Skip to content

CENTRAL AVENUE

by GLS Infraprojects · Sector 92, Gurugram

Not on our price list yet

Possession 17 Nov 2026 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 92, Gurugram4.8 km from Dwarka Expressway, in a straight line
Carpet area
427–624 sq ft
In m²about 40–58 m², as declared
Registered by
GLS INFRAPRROJECTS PVT. LTDthe company that filed it, for GLS Infraprojects
Timeline
  1. 28 Jul 2022Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 17 Nov 2026Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

162homes, 427 to 624 sq ft of carpet area
  • Under 1,000 sq ft427–624 sq ft162

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside1.106 acres in all, by use
  • Apartment buildings0.39 acres · 35%
  • Roads0.237 acres · 21%
  • Parks and playgrounds0.223 acres · 20%
  • Parking0.177 acres · 16%
  • Other usesas the form names them: Land0.079 acres · 7%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • KitchenOil bound distemper
  • LiftsAs per NBCC CODE
  • FloorsCeramic tiles
  • WallsOil bound distemper
  • BathroomsISI marked CP fitting, WC & washbasin
  • WindowsAluminium/UPVC section with 4MM thick glass
  • Main doorFlush doors (painted)
  • Electrical fittingsISI marked

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 92, GurugramSector 92, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Dwarka ExpresswayOpen, 17 Aug 20254.8 km
  • Delhi–Gurugram–SNB RRTS5.2 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 9 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 5
  • Registered, no OC or CC yet: 2
  • Other register states: 2

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it.

Questions buyers ask

Is CENTRAL AVENUE registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/600/332/2022/75. Valid to 17 Nov 2026.

The source ↗
What is the possession timeline for CENTRAL AVENUE?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 17 Nov 2026. Its registration runs to 17 Nov 2026; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around CENTRAL AVENUE?From the records · Map pin and road lines, read 6 Sep 2026

CENTRAL AVENUE is in Sector 92, Gurugram; the site address declared to HARERA is Sector 92 Gurugram, In The Revenue Estate Of Village Wazirpur, District Gurugram, Haryana. In a straight line it is about 4.8 km from Dwarka Expressway and 5.2 km from Delhi–Gurugram–SNB RRTS.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building CENTRAL AVENUE?From the records · HARERA, read 4 Nov 2026

CENTRAL AVENUE is a GLS Infraprojects project, registered by its company GLS INFRAPRROJECTS PVT. LTD.

The source ↗GLS Infraprojects's projects and court record

The records

What the registers hold for CENTRAL AVENUE: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/600/332/2022/75: Registered. Valid to 17 Nov 2026.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 98 OF 2021 is on the DTCP register: Licence ends soon; the register prints its validity to 17 Nov 2026.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 28 Jul 2022, building plans 28 Jul 2022.Declared to HARERA, read 29 Oct 2026
The court record of GLS Infraprojects’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Registration ends soon

    Valid to 17 Nov 2026. HARERA Gurugram, read 4 Nov 2026. Source

  • Amber flag: Licence 98 OF 2021 ends soon

    Named in this project’s application. Valid to 17 Nov 2026. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 47 HARERA files, with the dates we read them
Registration no.
GGM/600/332/2022/75
Registration valid till
17 Nov 2026
Declared possession
17 Nov 2026

Declared by the promoter to HARERA

Land area
1.10625 (Acre) (4,476.83 sq m)
FAR
2.37 proposed of 2.37 permissible
licence
98 of 2021 dated 18.11.2021
Estimated project cost
₹35.59 crore
Cost of land
₹4.36 crore
Layout plan, declared approved (field 5a)
28 Jul 2022
Building plans, declared approved
28 Jul 2022
Construction to start
1 Oct 2022
Completion declared for
17 Nov 2026
Declared inventory · 11 types

Declared inventory — 11 types declared, first 8 shown

  • Apartment/Shops/Other Buildings · 20 units · 40.93 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 20 units · 39.7 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 20 units · 41.48 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 2 units · 40.93 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 2 units · 39.7 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 2 units · 41.48 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 40 units · 57.99 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 40 units · 55.99 sq m carpet · 1 tower · one flat
Statutory approvals, as declared · 9

Statutory approvals, as declared

  • I. LOI — declared: already been obtained (3 Sept 2021)
  • II. LICENSE — declared: already been obtained (18 Nov 2021)
  • III. ELECTRIC LOAD ASSURANCE — declared: already been obtained (22 Mar 2022)
  • IV. HUDA CONSTRUCTION WATER NOC — declared: already been obtained (10 Feb 2022)
  • V. STORM WATER ASSURANCE — declared: already been obtained (9 Jun 2022)
  • VI. BUILDING PLAN — declared: already been obtained (18 Apr 2022)
  • VII. WATER ASSURANCE — declared: already been obtained (12 May 2022)
  • VIII. SEWERAGE ASSURANCE — declared: already been obtained (9 Jun 2022)
  • IX. EC — declared: applied for but yet to receive (28 May 2022)
On file with HARERA · 47 files

On file with HARERA (47)

Plans

Site plan

3 files
Approved Site Plan8 Jun 2022Demarcation Superimposed8 Jun 2022Drainage Site Plan8 Jun 2022

Layout plan

1 file
Latest Layout Plan8 Jun 2022

Zoning plan

1 file
Zoning Plan8 Jun 2022

Demarcation plan

1 file
Demarcation Plan8 Jun 2022

Building plans

6 files
Structure Plan5 Aug 2022Elevation Tower O8 Jun 2022Section Tower O8 Jun 2022

Floor plans

4 files
Tower O Ground and 1st8 Jun 2022Tower O Typical8 Jun 2022Tower P Ground and 1st8 Jun 2022Tower P Typical8 Jun 2022

Services

Sewerage and drainage

3 files
Sewerage Assurance9 Jun 2022Storm Water Assurance9 Jun 2022Sewerage Layout8 Jun 2022

Water supply

2 files
Water Assurance9 Jun 2022Water Supply Layout8 Jun 2022

Electricity

3 files
Electricity Plan5 Aug 2022Street Light Plan5 Aug 2022Power Load8 Jun 2022

Roads

1 file
Road Layout8 Jun 2022

Landscape and green areas

1 file
Paring and Green Area8 Jun 2022

Service plans

3 files
Solid Waste Plan5 Aug 2022Service Plans on the Layout8 Jun 2022Services8 Jun 2022

Approvals and clearances

DTCP licence

3 files
LOI8 Jun 2022Licence Copy with Land Schedule8 Jun 2022LC IV and Bilateral8 Jun 2022

Fire safety

1 file
Fire Site Plan8 Jun 2022

Other NOCs and clearances

2 files
STP Water NOC8 Jun 2022Forest NOC8 Jun 2022

Land records

Land records

5 files
Aks Sizra23 Jun 2022Mutation23 Jun 2022Revenue Record Entry of Licence and Collaboration9 Jun 2022

Money

Accounts and finance

4 files
Cash Flow Statement23 Jun 2022CA Certificate on the Application’s Figures23 Jun 2022Non-Default Certificate from a CA23 Jun 2022CA Certificate Cost Incurred23 Jun 2022

The promoter’s papers

Declarations and affidavits

2 files
The Promoter’s Declaration on Affidavit23 Jun 2022Affidavit23 Jun 2022

Other filings

Other filings

1 file
Commercial 28 Jun 2022

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

98 OF 2021 · GLS Infraprojects Pvt. Ltd. · GURGAON-MANESAR

Licence valid to 17 Nov 2026

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 23 Jun 2022 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

98 OF 2021: 5 parcels, 1.1063 acres in all, in Wazirpur (hadbast 115), tehsil Harsaru.

The licence register prints the same licensed area, 1.1063 acres.

  • 90//5/1/11 kanal 9 marla
  • 90//5/2/21 kanal 4 marla
  • 90//6/1/21 kanal 6 marla
  • 90//7/1min3 kanal 17 marla
Show the other 1 parcel
  • 90//4/2min1 kanal 1 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Wazirpur (hadbast 115), tehsil Harsaru. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 90//5/1/1.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate

No one collector rate can be matched to this project's type.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

3 files
Approved Site Plan8 Jun 2022Demarcation Superimposed8 Jun 2022Drainage Site Plan8 Jun 2022

Layout plan

1 file
Latest Layout Plan8 Jun 2022

Building plans

6 files
Structure Plan5 Aug 2022Elevation Tower O8 Jun 2022Section Tower O8 Jun 2022Approved Building Plans, Full Set8 Jun 2022Elevation Tower P8 Jun 2022Section Tower P8 Jun 2022

Floor plans

4 files
Tower O Ground and 1st8 Jun 2022Tower O Typical8 Jun 2022Tower P Ground and 1st8 Jun 2022Tower P Typical8 Jun 2022

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (47 in all), none is a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1978 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on GLS Infraprojects

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.