Possession 30 Jan 2025 · as the developer declared it to HARERA

About this project

Key facts

Location
Gurugram
Carpet area
500–770 sq ft
In m²about 46–72 m², as declared
Registered by
NAMDEV CONSTRUCTION PVT. LTD.the company that filed it, for Namdev Construction
Timeline
  1. 7 May 2021Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 24 Sep 2021Building plans approveddeclared to HARERA, read 29 Oct 2026
  3. 30 Jan 2025Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

288homes, 500 to 770 sq ft of carpet area
  • Under 1,000 sq ft500–770 sq ft288

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside8,747 m² in all, by use
  • Apartment buildings8,747 m² · 100%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningProviding in living, dining & bedrooms
  • KitchenWhite WASH / OBD
  • LiftsBranded make
  • FloorsIPS flooring / tiles /wooden flooring / imported marble
  • WallsWhite WASH / OBD
  • BathroomsEauset
  • WindowsAluminium
  • Main doorPRE-laminated flush door/hdhmr door

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: GUAL PAHARI

The builder

Its 3 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 1
  • Other register states: 2

Questions buyers ask

Is SUNCITY VATSAL VALLEY INDEPENDENT FLOORS 1 registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/510/242/2021/78. The register’s record shows an end date of 30 Jan 2025. The register shows it as: Registration lapsed.

The source ↗
What is the possession timeline for SUNCITY VATSAL VALLEY INDEPENDENT FLOORS 1?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 30 Jan 2025. Its registration runs to 30 Jan 2025; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around SUNCITY VATSAL VALLEY INDEPENDENT FLOORS 1?From the records · HARERA, read 4 Nov 2026

SUNCITY VATSAL VALLEY INDEPENDENT FLOORS 1 is in Gurugram; the site address declared to HARERA is Gual Pahari. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building SUNCITY VATSAL VALLEY INDEPENDENT FLOORS 1?From the records · HARERA, read 4 Nov 2026

SUNCITY VATSAL VALLEY INDEPENDENT FLOORS 1 is a Namdev Construction project, registered by its company NAMDEV CONSTRUCTION PVT. LTD..

The source ↗Namdev Construction's projects and court record

The records

What the registers hold for SUNCITY VATSAL VALLEY INDEPENDENT FLOORS 1: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/510/242/2021/78: Registration lapsed. The register’s record shows an end date of 30 Jan 2025.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 21 OF 2021 is on the DTCP register: Licence ended, LC-IX linked; the register prints its validity to 4 Jan 2024.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 7 May 2021, building plans 24 Sep 2021.Declared to HARERA, read 29 Oct 2026
The court record of Namdev Construction’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Registration lapsed

    The register’s record shows an end date of 30 Jan 2025. HARERA Gurugram, read 4 Nov 2026. Source

  • Amber flag: Licence 21 OF 2021 validity ended

    Named in this project’s application. Valid to 4 Jan 2024. The register links a completion certificate (LC-IX), dated 1 Sep 2023, against this licence. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 23 HARERA files, with the dates we read them
Registration no.
GGM/510/242/2021/78
Registration valid till
30 Jan 2025
Declared possession
30 Jan 2025

Declared by the promoter to HARERA

Land area
2.161 (Acre) (8,745.26 sq m)
FAR
2.42 proposed of 2.64 permissible
licence
License No 21 of 2021 dated 07.05.2021
Estimated project cost
₹99.51 crore
Cost of land
₹38.18 crore
Layout plan, declared approved (field 5a)
7 May 2021
Building plans, declared approved
24 Sept 2021
Construction to start
15 Oct 2021
Completion declared for
30 Jan 2025
Declared inventory · 5 types

Declared inventory

  • Apartment/Shops/Other Buildings · 40 units · 71.53 sq m carpet · 10 towers · one flat
  • Apartment/Shops/Other Buildings · 48 units · 70.61 sq m carpet · 12 towers · one flat
  • Apartment/Shops/Other Buildings · 88 units · 70.61 sq m carpet · 22 towers · one flat
  • Apartment/Shops/Other Buildings · 80 units · 50.03 sq m carpet · 20 towers · one flat
  • Apartment/Shops/Other Buildings · 32 units · 46.45 sq m carpet · 8 towers · one flat
Statutory approvals, as declared · 11

Statutory approvals, as declared

  • I. LICENSE — declared: already been obtained (7 May 2021)
  • II. ZONING PLAN — declared: already been obtained (9 Jul 2021)
  • III. BUILDING PLAN — declared: already been obtained (24 Sept 2021)
  • IV. ELECTRICAL LOAD SANCTION ASSURANCE — declared: already been obtained (22 Mar 2021)
  • V. WATER SUPPLY ASSURANCE — declared: already been obtained (23 Mar 2021)
  • VI. SEWERAGE DISPOSAL ASSURANCE — declared: already been obtained (15 Mar 2021)
  • VII. SERVICE ESTIMATE APPROVAL — declared: already been obtained (28 Jul 2021)
  • VIII. FOREST NOC — declared: already been obtained (28 Oct 2020)
  • IX. NATURAL CONSERVATION ZONE NOC — declared: already been obtained (28 Aug 2021)
  • X. WILDLIFE NOC — declared: already been obtained (15 Feb 2021)
  • XI. ENVIRONMENTAL CLEARANCE ( APPROVED BY SEAC & APPROVAL FROM SEIAA AWAITED) — declared: applied for but yet to receive
On file with HARERA · 23 files

On file with HARERA (23)

Plans

Site plan

1 file
Approved Site Plan1 Oct 2021

Layout plan

1 file
Latest Layout Plan23 Sept 2021

Zoning plan

1 file
Zoning Plan1 Oct 2021

Demarcation plan

2 files
Super-Imposed Demarcation Plan13 Nov 2021Demarcation Plan1 Oct 2021

Building plans

10 files
Building Plan Letter- A 1 to A 1115 Nov 2021Building Plan Letter- A 12 to A2215 Nov 2021Building Plan Letter- A 23 to A3415 Nov 2021

Services

Service plans

2 files
Service Estimates Plans13 Nov 2021Service Plans on the Layout1 Oct 2021

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule23 Sept 2021

Land records

Land records

1 file
Revenue Record Entry of Licence and Collaboration1 Oct 2021

Money

Accounts and finance

3 files
Cash Flow Statement13 Nov 2021Non-Default Certificate from a CA1 Oct 2021CA Certificate on the Application’s Figures1 Oct 2021

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit13 Nov 2021

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

21 OF 2021 · Namdev Construction Pvt. Ltd. · GWAL PAHARI

Licence valid to 4 Jan 2024

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 1 Oct 2021 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

21 OF 2021: 16 parcels, 9.5 acres in all, in Gwal pahari (hadbast 77), tehsil Wazirabad.

The licence register prints the same licensed area, 9.5 acres.

  • 7//25/15 kanal 17 marla
  • 7//25/22 kanal 3 marla
  • 7//25/31 kanal 1 marla
  • 14//14/29 marla
Show the other 12 parcels
  • 14//157 kanal 8 marla
  • 14//167 kanal 8 marla
  • 14//178 kanal
  • 14//248 kanal
  • 14//5/25 kanal
  • 14//67 kanal 8 marla
  • 27//14/1/11 marla
  • 27//14/1/32 kanal 7 marla
  • 27//15/13 kanal 13 marla
  • 27//16/1/21 kanal 5 marla
  • 27//48 kanal
  • 27//78 kanal

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Gwal pahari (hadbast 77), tehsil Wazirabad. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 7//25/1.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan1 Oct 2021

Layout plan

1 file
Latest Layout Plan23 Sept 2021

Building plans

10 files
Building Plan Letter- A 1 to A 1115 Nov 2021Building Plan Letter- A 12 to A2215 Nov 2021Building Plan Letter- A 23 to A3415 Nov 2021Building Plan Letter- A 35 to A 4015 Nov 2021Building Plan Letter- A 41 to A 4615 Nov 2021Building Plan Letter- B1 to B1015 Nov 2021

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (23 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1740 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Namdev Construction

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.