ALTIS AT DXP 92

by Sare Gurugram · Sector 92, Gurugram

Not on our price list yet

Possession 31 Mar 2032 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 92, Gurugram4.8 km from Dwarka Expressway, in a straight line
Carpet area
1,264–1,268 sq ft
In m²about 117–118 m², as declared
Registered by
SARE GURUGRAM PRIVATE LIMITEDthe company that filed it, for Sare Gurugram
Timeline
  1. 17 Feb 2026Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 31 Dec 2031Registration valid toHARERA, read 4 Nov 2026
  3. 31 Mar 2032Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

100homes, 1,264 to 1,268 sq ft of carpet area
  • 1,000–1,500 sq ft1,264–1,268 sq ft100

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside2.68 acres in all, by use
  • Club house0.68 acres · 25%
  • Parking0.5 acres · 19%
  • Pavements0.47 acres · 18%
  • Parks and playgrounds0.33 acres · 12%
  • Roads0.26 acres · 10%
  • Apartment buildings0.17 acres · 6%
  • Land for community services, handed to the government0.13 acres · 5%
  • Green belts0.07 acres · 3%
  • Sewage and waste treatment0.04 acres · 1%
  • Electricity sub-station0.03 acres · 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningVRF system
  • KitchenGranite stone top platform with SS sink ceramic tile DADO upto 600MM above platform
  • Kitchen appliancesGeyser 3 litres - racold or equivalent
  • Lifts2 NOS. passenger and one no. service lifts - 1.75 M/ SEC speed - with automatic rescue device, intercom facility and CCTV installed per each tower / WING
  • FloorsLiving & dining area: stone flooring master bedroom: laminated wooden flooring other bedrooms: vitirified tile flooring bathrooms: vitrified tile flooring balconies: vitrified tile flooring REST of the areas: vitrified tile flooring
  • WallsEmulstion paint over gypsum / plaster
  • BathroomsWater conserving CP fittings of reputed make white colour chinawear of reputed make
  • WindowsUPVC sliding windows with 5MM THK clear glass

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 92, GurugramSector 92, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Dwarka ExpresswayOpen, 17 Aug 20254.8 km
  • Delhi–Gurugram–SNB RRTS5.2 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 3 projects in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 2
  • Other register states: 1

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it.

Questions buyers ask

Is ALTIS AT DXP 92 registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/1060/792/2026/32. Valid to 31 Dec 2031.

The source ↗
What is the possession timeline for ALTIS AT DXP 92?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 31 Mar 2032. Its registration runs to 31 Dec 2031; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around ALTIS AT DXP 92?From the records · Map pin and road lines, read 6 Sep 2026

ALTIS AT DXP 92 is in Sector 92, Gurugram; the site address declared to HARERA is Sector-92, Gurugram Haryana. In a straight line it is about 4.8 km from Dwarka Expressway and 5.2 km from Delhi–Gurugram–SNB RRTS.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building ALTIS AT DXP 92?From the records · HARERA, read 4 Nov 2026

ALTIS AT DXP 92 is a Sare Gurugram project, registered by its company SARE GURUGRAM PRIVATE LIMITED.

The source ↗Sare Gurugram's projects and court record

The records

What the registers hold for ALTIS AT DXP 92: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/1060/792/2026/32: Registered. Valid to 31 Dec 2031.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 68 OF 2011 is on the DTCP register: Licence lapsed; the register prints its validity to 20 Jul 2015.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 17 Feb 2026, building plans 17 Feb 2026.Declared to HARERA, read 29 Oct 2026
The court record of Sare Gurugram’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Licence 68 OF 2011 lapsed

    Named in this project’s application. Valid to 20 Jul 2015; no renewal on record. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 66 HARERA files, with the dates we read them
Registration no.
GGM/1060/792/2026/32
Registration valid till
31 Dec 2031
Declared possession
31 Mar 2032

Declared by the promoter to HARERA

Land area
2.68 (Acre) (10,845.58 sq m)
FAR
1.75 proposed of 1.75 permissible
licence
44 of 2009 and 68 of 2011
Estimated project cost
₹232.01 crore
Cost of land
₹6.96 crore
Layout plan, declared approved (field 5a)
17 Feb 2026
Building plans, declared approved
17 Feb 2026
Construction to start
1 Mar 2026
Completion declared for
31 Mar 2032
Declared inventory · 4 types

Declared inventory

  • Apartment/Shops/Other Buildings · 25 units · 117.47 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 25 units · 117.49 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 25 units · 117.562 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 25 units · 117.771 sq m carpet · 1 tower · one flat
Statutory approvals, as declared · 1

Statutory approvals, as declared

  • I. BR-III — declared: already been obtained (17 Feb 2026)
On file with HARERA · 66 files

On file with HARERA (66)

Plans

Site plan

2 files
Approved Site Plan13 Aug 2026Site Plan with Old Site Plan13 Aug 2026

Layout plan

2 files
Latest Layout Plan13 Aug 2026Superimposed Demarcation Plan on Approved Layout Plan13 Aug 2026

Zoning plan

1 file
Zoning Plan13 Aug 2026

Demarcation plan

1 file
Demarcation Plan21 Nov 2025

Building plans

1 file
BR III13 Aug 2026

Floor plans

2 files
Floor Plan13 Aug 2026Parking Plan13 Aug 2026

Services

Sewerage and drainage

1 file
Storm Water Drainage Plan13 Aug 2026

Electricity

2 files
Power Line Shiffting Approval13 Aug 2026Electricity Load Connection13 Aug 2026

Roads

2 files
Road Connectivity Sare Gurugram13 Aug 2026Road and Pavement Plan13 Aug 2026

Service plans

2 files
Service Estimate Plan-Complete13 Aug 2026Service Plan and Estimates Approval13 Aug 2026

Approvals and clearances

DTCP licence

5 files
Change of Developer13 Aug 2026LC-IV13 Aug 2026License with Renewals13 Aug 2026

Environment clearance

1 file
EC13 Aug 2026

Other NOCs and clearances

5 files
Construction Water NOC13 Aug 2026NCZ Approval13 Aug 2026Forest Land Diversion13 Aug 2026

Land records

Land records

12 files
Revenue Record Entry of Licence and Collaboration13 Aug 2026Supplementary Collaboration Agreement LH2 and Sare13 Aug 2026Aks-Shjra13 Aug 2026

Sales papers

Allotment and sale agreements

3 files
Conveyance Deed13 Aug 2026Allotment Letter13 Aug 2026BBA13 Aug 2026

Brochure and specifications

1 file
Altis Brochure13 Aug 2026

Money

Accounts and finance

11 files
3 Years Financial Report-61-11913 Aug 2026BR-Phase VI Current Ac Sbi Bank13 Aug 2026BR Bank Operations13 Aug 2026

The promoter’s papers

Declarations and affidavits

8 files
Affidavit Sare Gurugram (Wrt 4 (2) (L) (D)13 Aug 2026Affidavit Sare Gurugram NCZ13 Aug 2026Affidavit Sare Gurugram Forest Land Diversion13 Aug 2026

Company papers

2 files
GST13 Aug 2026ROC13 Aug 2026

Other filings

Other filings

2 files
Old Vs New13 Aug 2026Phase 6 Comparison of Area13 Aug 2026

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The 2 DTCP licences named on the application

44 OF 2009 · SA Infratech · GURGAON-MANESAR

Licence valid to 13 Aug 2029

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

68 OF 2011 · SA Infratech · GURGAON-MANESAR

Licence valid to 20 Jul 2015

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 23 Feb 2026 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the 2 licences

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

44 OF 2009

DTCP’s page showed no land schedule for licence 44 OF 2009 when Bhumiq read it on 18 Oct 2026. verify at source

68 OF 2011: 13 parcels, 7.0438 acres in all, in Wazirpur (hadbast 115) and Meoka (hadbast 121), tehsil Harsaru.

The licence register prints the same licensed area, 7.04 acres.

  • 91//12/11 kanal 8 marlaWazirpur (115)
  • 91//12/28 kanalWazirpur (115)
  • 91//138 kanalWazirpur (115)
  • 91//148 kanalWazirpur (115)
Show the other 9 parcels
  • 91//17/23 kanal 19 marlaWazirpur (115)
  • 91//188 kanalWazirpur (115)
  • 91//198 kanalWazirpur (115)
  • 91//203 kanal 14 marlaWazirpur (115)
  • 91//21/18 marlaWazirpur (115)
  • 91//8/112 marlaWazirpur (115)
  • 91//9/29 marlaWazirpur (115)
  • 8//3/25 kanal 12 marlaMeoka (121)
  • 91//3/35 marlaWazirpur (115)

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village you want: Wazirpur (hadbast 115) or Meoka (hadbast 121), tehsil Harsaru. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 91//12/1.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate

No one collector rate can be matched to this project's type.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

2 files
Approved Site Plan13 Aug 2026Site Plan with Old Site Plan13 Aug 2026

Layout plan

2 files
Latest Layout Plan13 Aug 2026Superimposed Demarcation Plan on Approved Layout Plan13 Aug 2026

Building plans

1 file
BR III13 Aug 2026

Floor plans

2 files
Floor Plan13 Aug 2026Parking Plan13 Aug 2026

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (66 in all), none is a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/3821 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Sare Gurugram

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.