Skip to content

THE SELECT PREMIA

by Adore Projects · Faridabad

Not on our price list yet

Possession 30 May 2029 · as the developer declared it to HARERA

About this project

Key facts

Location
Faridabad
Carpet area
1,811–2,289 sq ft
In m²about 168–213 m², as declared
Registered by
ADORE BUILD PROJECTS LLPthe company that filed it, for Adore Projects
Timeline
  1. 22 Feb 2024Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 30 May 2029Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

165homes, 1,811 to 2,289 sq ft of carpet area
  • 1,500–2,000 sq ft1,811 sq ft66
  • 2,000–2,500 sq ft2,289 sq ft99

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside5.48 acres in all, by use
  • Apartment buildings4.138 acres · 76%
  • Green belts1.196 acres · 22%
  • Club house0.116 acres · 2%
  • Other uses0.03 acres · under 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningWiring and piping with ISI marked
  • KitchenCounter top - granite/marble top, vitrified tiles up to 2 FT height above counter
  • Lifts4 lift in each tower
  • FloorsVitrified tiles/ granite/ marble
  • WallsOil bound distemper (OBD)/ acrylic emulsion
  • BathroomsPPR pipes/CPVC pipes, CP fitting of ISI marked
  • WindowsPower coated aluminium/ UPVC
  • Main doorFlush door painted with FLAT enamel paint/ winear with polish door with SKIN

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: SECTOR 76 HSVP FARIDABAD

The builder

Its 2 projects in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 2

Questions buyers ask

Is THE SELECT PREMIA registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as HRERA-PKL-FBD-584-2024. Valid to 30 May 2029.

The source ↗
What is the possession timeline for THE SELECT PREMIA?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 30 May 2029. Its registration runs to 30 May 2029; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around THE SELECT PREMIA?From the records · HARERA, read 4 Nov 2026

THE SELECT PREMIA is in Faridabad; the site address declared to HARERA is Sector 76 Hsvp Faridabad. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building THE SELECT PREMIA?From the records · HARERA, read 4 Nov 2026

THE SELECT PREMIA is a Adore Projects project, registered by its company ADORE BUILD PROJECTS LLP.

The source ↗Adore Projects's projects and court record

The records

What the registers hold for THE SELECT PREMIA: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-FBD-584-2024: Registered. Valid to 30 May 2029.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Plans approved, as the developer declared: layout plan 22 Feb 2024, building plans 22 Feb 2024.Declared to HARERA, read 29 Oct 2026
The court record of Adore Projects’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 9 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-FBD-584-2024
Registration valid till
30 May 2029
Declared possession
30 May 2029

Declared by the promoter to HARERA

Land area
5.48 (Acre) (22,176.77 sq m)
FAR
the application prints 178, which is not a ratio
licence
Group Housing Scheme Site No 1 HSVP Sector 76 Faridabad allotment letter vide Memo No Z0001/E0001/UE001/GALOT/ 0000001398 dated 17/11/2023
Estimated project cost
₹410.00 crore
Cost of land
₹132.70 crore
Layout plan, declared approved (field 5a)
22 Feb 2024
Building plans, declared approved
22 Feb 2024
Construction to start
1 Jun 2024
Completion declared for
30 May 2029
Declared inventory · 2 types

Declared inventory

  • Apartment/Shops/Other Buildings · 99 units · 212.63 sq m carpet · 3 towers · one flat
  • Apartment/Shops/Other Buildings · 66 units · 168.23 sq m carpet · 2 towers · one flat
Statutory approvals, as declared · 1

Statutory approvals, as declared

  • I. BUILDING PLAN — declared: already been obtained (22 Feb 2024)
On file with HARERA · 9 files

On file with HARERA (9)

Plans

Site plan

1 file
Approved Site Plan29 Mar 2024

Layout plan

1 file
Latest Layout Plan29 Mar 2024

Zoning plan

1 file
Zoning Plan29 Mar 2024

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule29 Mar 2024

Money

Accounts and finance

3 files
Change of bank account details updated12 Nov 2024Non-Default Certificate from a CA29 Mar 2024CA Certificate on the Application’s Figures29 Mar 2024

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit29 Mar 2024

HARERA’s orders

HARERA’s orders

1 file
Corrigendum Uploaded23 Apr 2026

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

The promoter declared Group Housing Scheme Site No 1 HSVP Sector 76 Faridabad allotment letter vide Memo No Z0001/E0001/UE001/GALOT/ 0000001398 dated 17/11/2023. We could not read a licence number from that, so nothing is claimed about it here.

declared in the registration application (Form REP-I), Panchkula bench · submitted 30 Mar 2024 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan29 Mar 2024

Layout plan

1 file
Latest Layout Plan29 Mar 2024

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (9 in all), none is a building plan, a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/2844 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Adore Projects

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.