Skip to content

THE ANTALYAS

by Navraj Infratech · Sector 37D, Gurugram

Not on our price list yet

Possession 30 Apr 2027 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 37D, Gurugram0.8 km from Dwarka Expressway, in a straight line
Carpet area
1,430–1,613 sq ft
In m²about 133–150 m², as declared
Registered by
NAVRAJ INFRATECH PVT LTDthe company that filed it, for Navraj Infratech
Timeline
  1. 12 May 2023Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 30 Apr 2027Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

200homes, 1,430 to 1,613 sq ft of carpet area
  • 1,000–1,500 sq ft1,430 sq ft140
  • 1,500–2,000 sq ft1,613 sq ft60

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside5.453 acres in all, by use
  • Apartment buildings1.79 acres · 33%
  • Roads1.488 acres · 27%
  • Sewage and waste treatment1.19 acres · 22%
  • Parks and playgrounds0.82 acres · 15%
  • Club house0.135 acres · 2%
  • Pavements0.03 acres · under 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningSplit
  • KitchenISI marked
  • Kitchen appliancesHob & chimney
  • LiftsISI marked
  • WardrobesModular
  • FloorsVitrified & ceramic tiles/ italian stone
  • WallsPlastic paint
  • BathroomsSingle lever CP fittings/white china WARE

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 37D, GurugramSector 37D, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Dwarka ExpresswayOpen, 17 Aug 20250.8 km
  • Delhi–Gurugram–SNB RRTS4.0 km
  • Sohna Elevated Corridor (NH-248A)6.3 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 1

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it; asking rates from the Bhumiq team price list, 16 Sep 2026.

Questions buyers ask

Is THE ANTALYAS registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/735/467/2023/79. Valid to 30 Apr 2027.

The source ↗
What is the possession timeline for THE ANTALYAS?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 30 Apr 2027. Its registration runs to 30 Apr 2027; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around THE ANTALYAS?From the records · Map pin and road lines, read 6 Sep 2026

THE ANTALYAS is in Sector 37D, Gurugram; the site address declared to HARERA is Sector 37 D. In a straight line it is about 0.8 km from Dwarka Expressway, 4.0 km from Delhi–Gurugram–SNB RRTS and 6.3 km from Sohna Elevated Corridor (NH-248A).

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building THE ANTALYAS?From the records · HARERA, read 4 Nov 2026

THE ANTALYAS is a Navraj Infratech project, registered by its company NAVRAJ INFRATECH PVT LTD.

The source ↗Navraj Infratech's projects and court record

The records

What the registers hold for THE ANTALYAS: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/735/467/2023/79: Registered. Valid to 30 Apr 2027.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 12 OF 2009 is on the DTCP register: Licence lapsed; the register prints its validity to 20 May 2024.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 12 May 2023, building plans 12 May 2023.Declared to HARERA, read 29 Oct 2026
The court record of Navraj Infratech’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Licence 12 OF 2009 lapsed

    Named in this project’s application. Valid to 20 May 2024; no renewal on record. DTCP Haryana register, read 3 Nov 2026. Source

  • Amber flag: Registration ends soon

    Valid to 30 Apr 2027. HARERA Gurugram, read 4 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 48 HARERA files, with the dates we read them
Registration no.
GGM/735/467/2023/79
Registration valid till
30 Apr 2027
Declared possession
30 Apr 2027

Declared by the promoter to HARERA

Land area
5.43 (Acre) (21,974.43 sq m)
FAR
1.75 proposed of 1.75 permissible
licence
12 OF 2009
Estimated project cost
₹205.79 crore
Cost of land
₹75.28 crore
Layout plan, declared approved (field 5a)
12 May 2023
Building plans, declared approved
12 May 2023
Construction to start
1 Feb 2023
Completion declared for
30 Apr 2027
Declared inventory · 3 types

Declared inventory

  • Apartment/Shops/Other Buildings · 140 units · 132.88 sq m carpet · 11 towers · one flat
  • Apartment/Shops/Other Buildings · 30 units · 149.85 sq m carpet · 11 towers · one flat
  • Apartment/Shops/Other Buildings · 30 units · 149.85 sq m carpet · 11 towers · one flat
Statutory approvals, as declared · 2

Statutory approvals, as declared

  • I. LICENSE: 1 — declared: already been obtained (21 May 2009)
  • II. ZONING PLAN — declared: already been obtained (24 Jan 2013)
On file with HARERA · 48 files

On file with HARERA (48)

Plans

Site plan

1 file
Approved Site Plan1 Apr 2024

Layout plan

2 files
Approval of Phasing Plan L.no 12 of 2009 Dt. 12-07-20231 Apr 2024Latest Layout Plan1 Apr 2024

Zoning plan

1 file
Zoning Plan27 Jan 2023

Building plans

10 files
Elevation (Block - 9,10,11)1 Apr 2024Front Elevation & Section, Cb -2 and Cs -21 Apr 2024All Floor Area Cal and Terrace Plan (Block 9,10,11)1 Apr 2024

Floor plans

6 files
5 Floor Plan1 Apr 2024All Floor Area Cal, Cb -2, Cs -21 Apr 2024Stilt Gf, Typ - 1st Floor (Block - 9,10,11)1 Apr 2024

Services

Sewerage and drainage

2 files
Storm Assurance1 Apr 2024Sewer Assurance1 Apr 2024

Water supply

1 file
Water Assurance - 13 Acres - GMDA1 Apr 2024

Electricity

1 file
Electrical Load Availability - Ep Approved1 Apr 2024

Service plans

3 files
Service Estimates Receiving1 Apr 2024Service Plans on the Layout1 Apr 2024PERT Chart for Services1 Apr 2024

Approvals and clearances

DTCP licence

3 files
Licence Copy with Land Schedule1 Apr 2024License No. 12 Renewal1 Apr 2024COD Order1 Apr 2024

Environment clearance

2 files
Environment Clearance1 Apr 2024Latest Environment Clearance1 Apr 2024

Fire safety

1 file
Fire Scheme Approval1 Apr 2024

Other NOCs and clearances

4 files
Mining Permission1 Apr 2024Forest Clearance 13.156 Acres1 Apr 2024Assurance Construction Water NOC1 Apr 2024AAI Letters1 Apr 2024

Land records

Land records

2 files
Non Encumbrances Certificate1 Apr 2024Revenue Record Entry of Licence and Collaboration27 Jan 2023

Money

Accounts and finance

3 files
CA Certificate Project Cost1 Apr 2024CA Certificate on the Application’s Figures1 Apr 2024Non-Default Certificate from a CA1 Apr 2024

Timeline and progress

Construction schedule

1 file
PERT Chart for Construction1 Apr 2024

The promoter’s papers

Declarations and affidavits

2 files
Bank Undertaking Revised1 Apr 2024The Promoter’s Declaration on Affidavit1 Apr 2024

Other filings

Other filings

3 files
Change of name of the group housing project from "The Antalyas" to "The Analia"23 Aug 2024Navraj 4(2)(I)(D)1 Apr 2024Slilt Gf Plan Bl - 1,2,3,4,5,6,71 Apr 2024

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

12 OF 2009 · SA Infratech · GURGAON-MANESAR

Licence valid to 20 May 2024

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 27 Jan 2023 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

12 OF 2009: 7 parcels, 13.1563 acres in all, in Garauli kalan (hadbast 48), tehsil Kadipur.

The licence register prints the same licensed area, 13.16 acres.

  • rectangle 223, kila 2233 bigha
  • rectangle 224, kila 2243 bigha
  • rectangle 218, kila 2182 bigha 9 biswa
  • rectangle 219, kila 2193 bigha 12 biswa
Show the other 3 parcels
  • rectangle 267, kila 267/13 bigha 6 biswa
  • rectangle 267, kila 267/13 bigha 6 biswa
  • rectangle 268, kila 268/12 bigha 8 biswa

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Garauli kalan (hadbast 48), tehsil Kadipur. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as rectangle 223, kila 223.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate

No one collector rate can be matched to this project's type.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan1 Apr 2024

Layout plan

2 files
Approval of Phasing Plan L.no 12 of 2009 Dt. 12-07-20231 Apr 2024Latest Layout Plan1 Apr 2024

Building plans

10 files
Elevation (Block - 9,10,11)1 Apr 2024Front Elevation & Section, Cb -2 and Cs -21 Apr 2024All Floor Area Cal and Terrace Plan (Block 9,10,11)1 Apr 2024Building Plan- Basement1 Apr 2024Terrace Floor and Elevation Section (Block 4 and 8)1 Apr 2024BR-III1 Apr 2024

Floor plans

6 files
5 Floor Plan1 Apr 2024All Floor Area Cal, Cb -2, Cs -21 Apr 2024Stilt Gf, Typ - 1st Floor (Block - 9,10,11)1 Apr 2024All Floor Plan, Community Building -2 and Conv Shopping -21 Apr 2024Stilt Gf - 1st to 5th Floor and Area Cal Bl - 4 and 81 Apr 2024Typ 2nd to 5th Floor (Block - 9,10,11)1 Apr 2024

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (48 in all), none is a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/2212 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Navraj Infratech

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.