PARSVNATH CITY CENTER SONEPAT
by Parsvnath Developers · Sonipat
Not on our price list yet
Possession 30 Jun 2019 · as the developer declared it to HARERA
About this project
Key facts
- Registered by
- PARSVNATH DEVELOPERS LIMITEDthe company that filed it, for Parsvnath Developers
- 4 Dec 2007Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
- 30 Jun 2019Possession, as declareddeclared to HARERA, read 29 Oct 2026
- 31 Jul 2020Registration valid toHARERA, read 4 Nov 2026
Amenities and specifications
How the land is set aside and what comes in each home, as the developer declared them to HARERA.
- Apartment buildings2.35 acres · 58%
- Roads1.31 acres · 33%
- Parking0.37 acres · 9%
The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.
- Air-conditioningWater COOL system and mechanical ventilation through centrifugal fans
- Lifts6 lifts & 10 escalators
- FloorsCommon area – VDF/KOTA, polished granite/vitrified tiles or equivalent, marble/ ceramic tile shops - marble/ ceramic tile. toilets - combination of stone/granite/vitrified/ceramic tiles
- WallsCommon area – stone/vitrified tiles/stainless steel/textured paint covering, white WASH shops - plastering and OBD toilets – N/a celling – white WASH, POP gypsum
- BathroomsChinaware and CP fittings. electrical HAND dryer.
- WindowsToughened glass
- Main doorFrameless glass door
- Electrical fittingsAll ISI MARK fittings WILL USE
The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.
Location and connectivity
Where it is and what is near it. Every distance is a straight line, not a travel time.
Bhumiq holds no map point for this project yet.The site address declared to HARERA: CIVIL HOSPITAL SITE, NEW PWD GUEST HOUSE RALIWAY ROAD, SONEPAT
The builder
- Other register states: 7
Questions buyers ask
Is PARSVNATH CITY CENTER SONEPAT registered with HARERA?From the records · HARERA, read 4 Nov 2026
HARERA lists it as 141 OF 2017. The register’s record shows an end date of 31 Jul 2020. The register shows it as: Registration lapsed.
The source ↗What is the possession timeline for PARSVNATH CITY CENTER SONEPAT?From the records · HARERA, read 4 Nov 2026
When it registered the project, the developer declared that it would hand over homes by 30 Jun 2019. Its registration runs to 31 Jul 2020; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.
The source ↗How is the connectivity around PARSVNATH CITY CENTER SONEPAT?From the records · HARERA, read 4 Nov 2026
PARSVNATH CITY CENTER SONEPAT is in Sonipat; the site address declared to HARERA is Civil Hospital Site, New Pwd Guest House Raliway Road, Sonepat. Bhumiq has not measured its distance to the main roads and metro lines yet.
The source ↗What will I pay on top of the price?General guidance
You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.
Work out the stamp dutyWho is building PARSVNATH CITY CENTER SONEPAT?From the records · HARERA, read 4 Nov 2026
PARSVNATH CITY CENTER SONEPAT is a Parsvnath Developers project, registered by its company PARSVNATH DEVELOPERS LIMITED.
The source ↗Parsvnath Developers's projects and court recordThe records
What the registers hold for PARSVNATH CITY CENTER SONEPAT: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.
- HARERA registration 141 OF 2017: Registration lapsed. The register’s record shows an end date of 31 Jul 2020.HARERA, read 4 Nov 2026 · See it on HARERA ↗
- Plans approved, as the developer declared: layout plan 4 Dec 2007, building plans 4 Dec 2007.Declared to HARERA, read 29 Oct 2026
Flagged on the record
These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.
Amber flag: Registration lapsed
The register’s record shows an end date of 31 Jul 2020. HARERA Panchkula, read 4 Nov 2026. Source
Not checked yet: the land owner records (jamabandi) and complaints at HARERA.
Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 9 HARERA files, with the dates we read them
- Registration no.
- 141 OF 2017
- Registration valid till
- 31 Jul 2020
- Declared possession
- 30 Jun 2019
Declared by the promoter to HARERA
- Land area
- 4.03 (Acre) (16,308.83 sq m)
- FAR
- the application prints 200, which is not a ratio
- licence
- NA
- Estimated project cost
- ₹136.30 crore
- Cost of land
- ₹59.00 crore
- Layout plan, declared approved (field 5a)
- 4 Dec 2007
- Building plans, declared approved
- 4 Dec 2007
- Completion declared for
- 30 Jun 2019
Declared inventory · 1 type
Declared inventory
- APARTMENT/SHOPS/OTHER BUILDINGS Type SHOPS/SCO/FOOD COURT/MULTIPLEX (134 TO 35541 SQ FT.) · 703 units · 3,301 sq m carpet · a unit for another use, left out of home sizes
Statutory approvals, as declared · 1
Statutory approvals, as declared
- I. FIRE FIGHTING SCHEME — declared: already been obtained (1 Apr 2008)
On file with HARERA · 9 files
On file with HARERA (9)
Plans
Site plan
1 fileLayout plan
1 fileBuilding plans
1 fileServices
Service plans
1 fileApprovals and clearances
DTCP licence
1 fileLand records
Land records
1 fileMoney
Accounts and finance
2 filesThe promoter’s papers
Declarations and affidavits
1 fileThese are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.
The DTCP licence named on the application
The promoter declared NA. We could not read a licence number from that, so nothing is claimed about it here.
declared in the registration application (Form REP-I), Panchkula bench · submitted 1 Nov 2019 · read 29 Oct 2026 · not verified by Bhumiq
source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026
Layouts & payment plan
Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.
Site plan
1 fileLayout plan
1 fileBuilding plans
1 fileAmong the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (9 in all), none is a floor plan or a payment plan.
source: https://haryanarera.gov.in/view_project/project_preview_open/339 · read 29 Oct 2026
The call is with the Bhumiq team. You need a free account so we can call you back.
Run due diligence on Parsvnath Developers
Its court cases, its DTCP licences and the source of each fact, free once you sign in.
Open the developer profileAs of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.