 188, kila 1723 bigha 18 biswa
  • rectangle 188, kila 1733 bigha 4 biswa
  • rectangle 188, kila 174 min1 bigha 6 biswa 5 biswansi
  • rectangle 188, kila 1694 bigha 13 biswa
  • rectangle 188, kila 170/1 min2 biswa
  • rectangle 188, kila 170/2 min3 bigha 2 biswa 15 biswansi
  • rectangle 188, kila 166/12 bigha 16 biswa
  • rectangle 188, kila 165/11 bigha 8 biswa
  • rectangle 188, kila 165/41 bigha 8 biswa
  • rectangle 188, kila 191/2 min1 bigha 5 biswa
  • rectangle 188, kila 161/22 bigha 4 biswa
  • rectangle 188, kila 176/21 bigha 13 biswa
  • rectangle 188, kila 1852 bigha 18 biswa
  • rectangle 188, kila 186 min1 bigha 3 biswa
  • rectangle 188, kila 175 min1 bigha
  • rectangle 188, kila 176/18 biswa
  • rectangle 188, kila 420/193/21 biswa 10 biswansi
  • rectangle 188, kila 416/374/1874 biswa 15 biswansi
  • rectangle 188, kila 418/374/18713 biswa

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Garauli kalan (hadbast 48), tehsil Kadipur. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as rectangle 188, kila 188/1.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate, residential flat
₹6,500 per sq ft

this sector, collector rates effective 1 Apr 2026, Kadipur tehsil. Source

Stamp duty is charged on the higher of the price and the collector rate value. The rate is the government's floor for duty, not a valuation: Bhumiq does not say what a flat is worth.

Worked out on this page. Not saved or sent.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan7 Dec 2019

Layout plan

1 file
Latest Layout Plan7 Dec 2019

Building plans

5 files
Approved Building Plans, Full Set7 Dec 2019Approved Building Plans, Full Set7 Dec 2019Approved Building Plans, Full Set7 Dec 2019Approved Building Plans, Full Set7 Dec 2019Approved Building Plans, Full Set7 Dec 2019

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (24 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1061 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Ramprastha Promoters and Developers

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.