Skip to content

BPTP DISCTRICT 1 BLOCK C

by Countrywide Promoters · Faridabad

Not on our price list yet

Possession 18 Aug 2024 · as the developer declared it to HARERA

About this project

Key facts

Location
Faridabad
Registered by
COUNTRYWIDE PROMOTERS PRIVATE LIMITEDthe company that filed it, for Countrywide Promoters
Timeline
  1. 19 Aug 2019Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 18 Aug 2024Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside12.721 acres in all, by use
  • Plots for sale7.768 acres · 61%
  • Roads1.546 acres · 12%
  • Land for community services, handed to the government1.325 acres · 10%
  • Pavements1.006 acres · 8%
  • Parks and playgrounds0.994 acres · 8%
  • Other uses0.032 acres · under 1%
  • Electricity sub-station0.025 acres · under 1%
  • Sewage and waste treatment0.025 acres · under 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: VILLAGE BUDENA, SECTOR 81, FARIDABAD, HARYANA

The builder

Its 19 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 3
  • Registered, no OC or CC yet: 3
  • Other register states: 13

Questions buyers ask

Is BPTP DISCTRICT 1 BLOCK C registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as HRERA-PKL-FBD-160-2019. The register’s record shows an end date of 18 Aug 2024. The register shows it as: Registration lapsed.

The source ↗
What is the possession timeline for BPTP DISCTRICT 1 BLOCK C?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 18 Aug 2024. Its registration runs to 18 Aug 2024; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around BPTP DISCTRICT 1 BLOCK C?From the records · HARERA, read 4 Nov 2026

BPTP DISCTRICT 1 BLOCK C is in Faridabad; the site address declared to HARERA is Village Budena, Sector 81, Faridabad, Haryana. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building BPTP DISCTRICT 1 BLOCK C?From the records · HARERA, read 4 Nov 2026

BPTP DISCTRICT 1 BLOCK C is a Countrywide Promoters project, registered by its company COUNTRYWIDE PROMOTERS PRIVATE LIMITED.

The source ↗Countrywide Promoters's projects and court record

The records

What the registers hold for BPTP DISCTRICT 1 BLOCK C: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-FBD-160-2019: Registration lapsed. The register’s record shows an end date of 18 Aug 2024.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 94 OF 2019 is on the DTCP register: Licence ended, LC-IX linked; the register prints its validity to 18 Aug 2026.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 19 Aug 2019.Declared to HARERA, read 29 Oct 2026
The court record of Countrywide Promoters’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Registration lapsed

    The register’s record shows an end date of 18 Aug 2024. HARERA Panchkula, read 4 Nov 2026. Source

  • Amber flag: Licence 94 OF 2019 validity ended

    Named in this project’s application. Valid to 18 Aug 2026. The register links a completion certificate (LC-IX), dated 19 Jul 2024, against this licence. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 6 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-FBD-160-2019
Registration valid till
18 Aug 2024
Declared possession
18 Aug 2024

Declared by the promoter to HARERA

Land area
12.72 (Acre) (51,476.01 sq m)
FAR
1 proposed of 1 permissible
licence
LICENSE NO 94 OF 2019
Estimated project cost
₹63.12 crore
Cost of land
₹16.72 crore
Layout plan, declared approved (field 5a)
19 Aug 2019
Construction to start
20 Aug 2019
Completion declared for
18 Aug 2024
Statutory approvals, as declared · 2

Statutory approvals, as declared

  • I. LICENSE NO 94 OF 2019 — declared: already been obtained (19 Aug 2019)
  • II. LAYOUT APPROVAL — declared: already been obtained (19 Aug 2019)
On file with HARERA · 6 files

On file with HARERA (6)

Plans

Site plan

1 file
Approved Site Plan20 Aug 2019

Layout plan

1 file
Latest Layout Plan21 Aug 2019

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule20 Aug 2019

Money

Accounts and finance

1 file
Non-Default Certificate from a CA20 Aug 2019

The promoter’s papers

Declarations and affidavits

2 files
Rep-II21 Aug 2019The Promoter’s Declaration on Affidavit21 Aug 2019

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

94 OF 2019 · Countrywide Promoters Pvt. Ltd. · FARIDABAD

Licence valid to 18 Aug 2026

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 21 Aug 2019 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

94 OF 2019: 22 parcels, 13.25 acres in all, in Budina (hadbast 124), tehsil Faridabad.

The licence register prints the same licensed area, 13.25 acres.

  • 36//14/2 min5 kanal 12 marla
  • 36//157 kanal 7 marla
  • 36//167 kanal 7 marla
  • 36//17 min5 kanal 12 marla
Show the other 18 parcels
  • 36//24 min5 kanal 12 marla
  • 36//257 kanal 7 marla
  • 36//6/16 kanal
  • 36//6/21 kanal 7 marla
  • 36//7/11 kanal 7 marla
  • 36//7/2/1 min4 kanal 5 marla
  • 38//4/1 min1 kanal 5 marla
  • 38//4/24 kanal 7 marla
  • 38//57 kanal 13 marla
  • 38//7 min3 kanal 19 marla
  • 30//14 min3 kanal 5 marla
  • 30//17/25 kanal 4 marla
  • 30//18 min6 kanal 12 marla
  • 30//24/12 kanal
  • 30//24/25 kanal 3 marla
  • 39//17 kanal 9 marla
  • 39//2/13 kanal 8 marla
  • 38//14 min3 kanal 19 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Faridabad, then the tehsil and the village: Budina (hadbast 124), tehsil Faridabad. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 36//14/2 min.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan20 Aug 2019

Layout plan

1 file
Latest Layout Plan21 Aug 2019

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (6 in all), none is a building plan, a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/815 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Countrywide Promoters

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.