Key facts
- Registered by
- M/S RAHEJA DEVELOPERS LIMITEDthe company that filed it, for Raheja Developers
- 7 Apr 2015Layout plan approveddeclared to HARERA, read 29 Oct 2026
- 10 Jun 2015Building plans approveddeclared to HARERA, read 29 Oct 2026
- 6 Jul 2017Registered with HARERAHARERA, read 4 Nov 2026
- 5 Jul 2022Registration valid toHARERA, read 4 Nov 2026
- 31 Dec 2022Possession, as declareddeclared to HARERA, read 29 Oct 2026
Homes on offer
The homes the developer declared to HARERA, by size.
- Under 1,000 sq ft345–641 sq ft1,644
Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.
Location and connectivity
Where it is and what is near it. Every distance is a straight line, not a travel time.
Bhumiq holds no map point for this project yet.The site address declared to HARERA: SECTOR 14, SOHNA, GURUGRAM
The builder
- Other register states: 15
Questions buyers ask
Is Krishna Housing Scheme registered with HARERA?From the records · HARERA, read 4 Nov 2026
HARERA lists it as 21 OF 2017, registered on 6 Jul 2017. The register’s record shows an end date of 5 Jul 2022. The register shows it as: Registration lapsed.
The source ↗What is the possession timeline for Krishna Housing Scheme?From the records · HARERA, read 4 Nov 2026
When it registered the project, the developer declared that it would hand over homes by 31 Dec 2022. Its registration runs to 5 Jul 2022; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.
The source ↗How is the connectivity around Krishna Housing Scheme?From the records · HARERA, read 4 Nov 2026
Krishna Housing Scheme is in Nuh; the site address declared to HARERA is Sector 14, Sohna, Gurugram. Bhumiq has not measured its distance to the main roads and metro lines yet.
The source ↗What will I pay on top of the price?General guidance
You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.
Work out the stamp dutyWho is building Krishna Housing Scheme?From the records · HARERA, read 4 Nov 2026
Krishna Housing Scheme is a Raheja Developers project, registered by its company M/S RAHEJA DEVELOPERS LIMITED.
The source ↗Raheja Developers's projects and court recordThe records
What the registers hold for Krishna Housing Scheme: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.
- HARERA registration 21 OF 2017: Registration lapsed. The register’s record shows an end date of 5 Jul 2022.HARERA, read 4 Nov 2026 · See it on HARERA ↗
- Land licence 115 OF 2014 is on the DTCP register: Licence lapsed; the register prints its validity to 19 Aug 2021.DTCP, read 3 Nov 2026
- Plans approved, as the developer declared: layout plan 7 Apr 2015, building plans 10 Jun 2015.Declared to HARERA, read 29 Oct 2026
Flagged on the record
These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.
Not checked yet: the land owner records (jamabandi) and complaints at HARERA.
Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 8 HARERA files, with the dates we read them
- Registration no.
- 21 OF 2017
- Registration date
- 6 Jul 2017
- Registration valid till
- 5 Jul 2022
- Declared possession
- 31 Dec 2022
Declared by the promoter to HARERA
- Land area
- 10 (Acre) (40,468.56 sq m)
- FAR
- 2.25 proposed of 2.25 permissible
- licence
- 115 of 2014 dated 20.08.2014
- Estimated project cost
- ₹211.89 crore
- Cost of land
- ₹37.00 crore
- Layout plan, declared approved (field 5a)
- 7 Apr 2015
- Building plans, declared approved
- 10 Jun 2015
- Completion declared for
- 31 Dec 2022
Declared inventory · 5 types
Declared inventory
- APARTMENT/SHOPS/OTHER BUILDINGS Type 1 BHK TYPE 1 · 676 units · 38.496 sq m carpet · one flat
- APARTMENT/SHOPS/OTHER BUILDINGS Type 1 BHK TYPE 2 · 264 units · 32.093 sq m carpet · one flat
- APARTMENT/SHOPS/OTHER BUILDINGS Type 2 BHK TYPE 1 · 80 units · 58.608 sq m carpet · one flat
- APARTMENT/SHOPS/OTHER BUILDINGS Type 2 BHK TYPE 2 · 40 units · 59.514 sq m carpet · one flat
- APARTMENT/SHOPS/OTHER BUILDINGS Type 2 BHK TYPE 3 · 584 units · 42.022 sq m carpet · one flat
Statutory approvals, as declared · 8
Statutory approvals, as declared
- I. LICENSE NO. 115 OF 2014 — declared: already been obtained (20 Aug 2014)
- II. BUILDING PLAN — declared: already been obtained (10 Jun 2015)
- III. ENVIRONMENTAL CLEARANCE — declared: already been obtained (9 Mar 2015)
- IV. CONSENT TO ESTABLISH — declared: already been obtained (29 Aug 2017)
- V. AIRPORT HEIGHT CLEARANCE NOC — declared: already been obtained (15 Oct 2014)
- VI. HUDA CONSTRUCTION NOC — declared: already been obtained (4 Nov 2014)
- VII. POWER ASSURANCE — declared: already been obtained (27 Oct 2014)
- VIII. HUDA WATER NOC — declared: already been obtained (7 Oct 2014)
On file with HARERA · 8 files
On file with HARERA (8)
Plans
Site plan
1 fileLayout plan
1 fileZoning plan
1 fileBuilding plans
1 fileServices
Service plans
1 fileApprovals and clearances
DTCP licence
1 fileMoney
Accounts and finance
1 fileThe promoter’s papers
Declarations and affidavits
1 fileThese are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.
The DTCP licence named on the application
115 OF 2014 · Raheja Developers Ltd. · Sohna
Licence valid to 19 Aug 2021
From the Town & Country Planning department’s licence register, read 3 Nov 2026.
A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.
declared in the registration application (Form REP-I), Panchkula bench · submitted 7 Feb 2020 · read 29 Oct 2026 · not verified by Bhumiq
source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026
Land under the licence
The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.
115 OF 2014: 18 parcels, 10 acres in all, in Raisika (hadbast 174), tehsil Nuh.
The licence register prints the same licensed area, 10 acres.
- 2//2111 marla
- 7//16 kanal 17 marla
- 7//10/1/13 kanal 4 marla
- 7//127 kanal 10 marla
Show the other 14 parcels
- 7//138 kanal
- 7//142 kanal 1 marla
- 7//171 kanal 16 marla
- 7//18/14 kanal
- 7//18/24 kanal
- 7//197 kanal 10 marla
- 7//21/2min3 kanal
- 7//22/13 kanal
- 7//233 kanal 4 marla
- 7//83 kanal 7 marla
- 7//9/19 kanal 5 marla
- 8//1/23 kanal 19 marla
- 8//1/31 kanal 9 marla
- 8//2/17 kanal 7 marla
The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.
From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source
Who owns this land today, or is it mortgaged?
The Bhumiq team checks it with you.
Check it yourself on jamabandi.nic.in
- Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
- Pick district Gurugram, then the tehsil and the village: Raisika (hadbast 174), tehsil Nuh. The site lists villages in Hindi, so the hadbast number is the surer match.
- Pick the latest year, then a from the list here, such as 2//21.
- Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.
Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.
Layouts & payment plan
Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.
Site plan
1 fileLayout plan
1 fileBuilding plans
1 fileAmong the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (8 in all), none is a floor plan or a payment plan.
source: https://haryanarera.gov.in/view_project/project_preview_open/1265 · read 29 Oct 2026
The call is with the Bhumiq team. You need a free account so we can call you back.
Run due diligence on Raheja Developers
Its court cases, its DTCP licences and the source of each fact, free once you sign in.
Open the developer profileAs of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.