Skip to content

SCO PHASE - 3 EXTENSION

by Omaxe World Street · Faridabad

Not on our price list yet

Possession 31 Aug 2030 · as the developer declared it to HARERA

About this project

Key facts

Location
Faridabad
Registered by
OMAXE WORLD STREETPRIVATE LIMITEDthe company that filed it, for Omaxe World Street
Timeline
  1. 11 Dec 2025Building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 31 Aug 2030Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside29,636 m² in all, by use
  • Roads14,975 m² · 51%
  • Plots for sale9,857 m² · 33%
  • Parking3,577 m² · 12%
  • Pavements1,227 m² · 4%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Bhumiq holds no map point for this project yet.The site address declared to HARERA: SECTOR 79 O, OMAXE CITY CENTRE FARIDABAD HARYANA -121004

The builder

Its 11 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 1
  • Registered, no OC or CC yet: 7
  • Other register states: 3

Questions buyers ask

Is SCO PHASE - 3 EXTENSION registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as HRERA-PKL-FBD-849-2026. Valid to 31 Aug 2030.

The source ↗
What is the possession timeline for SCO PHASE - 3 EXTENSION?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Aug 2030. Its registration runs to 31 Aug 2030; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around SCO PHASE - 3 EXTENSION?From the records · HARERA, read 4 Nov 2026

SCO PHASE - 3 EXTENSION is in Faridabad; the site address declared to HARERA is Sector 79 O, Omaxe City Centre Faridabad Haryana -121004. Bhumiq has not measured its distance to the main roads and metro lines yet.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building SCO PHASE - 3 EXTENSION?From the records · HARERA, read 4 Nov 2026

SCO PHASE - 3 EXTENSION is a Omaxe World Street project, registered by its company OMAXE WORLD STREETPRIVATE LIMITED.

The source ↗Omaxe World Street's projects and court record

The records

What the registers hold for SCO PHASE - 3 EXTENSION: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration HRERA-PKL-FBD-849-2026: Registered. Valid to 31 Aug 2030.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 158 OF 2025 is on the DTCP register, valid to 28 Aug 2030.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: building plans 11 Dec 2025.Declared to HARERA, read 29 Oct 2026
The court record of Omaxe World Street’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 12 HARERA files, with the dates we read them
Registration no.
HRERA-PKL-FBD-849-2026
Registration valid till
31 Aug 2030
Declared possession
31 Aug 2030

Declared by the promoter to HARERA

Land area
7.32325 (Acre) (29,636.14 sq m)
FAR
the application prints 117.02, which is not a ratio
licence
License No. 158 of 2025 and License No. 159 of 2025
Estimated project cost
₹98.37 crore
Cost of land
₹36.59 crore
Building plans, declared approved
11 Dec 2025
Construction to start
1 Jan 2026
Completion declared for
31 Aug 2030
Statutory approvals, as declared · 4

Statutory approvals, as declared

  • I. LAYOUT — declared: already been obtained (1 Sept 2025)
  • II. LICENSE NO 158 OF 2025 — declared: already been obtained (1 Sept 2025)
  • III. LICENSE NO 159 OF 2025 — declared: already been obtained (29 Aug 2025)
  • IV. STANDARD BUILDING PLAN — declared: already been obtained (11 Dec 2025)
On file with HARERA · 12 files

On file with HARERA (12)

Plans

Site plan

1 file
Approved Site Plan30 Dec 2025

Layout plan

1 file
Latest Layout Plan19 Dec 2025

Demarcation plan

1 file
Demarcation Plan19 Dec 2025

Building plans

1 file
Approved Building Plans, Full Set24 Dec 2025

Services

Service plans

1 file
Service Plans on the Layout19 Dec 2025

Approvals and clearances

DTCP licence

2 files
LC IV30 Dec 2025Licence Copy with Land Schedule19 Dec 2025

Land records

Land records

1 file
Revenue Record Entry of Licence and Collaboration19 Dec 2025

Sales papers

Payment plan

1 file
Payment Plan18 Feb 2026

Money

Accounts and finance

2 files
CA Certificate on the Application’s Figures2 Jan 2026Non-Default Certificate from a CA2 Jan 2026

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit18 Feb 2026

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The 2 DTCP licences named on the application

158 OF 2025 · Omaxe World Street Pvt. Ltd. · FARIDABAD

Licence valid to 28 Aug 2030

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

159 OF 2025 · Omaxe World Street Pvt. Ltd. · FARIDABAD

Licence valid to 28 Aug 2030

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Panchkula bench · submitted 5 Jan 2026 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/1 · fetched 4 Nov 2026

Land under the 2 licences

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

158 OF 2025: 13 parcels, 4.6813 acres in all, in Bhatola (hadbast 115), tehsil Faridabad.

The licence register prints the same licensed area, 4.6813 acres.

  • 37//13/2 min east1 kanal 2 marla
  • 37//14/11 kanal
  • 37//14/2/1 min south east4 kanal 3 marla
  • 37//14/2/2/14 marla
Show the other 9 parcels
  • 37//15/1/13 marla
  • 37//15/2/13 marla
  • 37//15/3/2 min2 kanal 4 marla
  • 37//6/16 kanal
  • 37//6/22 kanal
  • 37//7/11 kanal 10 marla
  • 37//7/26 kanal 10 marla
  • 40//17 kanal 9 marla
  • 40//2/15 kanal 1 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

159 OF 2025: 5 parcels, 2.6424 acres in all, in Bhatola (hadbast 115), tehsil Faridabad.

The licence register prints the same licensed area, 2.642 acres.

  • 37//248 kanal
  • 37//25/2/11 kanal 16 marla
  • 37//25/2/21 kanal 3 marla
  • 40//47 kanal 9 marla
Show the other 1 parcel
  • 40//5/1 min west2 kanal 14 marla 7 sarsai

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Faridabad, then the tehsil and the village: Bhatola (hadbast 115), tehsil Faridabad. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 37//13/2 min east.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan30 Dec 2025

Layout plan

1 file
Latest Layout Plan19 Dec 2025

Building plans

1 file
Approved Building Plans, Full Set24 Dec 2025

Payment plan

1 file
Payment Plan18 Feb 2026

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (12 in all), none is a floor plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/3882 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Omaxe World Street

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Panchkula records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.