GRATITUDE 84
by Lamose Infra · Sector 84, Gurugram
Not on our price list yet
Possession 30 Apr 2032 · as the developer declared it to HARERA
About this project
Key facts
- Location
- Sector 84, Gurugram1.1 km from Dwarka Expressway, in a straight line
- Registered by
- LAMOSE INFRA LLPthe company that filed it, for Lamose Infra
- 25 Nov 2025Building plans approveddeclared to HARERA, read 29 Oct 2026
- 30 Apr 2032Possession, as declareddeclared to HARERA, read 29 Oct 2026
Homes on offer
The homes the developer declared to HARERA, by size.
- Under 1,000 sq ft728–875 sq ft154
Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft. Left out: 39 units under 25 m², because the form lists homes, shops and other buildings in one table.
Amenities and specifications
How the land is set aside and what comes in each home, as the developer declared them to HARERA.
- Other usesas the form names them: Guard and meter room, Internal roads and pavements, Area under commercial2,661 m² · 39%
- Parks and playgrounds2,004 m² · 29%
- Apartment buildings1,358 m² · 20%
- Roads446 m² · 7%
- Parking385 m² · 6%
The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.
- Air-conditioningWithout and with split AC
- KitchenSEMI furnished without modular
- Lifts4 no'S units per floor, 2 passenger lift, 1 service lift-johnson, thyssenkr UPP or equivalent
- FloorsLiving room, dining room, internal lobby area -imported marble / vetrified tile. master bedroom, other bedroom-laminated wooden flooring. master toilet, other toilet, kitchen, room/utility room - anti skid tiles. stair CASE-P- white
- WallsInternal wall-OBD & plastic emulsion. extern/AL wall-texture
- BathroomsFaucet, basin, WC
- Windows"aluminium with 6MM toughene D glass"
- Main doorLaminated shutter
The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.
Location and connectivity
Where it is and what is near it. Every distance is a straight line, not a travel time.
- Dwarka ExpresswayOpen, 17 Aug 20251.1 km
- Delhi–Gurugram–SNB RRTS2.3 km
- Sohna Elevated Corridor (NH-248A)7.5 km
Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.
Map data © OpenStreetMap contributors.
The builder
- Registered, no OC or CC yet: 1
Other projects nearby
8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.
| Project | Builder | Distance | Stage | Asking rate | Possession |
|---|---|---|---|---|---|
No photo of the project on file yet | Spaze Towers | Same sector | — | — | — |
No photo of the project on file yet | SS Group | Same sector | — | — | 31 Jul 2024 |
DevaanNo photo on file yet | Pivotal Infrastructure | Same sector | — | — | — |
No photo of the project on file yet | SS Group | Same sector | — | — | 31 Dec 2023 |
No photo of the project on file yet | SS Group | Same sector | — | — | 29 Feb 2024 |
No photo of the project on file yet | SS Group | Same sector | — | — | 31 Mar 2026 |
| Forever Buildtech | Same sector | — | — | 30 May 2030 | |
| Ganga Realty | Same sector | Under construction | ₹14,000/sq ft | 23 Feb 2028 |
Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it; asking rates from the Bhumiq team price list, 16 Sep 2026.
Questions buyers ask
Is GRATITUDE 84 registered with HARERA?From the records · HARERA, read 4 Nov 2026
HARERA lists it as GGM/1034/766/2026/06. Valid to 30 Apr 2032.
The source ↗What is the possession timeline for GRATITUDE 84?From the records · HARERA, read 4 Nov 2026
When it registered the project, the developer declared that it would hand over homes by 30 Apr 2032. Its registration runs to 30 Apr 2032; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.
The source ↗How is the connectivity around GRATITUDE 84?From the records · Map pin and road lines, read 6 Sep 2026
GRATITUDE 84 is in Sector 84, Gurugram; the site address declared to HARERA is Sector 84, Village Sikandepur Badha, Gurugram. In a straight line it is about 1.1 km from Dwarka Expressway, 2.3 km from Delhi–Gurugram–SNB RRTS and 7.5 km from Sohna Elevated Corridor (NH-248A).
The source ↗What will I pay on top of the price?General guidance
You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.
Work out the stamp dutyWho is building GRATITUDE 84?From the records · HARERA, read 4 Nov 2026
GRATITUDE 84 is a Lamose Infra project, registered by its company LAMOSE INFRA LLP.
The source ↗Lamose Infra's projects and court recordThe records
What the registers hold for GRATITUDE 84: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.
- HARERA registration GGM/1034/766/2026/06: Registered. Valid to 30 Apr 2032.HARERA, read 4 Nov 2026 · See it on HARERA ↗
- Land licence 68 OF 2025 is on the DTCP register, valid to 6 May 2030.DTCP, read 3 Nov 2026
- Plans approved, as the developer declared: building plans 25 Nov 2025.Declared to HARERA, read 29 Oct 2026
Not checked yet: the land owner records (jamabandi) and complaints at HARERA.
Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 53 HARERA files, with the dates we read them
- Registration no.
- GGM/1034/766/2026/06
- Registration valid till
- 30 Apr 2032
- Declared possession
- 30 Apr 2032
Declared by the promoter to HARERA
- Land area
- 1.69375 (Acre) (6,854.36 sq m)
- FAR
- 2.39 proposed of 2.4 permissible
- licence
- LC-68 OF 2025 dated 07.05.2025
- Estimated project cost
- ₹227.66 crore
- Cost of land
- ₹58.01 crore
- Building plans, declared approved
- 25 Nov 2025
- Construction to start
- 1 May 2026
- Completion declared for
- 30 Apr 2032
Declared inventory · 4 types
Declared inventory
- Apartment/Shops/Other Buildings · 152 units · 81.3 sq m carpet · 2 towers · one flat
- Apartment/Shops/Other Buildings · 2 units · 67.62 sq m carpet · 2 towers · one flat
- Apartment/Shops/Other Buildings · 30 units · 12 sq m carpet · 2 towers · under 25 m²: a shop or service unit the form does not label
- Apartment/Shops/Other Buildings · 9 units · 9 sq m carpet · 2 towers · under 25 m²: a shop or service unit the form does not label
Statutory approvals, as declared · 5
Statutory approvals, as declared
- I. LC V — declared: already been obtained (7 May 2025)
- II. BR III — declared: already been obtained (25 Nov 2025)
- III. ZONING PLAN — declared: already been obtained (9 May 2025)
- IV. AIRPORT HEIGHT CLEARANCE — declared: already been obtained (16 Jul 2025)
- V. FOREST NOC — declared: already been obtained (11 Feb 2025)
On file with HARERA · 53 files
On file with HARERA (53)
Plans
Site plan
3 filesLayout plan
1 fileZoning plan
1 fileDemarcation plan
1 fileBuilding plans
9 filesFloor plans
8 filesServices
Sewerage and drainage
2 filesWater supply
2 filesElectricity
1 fileApprovals and clearances
DTCP licence
4 filesEnvironment clearance
1 fileOther NOCs and clearances
7 filesLand records
Land records
2 filesSales papers
Allotment and sale agreements
2 filesMoney
Accounts and finance
5 filesThe promoter’s papers
Declarations and affidavits
3 filesOther filings
Other filings
1 fileThese are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.
The DTCP licence named on the application
68 OF 2025 · LAMOSE INFRA LLP · GURGAON-MANESAR
Licence valid to 6 May 2030
From the Town & Country Planning department’s licence register, read 3 Nov 2026.
A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.
declared in the registration application (Form REP-I), Gurugram bench · submitted 6 Dec 2025 · read 29 Oct 2026 · not verified by Bhumiq
source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026
Land under the licence
The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.
68 OF 2025: 2 parcels, 1.6938 acres in all, in Sikanderpur badha (hadbast 109), tehsil Manesar.
The licence register prints the same licensed area, 1.6938 acres.
- 2//188 kanal
- 2//23/15 kanal 11 marla
The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.
From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source
Who owns this land today, or is it mortgaged?
The Bhumiq team checks it with you.
Check it yourself on jamabandi.nic.in
- Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
- Pick district Gurugram, then the tehsil and the village: Sikanderpur badha (hadbast 109), tehsil Manesar. The site lists villages in Hindi, so the hadbast number is the surer match.
- Pick the latest year, then a from the list here, such as 2//18.
- Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.
Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.
Collector rate
No one collector rate can be matched to this project's type.
Layouts & payment plan
Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.
Site plan
3 filesLayout plan
1 fileBuilding plans
9 filesFloor plans
8 filesAmong the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (53 in all), none is a payment plan.
source: https://haryanarera.gov.in/view_project/project_preview_open/3769 · read 29 Oct 2026
The call is with the Bhumiq team. You need a free account so we can call you back.
Run due diligence on Lamose Infra
Its court cases, its DTCP licences and the source of each fact, free once you sign in.
Open the developer profileAs of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.