Skip to content

YCON PLATINUM HEIGHTS

by Ycon Infra · Gurugram

Not on our price list yet

Possession 31 Oct 2030 · as the developer declared it to HARERA

About this project

Key facts

Location
Gurugram
Carpet area
278–645 sq ft
In m²about 26–60 m², as declared
Timeline
  1. 13 Mar 2026Layout and building plans approveddeclared to HARERA, read 1 Oct 2026
  2. 31 Oct 2030Possession, as declareddeclared to HARERA, read 1 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

1,982homes, 278 to 645 sq ft of carpet area
  • Under 1,000 sq ft278–645 sq ft1,982

Carpet area per home, as declared to HARERA (read 1 Oct 2026), in sq ft. Left out: 1 row of a single unit and 52 units under 25 m², because the form lists homes, shops and other buildings in one table.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside13.275 acres in all, by use
  • Roads3.809 acres · 29%
  • Apartment buildings3.527 acres · 27%
  • Parking2.53 acres · 19%
  • Parks and playgrounds2.393 acres · 18%
  • Shops and offices0.38 acres · 3%
  • Green belts0.33 acres · 2%
  • Other usesas the form names them: Aanganwadi, Community0.247 acres · 2%
  • Electricity sub-station0.059 acres · under 1%

The land-use table of the HARERA application, declared to HARERA, read 1 Oct 2026. The share is of the land the table itemises.

In each home
  • KitchenOil bound distemper/ whitewash
  • LiftsAs per NBCC CODE
  • FloorsVitrified/ ceramic tiles
  • WallsOil bound distemper/ whitewash
  • BathroomsBranded CP fitting, WC & washbasin
  • WindowsAluminium/UPVC/steel section with 4MM thick glass
  • Main doorFlush doors
  • Electrical fittingsBranded

The developer’s specifications in the HARERA application, declared to HARERA, read 1 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: REVENUE ESTATE OF VILLAGE PATAUDI, SECTOR 3 PATAUDI, DISTRICT GURUGRAM

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 1

Questions buyers ask

Is YCON PLATINUM HEIGHTS registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/1065/797/2026/37. Valid to 31 Oct 2030.

The source ↗
What is the possession timeline for YCON PLATINUM HEIGHTS?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Oct 2030. Its registration runs to 31 Oct 2030; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around YCON PLATINUM HEIGHTS?From the records · HARERA, read 4 Nov 2026

YCON PLATINUM HEIGHTS is in Gurugram; the site address declared to HARERA is Revenue Estate Of Village Pataudi, Sector 3 Pataudi, District Gurugram. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building YCON PLATINUM HEIGHTS?From the records · HARERA, read 4 Nov 2026

YCON PLATINUM HEIGHTS is a Ycon Infra project.

The source ↗Ycon Infra's projects and court record

The records

What the registers hold for YCON PLATINUM HEIGHTS: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/1065/797/2026/37: Registered. Valid to 31 Oct 2030.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 193 OF 2025 is on the DTCP register, valid to 8 Oct 2030.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 13 Mar 2026, building plans 13 Mar 2026.Declared to HARERA, read 1 Oct 2026
The court record of Ycon Infra’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 71 HARERA files, with the dates we read them
Registration no.
GGM/1065/797/2026/37
Registration valid till
31 Oct 2030
Declared possession
31 Oct 2030

Declared by the promoter to HARERA

Land area
13.275 (Acre) (53,722.02 sq m)
FAR
2.4 proposed of 2.4 permissible
licence
193 of 2025 Dated 09.10.2025
Estimated project cost
₹630.86 crore
Cost of land
₹179.44 crore
Layout plan, declared approved (field 5a)
13 Mar 2026
Building plans, declared approved
13 Mar 2026
Construction to start
1 Jul 2026
Completion declared for
31 Oct 2030
Declared inventory · 31 types

Declared inventory — 31 types declared, first 8 shown

  • Apartment/Shops/Other Buildings · 4 units · 59.9 sq m carpet · 18 towers · one flat
  • Apartment/Shops/Other Buildings · 4 units · 59.93 sq m carpet · 18 towers · one flat
  • Apartment/Shops/Other Buildings · 44 units · 59.9 sq m carpet · 18 towers · one flat
  • Apartment/Shops/Other Buildings · 44 units · 59.93 sq m carpet · 18 towers · one flat
  • Apartment/Shops/Other Buildings · 624 units · 59.9 sq m carpet · 18 towers · one flat
  • Apartment/Shops/Other Buildings · 624 units · 59.93 sq m carpet · 18 towers · one flat
  • Apartment/Shops/Other Buildings · 20 units · 46.62 sq m carpet · 18 towers · one flat
  • Apartment/Shops/Other Buildings · 20 units · 49.18 sq m carpet · 18 towers · one flat
Statutory approvals, as declared · 15

Statutory approvals, as declared

  • I. LICENSE — declared: already been obtained (9 Oct 2025)
  • II. LOI — declared: already been obtained (13 Jun 2025)
  • III. AAI NOC — declared: already been obtained (30 Dec 2025)
  • IV. ARAWALI NOC — declared: already been obtained (2 Jan 2026)
  • V. BR III — declared: already been obtained (13 Mar 2026)
  • VI. ELECTRIFICATION PLAN — declared: already been obtained (9 Jan 2026)
  • VII. FOREST NOC — declared: already been obtained (4 Aug 2025)
  • VIII. SEWERAGE ASSURANCE — declared: already been obtained (30 Oct 2025)
  • IX. STORM WATER ASSURANCE — declared: already been obtained (30 Oct 2025)
  • X. DOMESTIC WATER ASSURANCE — declared: already been obtained (30 Oct 2025)
  • XI. STP WATER NOC — declared: already been obtained (30 Oct 2025)
  • XII. ZONING — declared: already been obtained (10 Oct 2025)
  • XIII. FIRE — declared: already been obtained (21 May 2026)
  • XIV. EC — declared: already been obtained (3 Jun 2026)
  • XV. SERVICE PLAN ESTIMATES — declared: yet to file for approval
On file with HARERA · 71 files

On file with HARERA (71)

Plans

Site plan

1 file
Approved Site Plan18 Apr 2026

Layout plan

1 file
Latest Layout Plan18 Apr 2026

Zoning plan

1 file
Zoning Plan18 Apr 2026

Demarcation plan

2 files
Demarcation Plan20 Apr 2026Superimposed Demarcation Plan20 Apr 2026

Building plans

10 files
Tower Plan 1 to 12-Typical Floor Plan, Terrace Plan & Area Diagram24 Jun 2026Tower Plan 1 to 2-Typical Floor Plan, Terrace Plan & Area Diagram24 Jun 20268 3 Bhk Tower 1-12 Elevation18 Apr 2026

Floor plans

4 files
Tower Plan 1 to 2-Ground & First Floor Plan & Area Diagram24 Jun 2026Tower Plan 3 to 12-Ground & First Floor Plan & Area Diagram24 Jun 2026Unit Detail18 Apr 20269 2 Bhk Tower 13-17 Gf & Ff18 Apr 2026

Services

Sewerage and drainage

2 files
Storm Water Assurance18 Apr 2026Sewerage Assurance18 Apr 2026

Water supply

1 file
Water Assurance18 Apr 2026

Electricity

1 file
Electrification Plan18 Apr 2026

Roads

1 file
Road Layout18 Apr 2026

Service plans

2 files
Service Estimate Receiving24 Jun 2026Service Plans on the Layout24 Jun 2026

Approvals and clearances

DTCP licence

3 files
LOI18 Apr 2026LC IV18 Apr 2026Licence Copy with Land Schedule5 Dec 2025

Environment clearance

1 file
Environment Clearence24 Jun 2026

Fire safety

1 file
Fire Scheme Approval24 Jun 2026

Other NOCs and clearances

4 files
Forest NOC18 Apr 2026AAI NOC18 Apr 2026STP Water NOC18 Apr 2026Arawali NOC18 Apr 2026

Land records

Land records

9 files
Search Report24 Jun 2026Non Encumbrance Certificate24 Apr 2026Jamabandi24 Apr 2026

Sales papers

Brochure and specifications

1 file
Brochure24 Jun 2026

Money

Accounts and finance

9 files
Quaterly Estimated Expenditure24 Jun 2026Source of Funds24 Jun 2026Cash Flow Statement24 Jun 2026

Timeline and progress

Construction schedule

1 file
PERT Chart24 Jun 2026

The promoter’s papers

Declarations and affidavits

11 files
The Promoter’s Declaration on Affidavit24 Jun 2026Undertaking No Trees24 Jun 2026Affidavit - No Litigation24 Jun 2026

Company papers

1 file
Board Resolution22 Apr 2026

HARERA’s orders

HARERA’s orders

1 file
Collaboration and Addendum24 Jun 2026

Other filings

Other filings

3 files
Lei (Legal Identity Identirier)24 Jun 2026Commercial -124 Jun 2026Commercial- 2 and 324 Jun 2026

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

193 OF 2025 · M/s Y CON INFRA · PATAUDI

Licence valid to 8 Oct 2030

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 24 Apr 2026 · read 1 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

193 OF 2025: 29 parcels, 13.275 acres in all, in Pataudi (hadbast 1), tehsil Pataudi.

The licence register prints the same licensed area, 13.275 acres.

  • 56//13/31 kanal
  • 56//14/26 kanal 7 marla
  • 56//14/31 kanal 12 marla
  • 56//158 kanal
Show the other 25 parcels
  • 56//168 kanal
  • 56//17/110 marla
  • 56//17/27 kanal 10 marla
  • 56//18/11 kanal 3 marla
  • 56//23/1/33 marla
  • 56//24/11 kanal 2 marla
  • 56//25/11 kanal 2 marla
  • 56//5/2/13 kanal
  • 56//5/2/511 marla
  • 56//68 kanal
  • 56//7/12 kanal 3 marla
  • 56//7/26 kanal 8 marla
  • 55//1/2/22 kanal 7 marla
  • 55//1/2/32 kanal 9 marla
  • 55//107 kanal 20 marla
  • 55//118 kanal
  • 55//12/15 kanal 4 marla
  • 55//12/22 kanal 16 marla
  • 55//19/1/119 marla
  • 55//19/1/21 kanal 14 marla
  • 55//2/2/15 kanal 19 marla
  • 55//2/2/21 kanal 12 marla
  • 55//20/12 kanal 13 marla
  • 55//9/12 kanal 16 marla
  • 55//9/25 kanal 4 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Pataudi (hadbast 1), tehsil Pataudi. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 56//13/3.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan18 Apr 2026

Layout plan

1 file
Latest Layout Plan18 Apr 2026

Building plans

10 files
Tower Plan 1 to 12-Typical Floor Plan, Terrace Plan & Area Diagram24 Jun 2026Tower Plan 1 to 2-Typical Floor Plan, Terrace Plan & Area Diagram24 Jun 20268 3 Bhk Tower 1-12 Elevation18 Apr 2026BR III18 Apr 202613 2 Bhk Tower 18 Elevation E-1 & Section Aa-Bb18 Apr 202610 2 Bhk Tower 13-17 Typ Fl & Terrace Fl18 Apr 2026

Floor plans

4 files
Tower Plan 1 to 2-Ground & First Floor Plan & Area Diagram24 Jun 2026Tower Plan 3 to 12-Ground & First Floor Plan & Area Diagram24 Jun 2026Unit Detail18 Apr 20269 2 Bhk Tower 13-17 Gf & Ff18 Apr 2026

Among the uploads Bhumiq read from HARERA's page on 1 Oct 2026 (71 in all), none is a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/3853 · read 1 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Ycon Infra

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.