About this project

Key facts

Timeline
  1. 25 Jan 2024Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 31 Dec 2027Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside6.583 acres in all, by use
  • Plots for sale3.557 acres · 54%
  • Roads1.644 acres · 25%
  • Land for community services, handed to the government0.658 acres · 10%
  • Green belts0.497 acres · 8%
  • Other usesas the form names them: Commercial area0.227 acres · 3%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: VILLAGE SIMLA MULANA, SECTOR-40, PANIPAT

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 1

Questions buyers ask

Is WINDSOR HOMES registered with HARERA?From the records · HARERA, read 3 Nov 2026

HARERA lists it as HRERA-PKL-PNP-576-2024. Valid to 31 Dec 2027.

The source ↗
What is the possession timeline for WINDSOR HOMES?From the records · HARERA, read 3 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Dec 2027. Its registration runs to 31 Dec 2027; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around WINDSOR HOMES?From the records · HARERA, read 3 Nov 2026

WINDSOR HOMES is in Panipat; the site address declared to HARERA is Village Simla Mulana, Sector-40, Panipat. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building WINDSOR HOMES?From the records · HARERA, read 3 Nov 2026

WINDSOR HOMES is a Liberty Infra Co project.

The source ↗Liberty Infra Co's projects and court record

The records

What the registers hold for WINDSOR HOMES: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-PNP-576-2024: Registered. Valid to 31 Dec 2027.HARERA, read 3 Nov 2026 · See it on HARERA ↗
  • Land licence 11 OF 2024 is on the DTCP register, valid to 23 Jan 2029.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 25 Jan 2024.Declared to HARERA, read 29 Oct 2026
The court record of Liberty Infra Co’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 10 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-PNP-576-2024
Registration valid till
31 Dec 2027
Declared possession
31 Dec 2027

Declared by the promoter to HARERA

Land area
6.583 (Acre) (26,640.46 sq m)
FAR
1 proposed of 1 permissible
licence
License No. 11 of 2024 Dated 24-01-2024
Estimated project cost
₹47.55 crore
Cost of land
₹30.00 crore
Layout plan, declared approved (field 5a)
25 Jan 2024
Construction to start
1 Mar 2024
Completion declared for
31 Dec 2027
Statutory approvals, as declared · 4

Statutory approvals, as declared

  • I. DTCP LICENSE — declared: already been obtained (24 Jan 2024)
  • II. LAYOUT PLAN — declared: already been obtained (25 Jan 2024)
  • III. DEMARCATION CUM ZONING PLAN — declared: already been obtained (11 Mar 2024)
  • IV. STANDARD DESIGNS OF BOOTHS OF COMMERCIAL SITE — declared: already been obtained (11 Mar 2024)
On file with HARERA · 10 files

On file with HARERA (10)

Plans

Site plan

1 file
Approved Site Plan11 Mar 2024

Layout plan

1 file
Latest Layout Plan11 Mar 2024

Zoning plan

1 file
Zoning Plan11 Mar 2024

Demarcation plan

1 file
Demarcation Plan11 Mar 2024

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule12 Feb 2024

Money

Accounts and finance

3 files
Non-Default Certificate from a CA1 Mar 2024CA Certificate on the Application’s Figures1 Mar 2024Cash Flow Statement29 Feb 2024

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit29 Feb 2024

HARERA’s orders

HARERA’s orders

1 file
Corrigendum18 Jun 2024

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

11 OF 2024 · Harish Gupta · Panipat

Licence valid to 23 Jan 2029

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 11 Mar 2024 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 3 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

11 OF 2024: 18 parcels, 6.583 acres in all, in Simla mulana (hadbast 2), tehsil Panipat.

The licence register prints the same licensed area, 6.583 acres.

  • rectangle 198, kila 198/118 biswa
  • rectangle 199, kila 199/12 bigha 8 biswa
  • rectangle 200, kila 200/1/114 biswa
  • rectangle 201, kila 201/218 biswa
Show the other 14 parcels
  • rectangle 202, kila 2023 bigha
  • rectangle 203, kila 2033 bigha
  • rectangle 208, kila 2083 bigha
  • rectangle 209, kila 2093 bigha
  • rectangle 213, kila 2133 bigha
  • rectangle 229, kila 229/2/13 biswa
  • rectangle 954, kila 211/2/1/23 biswa
  • rectangle 954, kila 211/2/215 biswa
  • rectangle 197, kila 1971 bigha 10 biswa
  • rectangle 210, kila 210/118 biswa
  • rectangle 212, kila 2123 bigha
  • rectangle 227, kila 2271 bigha 10 biswa
  • rectangle 228, kila 2283 bigha
  • rectangle 229, kila 229/115 biswa

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Panipat, then the tehsil and the village: Simla mulana (hadbast 2), tehsil Panipat. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as rectangle 198, kila 198/1.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan11 Mar 2024

Layout plan

1 file
Latest Layout Plan11 Mar 2024

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (10 in all), none is a building plan, a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/2800 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Liberty Infra Co

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.