CENTRAL PARK THE ORCHARD

by St. Patricks Realty · Gurugram

Not on our price list yet

Possession 30 Jun 2026 · as the developer declared it to HARERA

About this project

Key facts

Location
Gurugram
Carpet area
1,326–1,439 sq ft
In m²about 123–134 m², as declared
Registered by
ST PATRICKS REALTY PRIVATE LIMITEDthe company that filed it, for St. Patricks Realty
Timeline
  1. 13 Dec 2021Layout plan approveddeclared to HARERA, read 29 Oct 2026
  2. 12 Jan 2023Building plans approveddeclared to HARERA, read 29 Oct 2026
  3. 30 Jun 2026Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

304homes, 1,326 to 1,439 sq ft of carpet area
  • 1,000–1,500 sq ft1,326–1,439 sq ft304

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside16,701 m² in all, by use
  • Apartment buildings16,701 m² · 100%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningVRV
  • KitchenAnti skid /vitrified tiles / marble
  • Kitchen appliancesModular type
  • LiftsSchneider
  • WardrobesHmhdr board
  • FloorsLaminated wooden flooring / marble
  • WallsHigh quality designer ceramic tiles / marble
  • BathroomsHigh quality designer ceramic tiles / marble

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: SITUATED IN SECTOR-32, TEHSIL-SOHNA, GURUGRAM

The builder

Its 11 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 3
  • Registered, no OC or CC yet: 8

Questions buyers ask

Is CENTRAL PARK THE ORCHARD registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/672/404/2023/16. Ended 30 Jun 2026. The register shows it as: Registration expired.

The source ↗
What is the possession timeline for CENTRAL PARK THE ORCHARD?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 30 Jun 2026. Its registration runs to 30 Jun 2026; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around CENTRAL PARK THE ORCHARD?From the records · HARERA, read 4 Nov 2026

CENTRAL PARK THE ORCHARD is in Gurugram; the site address declared to HARERA is Situated In Sector-32, Tehsil-Sohna, Gurugram. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building CENTRAL PARK THE ORCHARD?From the records · HARERA, read 4 Nov 2026

CENTRAL PARK THE ORCHARD is a St. Patricks Realty project, registered by its company ST PATRICKS REALTY PRIVATE LIMITED.

The source ↗St. Patricks Realty's projects and court record

The records

What the registers hold for CENTRAL PARK THE ORCHARD: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/672/404/2023/16: Registration expired. Ended 30 Jun 2026.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 104 OF 2021 is on the DTCP register: Licence ends soon; the register prints its validity to 9 Dec 2026.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 13 Dec 2021, building plans 12 Jan 2023.Declared to HARERA, read 29 Oct 2026
The court record of St. Patricks Realty’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Registration expired

    Ended 30 Jun 2026. HARERA Gurugram, read 4 Nov 2026. Source

  • Amber flag: Licence 104 OF 2021 ends soon

    Named in this project’s application. Valid to 9 Dec 2026. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 21 HARERA files, with the dates we read them
Registration no.
GGM/672/404/2023/16
Registration valid till
30 Jun 2026
Declared possession
30 Jun 2026

Declared by the promoter to HARERA

Land area
4.127 (Acre) (16,701.38 sq m)
FAR
2.64 proposed of 2.64 permissible
licence
104 OF 2021 (13.12.2021)
Estimated project cost
₹435.40 crore
Cost of land
₹55.96 crore
Layout plan, declared approved (field 5a)
13 Dec 2021
Building plans, declared approved
12 Jan 2023
Construction to start
1 Feb 2023
Completion declared for
30 Jun 2026
Declared inventory · 5 types

Declared inventory

  • Apartment/Shops/Other Buildings · 104 units · 123.185 sq m carpet · 26 towers · one flat
  • Apartment/Shops/Other Buildings · 128 units · 124.207 sq m carpet · 32 towers · one flat
  • Apartment/Shops/Other Buildings · 32 units · 133.683 sq m carpet · 8 towers · one flat
  • Apartment/Shops/Other Buildings · 20 units · 123.835 sq m carpet · 5 towers · one flat
  • Apartment/Shops/Other Buildings · 20 units · 123.649 sq m carpet · 5 towers · one flat
Statutory approvals, as declared · 10

Statutory approvals, as declared

  • I. ENVIRONMENT CLEARANCE — declared: already been obtained (19 Aug 2022)
  • II. DTCP LICENSE — declared: already been obtained (10 Dec 2021)
  • III. LAYOUT PLAN APPROVAL — declared: already been obtained (13 Dec 2021)
  • IV. ELECTRICITY LOAD SANCTIONED — declared: already been obtained (19 Mar 2021)
  • V. SERVICE ESTIMATE — declared: already been obtained (16 May 2022)
  • VI. ZONING PLAN — declared: already been obtained (10 Aug 2022)
  • VII. FOREST NOC — declared: already been obtained (29 Dec 2021)
  • VIII. BR-III — declared: already been obtained (29 Dec 2022)
  • IX. LOI — declared: already been obtained (24 Sept 2021)
  • X. LC-IV — declared: already been obtained (10 Dec 2021)
On file with HARERA · 21 files

On file with HARERA (21)

Plans

Site plan

1 file
Approved Site Plan15 Sept 2022

Layout plan

1 file
Latest Layout Plan15 Sept 2022

Zoning plan

1 file
Zoning Plan14 Sept 2022

Building plans

1 file
BR III25 Jan 2023

Services

Sewerage and drainage

2 files
Drainage Plan25 Jan 2023Sewerage Plan25 Jan 2023

Water supply

2 files
Dual Plumbing Plan25 Jan 2023Water Supply Plan25 Jan 2023

Electricity

1 file
Electrical Load Approval Letter14 Sept 2022

Roads

1 file
Road Layout Plan25 Jan 2023

Approvals and clearances

Occupation certificate (OC)

1 file
OC uploaded17 Apr 2026

DTCP licence

3 files
LC-IV 47.75925 Jan 2023LOI 47.759 Acres25 Jan 2023Licence Copy with Land Schedule14 Sept 2022

Environment clearance

1 file
Environment Clearance Letter25 Jan 2023

Fire safety

1 file
Fire Fighting Plan25 Jan 2023

Land records

Land records

1 file
Revenue Record Entry of Licence and Collaboration14 Sept 2022

Money

Accounts and finance

3 files
CA Certificate25 Jan 2023Cash Flow Statement25 Jan 2023Non-Default Certificate from a CA14 Sept 2022

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit15 Sept 2022

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

104 OF 2021 · St. Patrics Realty Pvt. Ltd. · SOHNA

Licence valid to 9 Dec 2026

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 15 Sept 2022 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

104 OF 2021: 73 parcels, 47.7594 acres in all, in Dhunela (hadbast 182) and Berka (hadbast 181), tehsil Sohna.

The licence register prints the same licensed area, 47.759 acres.

  • 40//138 kanalDhunela (182)
  • 40//14/118 marlaDhunela (182)
  • 40//14/27 kanal 2 marlaDhunela (182)
  • 40//17/19 marlaDhunela (182)
Show the other 69 parcels
  • 40//17/2/14 kanal 9 marlaDhunela (182)
  • 40//17/2/21 kanal 2 marlaDhunela (182)
  • 40//17/3/113 marlaDhunela (182)
  • 40//18/16 kanal 18 marlaDhunela (182)
  • 40//77 kanal 10 marlaDhunela (182)
  • 40//88 kanalDhunela (182)
  • 40//98 kanalDhunela (182)
  • 41//258 kanalDhunela (182)
  • 42//14/12 kanal 10 marlaDhunela (182)
  • 42//168 kanalDhunela (182)
  • 42//178 kanalDhunela (182)
  • 42//188 kanalDhunela (182)
  • 42//198 kanalDhunela (182)
  • 42//20/24 kanalDhunela (182)
  • 42//218 kanalDhunela (182)
  • 42//228 kanalDhunela (182)
  • 42//238 kanalDhunela (182)
  • 42//248 kanalDhunela (182)
  • 42//25/14 kanalDhunela (182)
  • 42//25/24 kanalDhunela (182)
  • 45//1410 marlaDhunela (182)
  • 45//158 kanalDhunela (182)
  • 45//166 kanal 16 marlaDhunela (182)
  • 45//175 kanal 16 marlaDhunela (182)
  • 45//48 kanalDhunela (182)
  • 45//58 kanalDhunela (182)
  • 45//68 kanalDhunela (182)
  • 45//78 kanalDhunela (182)
  • 29//217 kanal 15 marlaDhunela (182)
  • 29//215 marlaDhunela (182)
  • 29//22/15 kanal 14 marlaDhunela (182)
  • 29//22/22 kanal 6 marlaDhunela (182)
  • 29//238 kanalDhunela (182)
  • 29//24/13 kanal 6 marlaDhunela (182)
  • 29//24/24 kanal 14 marlaDhunela (182)
  • 29//258 kanalDhunela (182)
  • 30//21/118 marlaDhunela (182)
  • 30//237 kanal 4 marlaDhunela (182)
  • 31//1/118 marlaDhunela (182)
  • 31//1/2/217 marlaDhunela (182)
  • 31//25 kanal 18 marlaDhunela (182)
  • 32//18 kanalDhunela (182)
  • 32//2/15 kanal 14 marlaDhunela (182)
  • 32//2/22 kanal 6 marlaDhunela (182)
  • 32//38 kanalDhunela (182)
  • 32//4/13 kanal 6 marlaDhunela (182)
  • 32//4/24 kanal 14 marlaDhunela (182)
  • 32//58 kanalDhunela (182)
  • 17//1/2/11 kanal 1 marlaBerka (181)
  • 17//10/22 kanal 4 marlaBerka (181)
  • 18//34 marlaBerka (181)
  • 18//4/17 kanalBerka (181)
  • 18//58 kanalBerka (181)
  • 18//6/15 kanalBerka (181)
  • 18//6/23 kanalBerka (181)
  • 18//8/15 marlaBerka (181)
  • 13//24/22 kanal 13 marlaBerka (181)
  • 13//25/1/22 kanal 11 marlaBerka (181)
  • 13//25/28 marlaBerka (181)
  • 14//118 kanalBerka (181)
  • 14//12/12 kanal 13 marlaBerka (181)
  • 14//208 kanalBerka (181)
  • 14//21/17 kanal 11 marlaBerka (181)
  • 14//9/25 kanal 7 marlaBerka (181)
  • 13//238 kanalBerka (181)
  • 40//710 marlaDhunela (182)
  • 45//147 kanal 10 marlaDhunela (182)
  • 30//22/26 kanalDhunela (182)
  • 18//37 kanal 16 marlaBerka (181)

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village you want: Dhunela (hadbast 182) or Berka (hadbast 181), tehsil Sohna. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 40//13.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan15 Sept 2022

Layout plan

1 file
Latest Layout Plan15 Sept 2022

Building plans

1 file
BR III25 Jan 2023

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (21 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/2116 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on St. Patricks Realty

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.