Skip to content

THE GOLDEN CITY II

by Rennova Buildcone · Sirsa

Not on our price list yet

Possession 24 Aug 2031 · as the developer declared it to HARERA

About this project

Key facts

Registered by
RENNOVA BUILDCONE PRIVATE LIMITEDthe company that filed it, for Rennova Buildcone
Timeline
  1. 25 Aug 2026Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 24 Aug 2031Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside18.944 acres in all, by use
  • Plots for sale12.196 acres · 64%
  • Roads5.116 acres · 27%
  • Parks and playgrounds0.64 acres · 3%
  • Land for community services, handed to the government0.51 acres · 3%
  • Green belts0.264 acres · 1%
  • Sewage and waste treatment0.111 acres · under 1%
  • Electricity sub-station0.054 acres · under 1%
  • Other uses0.053 acres · under 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: REVENUE ESTATE OF VILLAGE RAMNAGAR AND KHAJAKHERA TEHSIL AND DISTRICT SIRSA HARYANA

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 1

Questions buyers ask

Is THE GOLDEN CITY II registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as HRERA-PKL-SRS-996-2026. Valid to 24 Aug 2031.

The source ↗
What is the possession timeline for THE GOLDEN CITY II?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 24 Aug 2031. Its registration runs to 24 Aug 2031; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around THE GOLDEN CITY II?From the records · HARERA, read 4 Nov 2026

THE GOLDEN CITY II is in Sirsa; the site address declared to HARERA is Revenue Estate Of Village Ramnagar And Khajakhera Tehsil And District Sirsa Haryana. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building THE GOLDEN CITY II?From the records · HARERA, read 4 Nov 2026

THE GOLDEN CITY II is a Rennova Buildcone project, registered by its company RENNOVA BUILDCONE PRIVATE LIMITED.

The source ↗Rennova Buildcone's projects and court record

The records

What the registers hold for THE GOLDEN CITY II: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-SRS-996-2026: Registered. Valid to 24 Aug 2031.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 169 OF 2026 is on the DTCP register, valid to 24 Aug 2031.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 25 Aug 2026, building plans 25 Aug 2026.Declared to HARERA, read 29 Oct 2026
The court record of Rennova Buildcone’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 23 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-SRS-996-2026
Registration valid till
24 Aug 2031
Declared possession
24 Aug 2031

Declared by the promoter to HARERA

Land area
18.94375 (Acre) (76,662.64 sq m)
FAR
1.25 proposed of 1.25 permissible
licence
LICENCE NO. 169 OF 2026 DATED 25.08.2026 BEARING ENDST NO. LC-5972/Asstt.(MS)/2026/30600
Estimated project cost
₹65.01 crore
Cost of land
₹10.35 crore
Layout plan, declared approved (field 5a)
25 Aug 2026
Building plans, declared approved
25 Aug 2026
Construction to start
1 Oct 2026
Completion declared for
24 Aug 2031
Statutory approvals, as declared · 5

Statutory approvals, as declared

  • I. LICENCE NO. 169 OF 2026 — declared: already been obtained (25 Aug 2026)
  • II. ELECTRIFICATION PERMISSION BEARING MEMO. NO. CH-107/OLNC-HT/SRS/EP-614 — declared: already been obtained (14 Aug 2026)
  • III. FOREST DIVERSION BEARING MEMO. NO. 3064 — declared: already been obtained (10 Aug 2026)
  • IV. PWD ACCESS PERMISSION BEARING MEMO. NO. 3278 — declared: already been obtained (30 Jul 2026)
  • V. NOC FOR CONSTRUCTION OF CULVERT FROM GHAGGAR WATER SERVICE DIVISION SIRSA BEARING MEMO. NO. 323/1-W/SDR — declared: already been obtained (4 Aug 2026)
On file with HARERA · 23 files

On file with HARERA (23)

Plans

Site plan

1 file
Approved Site Plan2 Sept 2026

Layout plan

1 file
Latest Layout Plan2 Sept 2026

Zoning plan

1 file
Zoning Plan23 Sept 2026

Demarcation plan

2 files
Demarcation Plan9 Sept 2026Demarcation Approval Letter9 Sept 2026

Building plans

1 file
Approved Building Plans, Full Set9 Sept 2026

Services

Sewerage and drainage

2 files
Sewerage Treatment Plant Assurance11 Sept 2026Storm Water Connection Assurance11 Sept 2026

Water supply

1 file
Water Supply Assurance11 Sept 2026

Electricity

1 file
Electrification Plan9 Sept 2026

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule2 Sept 2026

Other NOCs and clearances

3 files
Forest Diversion15 Sept 2026Pwd Access Permission9 Sept 2026Irrigation NOC9 Sept 2026

Land records

Land records

2 files
Revenue Record Entry of Licence and Collaboration14 Sept 2026Aks Sajra14 Sept 2026

Money

Accounts and finance

4 files
Non-Default Certificate from a CA10 Sept 2026Cash Flow Statement10 Sept 2026Project Report10 Sept 2026CA Certificate on the Application’s Figures10 Sept 2026

Timeline and progress

Construction schedule

1 file
PERT Chart10 Sept 2026

The promoter’s papers

Declarations and affidavits

2 files
Bank Undertaking14 Sept 2026The Promoter’s Declaration on Affidavit2 Sept 2026

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

169 OF 2026 · Rennovaa Buidcone Pvt.Ltd · SIRSA

Licence valid to 24 Aug 2031

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 23 Sept 2026 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

169 OF 2026: 44 parcels, 18.9438 acres in all, in Ramnagria (hadbast 0084) and Khaza khera (hadbast 0083), tehsil Sirsa.

The licence register prints the same licensed area, 18.9438 acres.

  • 26//14/2/25 kanal 2 marlaRamnagria (0084)
  • 26//15/23 kanal 16 marlaRamnagria (0084)
  • 26//16/1/24 kanal 10 marlaRamnagria (0084)
  • 26//25/26 kanal 1 marlaRamnagria (0084)
Show the other 40 parcels
  • 26//7/2/167 marlaRamnagria (0084)
  • 26//7/2/5/17 marlaRamnagria (0084)
  • 26//7/2/5/2/11 marlaRamnagria (0084)
  • 26//7/2/5/2/21 marlaRamnagria (0084)
  • 26//7/2/6/13 marlaRamnagria (0084)
  • 26//7/3/1/11 marlaRamnagria (0084)
  • 26//7/3/2/11 marlaRamnagria (0084)
  • 27//21/13 kanal 5 marlaRamnagria (0084)
  • 27//21/23 kanal 19 marlaRamnagria (0084)
  • 27//223 kanal 14 marlaRamnagria (0084)
  • 28//18 kanalRamnagria (0084)
  • 28//10/13 kanal 12 marlaRamnagria (0084)
  • 28//10/24 kanal 8 marlaRamnagria (0084)
  • 28//2/11 kanal 8 marlaRamnagria (0084)
  • 28//9/13 kanal 7 marlaRamnagria (0084)
  • rectangle 43, kila 25 kanalRamnagria (0084)
  • 18//10/22 kanal 17 marlaKhaza khera (0083)
  • 18//128 kanal 6 marlaKhaza khera (0083)
  • 18//138 kanalKhaza khera (0083)
  • 18//14/110 marlaKhaza khera (0083)
  • 18//14/26 kanal 7 marlaKhaza khera (0083)
  • 18//172 kanal 6 marlaKhaza khera (0083)
  • 18//18/19 marlaKhaza khera (0083)
  • 18//18/27 kanal 11 marlaKhaza khera (0083)
  • 18//196 kanal 6 marlaKhaza khera (0083)
  • 18//224 kanalKhaza khera (0083)
  • 18//23/19 marlaKhaza khera (0083)
  • 18//23/25 kanal 4 marlaKhaza khera (0083)
  • 18//44 kanalKhaza khera (0083)
  • 18//5/15 kanalKhaza khera (0083)
  • 18//63 kanal 4 marlaKhaza khera (0083)
  • 18//78 kanalKhaza khera (0083)
  • 18//88 kanalKhaza khera (0083)
  • 18//9/27 kanal 11 marlaKhaza khera (0083)
  • rectangle 26, kila 7/2/15/25 marlaRamnagria (0084)
  • rectangle 26, kila 7/1min1 kanal 15 marlaRamnagria (0084)
  • 26//7/3/1/21 marlaRamnagria (0084)
  • 26//7/3/2/21 marlaRamnagria (0084)
  • 26//7/3/68 marlaRamnagria (0084)
  • 28//2/23 kanal 18 marlaRamnagria (0084)

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 23 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Sirsa, then the tehsil and the village you want: Ramnagria (hadbast 0084) or Khaza khera (hadbast 0083), tehsil Sirsa. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 26//14/2/2.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan2 Sept 2026

Layout plan

1 file
Latest Layout Plan2 Sept 2026

Building plans

1 file
Approved Building Plans, Full Set9 Sept 2026

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (23 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/4317 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Rennova Buildcone

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.