Skip to content

ATS Marigold

by ATS Real Estate Builders · Sector 89, Gurugram

Not on our price list yet

About this project

Key facts

Location
Sector 89, Gurugram1.7 km from Dwarka Expressway, in a straight linePrices and what changed
Carpet area
1,117–4,808 sq ft
In m²about 104–447 m², as declared
Registered
17 Aug 2017
Registered by
ATS REAL ESTATE BUILDERS PVT LTDthe company that filed it, for ATS Real Estate Builders
Timeline
  1. 6 Jun 2014Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 17 Aug 2017Registered with HARERAHARERA, read 3 Nov 2026
  3. 28 Feb 2027Registration valid toHARERA, read 3 Nov 2026

Homes on offer

The homes the developer declared to HARERA, by size.

428homes, 1,117 to 4,808 sq ft of carpet area
  • 1,000–1,500 sq ft1,117–1,340 sq ft312
  • 1,500–2,000 sq ft1,602 sq ft90
  • 2,000–2,500 sq ft2,203 sq ft8
  • 2,500–3,000 sq ft2,590 sq ft4
  • 3,000 sq ft and above3,459–4,808 sq ft14

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft. Left out: 83 units under 25 m², because the form lists homes, shops and other buildings in one table.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside11.125 acres in all, by use
  • Parks and playgrounds3.259 acres · 29%
  • Other uses2.517 acres · 23%
  • Apartment buildings2.028 acres · 18%
  • Roads1.239 acres · 11%
  • Parking1.085 acres · 10%
  • Pavements0.46 acres · 4%
  • Green belts0.367 acres · 3%
  • Land for community services, handed to the government0.106 acres · under 1%
  • Club house0.05 acres · under 1%
  • Electricity sub-station0.007 acres · under 1%
  • Sewage and waste treatment0.007 acres · under 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningSplit units in living room, dining & all bed rooms
  • KitchenAll kitchen counters in PRE-polished granite/ marble stone, electrical points for kitchen chimney & hob, washing machine & fridge to be provided. kitchen WILL be provided with modular cabinets of appropriate finish
  • LiftsLifts to be provided for access to all floors
  • FloorsVitrified tiles flooring in living, dining & lobby- wooden/ vitrified tiles flooring in bedrooms- vitrified tiles in kitchen, utility & servant room and ceramic tiles in toilets. staircase & landings to be in white marble flooring. balconies WILL be in anti-skid ceramic flooring
  • WallsOil bound distemper of appropriate colour on interior walls
  • BathroomsPremium sanitary fixtures, premium chrome plated fittings
  • WindowsUPVC and aluminium fixed and openable windows
  • Main doorFlush doors - polished/enamel painted; stainless steel/ brass finished hardware fittings for MAIN door & aluminium powder coated hardware fitting and locks of branded makes. door frames of seasoned hardwood

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 89, GurugramSector 89, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Dwarka ExpresswayOpen, 17 Aug 20251.7 km
  • Delhi–Gurugram–SNB RRTS4.3 km
  • Sohna Elevated Corridor (NH-248A)8.9 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 6 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 1
  • Registered, no OC or CC yet: 5

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it; asking rates from the Bhumiq team price list, 16 Sep 2026.

Questions buyers ask

Is ATS Marigold registered with HARERA?From the records · HARERA, read 3 Nov 2026

HARERA lists it as 55 OF 2017, registered on 17 Aug 2017. Valid to 28 Feb 2027.

The source ↗
How is the connectivity around ATS Marigold?From the records · Map pin and road lines, read 6 Sep 2026

ATS Marigold is in Sector 89, Gurugram; the site address declared to HARERA is Sector 89a, Village- Harsaru, Tehsil & District Gurugram, State-Haryana. In a straight line it is about 1.7 km from Dwarka Expressway, 4.3 km from Delhi–Gurugram–SNB RRTS and 8.9 km from Sohna Elevated Corridor (NH-248A).

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building ATS Marigold?From the records · HARERA, read 3 Nov 2026

ATS Marigold is a ATS Real Estate Builders project, registered by its company ATS REAL ESTATE BUILDERS PVT LTD.

The source ↗ATS Real Estate Builders's projects and court record
What protections do I have as a buyer?General guidance

Under the RERA Act, a registered project has to keep most of the money buyers pay in a separate bank account for that project, sell by carpet area, and stick to the plans it registered unless enough buyers agree to a change. If possession is late, a buyer can ask HARERA for interest or a refund. How this applies to your own purchase depends on your agreement, so ask a lawyer before you sign.

The records

What the registers hold for ATS Marigold: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration 55 OF 2017: Registered. Valid to 28 Feb 2027.HARERA, read 3 Nov 2026 · See it on HARERA ↗
  • Land licence 87 OF 2013 is on the DTCP register, valid to 10 Oct 2027.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 6 Jun 2014, building plans 6 Jun 2014.Declared to HARERA, read 29 Oct 2026
The court record of ATS Real Estate Builders’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Registration ends soon

    Valid to 28 Feb 2027. HARERA Gurugram, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 31 HARERA files, with the dates we read them
Registration no.
55 OF 2017
Registration date
17 Aug 2017
Registration valid till
28 Feb 2027

Declared by the promoter to HARERA

Land area
11.125 (Acre) (45,021.28 sq m)
FAR
the application prints 173.9, which is not a ratio
licence
87 of 2013(10-10-2017)
Estimated project cost
₹765.40 crore
Cost of land
₹148.79 crore
Layout plan, declared approved (field 5a)
6 Jun 2014
Building plans, declared approved
6 Jun 2014
Declared inventory · 10 types

Declared inventory — 10 types declared, first 8 shown

  • APARTMENT/SHOPS/OTHER BUILDINGS Type APARTMENT TYPE A(TOWER NO-3,6) · 90 units · 148.83 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type APARTMENT TYPE A PENTHOUSE(TOWER NO-3,6) · 4 units · 240.62 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type APARTMENT TYPE B(TOWER NO-1,2,4,5) · 156 units · 124.49 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type APARTMENT TYPE B GROUND FLOOR(TOWER NO-1,2,4,5) · 8 units · 204.66 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type APARTMENT TYPE B PENTHOUSE(TOWER NO-1,2,4,5) · 4 units · 331.57 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type APARTMENT TYPE C(TOWER NO-1,2,4,5) · 156 units · 103.77 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type APARTMENT TYPE C PENTHOUSE(TOWER NO-1,2,4,5) · 4 units · 321.35 sq m carpet · one flat
  • APARTMENT/SHOPS/OTHER BUILDINGS Type ROW HOUSE · 6 units · 446.67 sq m carpet · one flat
Statutory approvals, as declared · 13

Statutory approvals, as declared

  • I. FIRE FIGHTING (NOC) — declared: already been obtained (29 Dec 2014)
  • II. SERVICE ESTIMATE — declared: already been obtained (8 Jan 2016)
  • III. HEIGHT CLEARANCE (AAI) — declared: already been obtained (2 Jan 2014)
  • IV. NWBL NOC — declared: already been obtained (12 Jun 2014)
  • V. FOREST (ARAWALI) NOC — declared: already been obtained (1 Apr 2013)
  • VI. WATER NOC — declared: already been obtained (28 Nov 2013)
  • VII. STRUCTURE STABILITY — declared: already been obtained (16 May 2015)
  • VIII. ENVIRONMENT CLEARANCE — declared: already been obtained (3 Sept 2014)
  • IX. HARYANA STATE POLLUTION CONTROL BOARD — declared: already been obtained (20 Nov 2014)
  • X. SANCTION LETTER — declared: already been obtained (6 Jun 2016)
  • XI. TEMPORARY STRUCTURE APPROVAL — declared: already been obtained (24 Dec 2013)
  • XII. ZONING PLAN — declared: already been obtained (11 Oct 2013)
  • XIII. ELECTRIC POWER UNDERTAKING & APPLICATION — declared: already been obtained (27 Nov 2013)
On file with HARERA · 31 files

On file with HARERA (31)

Plans

Site plan

1 file
Approved Site Plan12 Dec 2019

Layout plan

1 file
Latest Layout Plan7 Feb 2020

Zoning plan

1 file
Zoning Plan12 Dec 2019

Demarcation plan

1 file
Demarcation Plan7 Feb 2020

Building plans

2 files
Building Plan Approval Letter (BR-III)27 Jul 2021Approved Building Plans, Full Set12 Dec 2019

Services

Service plans

3 files
Service Plan Estimates28 Jul 2021Service Plan Estimates Approval Letter28 Jul 2021Service Plans on the Layout12 Dec 2019

Approvals and clearances

DTCP licence

5 files
COD27 Jul 2021Renewal of License (Marigold)27 Jul 2021ATS Marigold LOI7 Feb 2020

Environment clearance

1 file
Environment Clearance Approval7 Feb 2020

Fire safety

1 file
Fire NOC7 Feb 2020

Other NOCs and clearances

2 files
Airport Height Clearance7 Feb 2020Forest NOC7 Feb 2020

Land records

Land records

3 files
Non Encumbrance Certificate7 Feb 2020License Along with Land Schedule7 Feb 2020Revenue Record Entry of Licence and Collaboration12 Dec 2019

Sales papers

Allotment and sale agreements

1 file
Gist of the Important Provisions of Draft Agreement28 Jan 2021

Money

Accounts and finance

5 files
Deficit Fees27 Jul 2021Cash Flow Statement22 Jul 2021CA Certificate on the Application’s Figures22 Jul 2021

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit1 Jun 2021

Company papers

1 file
Board Resolution7 Feb 2020

Other filings

Other filings

2 files
Project Continuation- RC/REP/HARERA/GGM/55 of 2017/7(3)/2022/07 Dated 24.06.20249 Jul 2024PROJECT CONTINUATION- RC/REP/HARERA/GGM/55 of 2017/7(3)/2022/07 DATED 20.09.202226 Dec 2022

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

87 OF 2013 · Vatika Ltd. · GURGAON-MANESAR

Licence valid to 10 Oct 2027

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 24 Dec 2019 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 3 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

87 OF 2013: 14 parcels, 11.125 acres in all, in Harsuru (hadbast 107), tehsil Harsaru.

The licence register prints the same licensed area, 11.13 acres.

  • 44//128 kanal
  • 44//138 kanal
  • 44//148 kanal
  • 44//158 kanal
Show the other 10 parcels
  • 44//161 kanal
  • 44//178 kanal
  • 44//18/14 kanal
  • 44//18/24 kanal
  • 44//19/14 kanal
  • 44//19/24 kanal
  • 44//218 kanal
  • 44//228 kanal
  • 44//238 kanal
  • 44//248 kanal

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Harsuru (hadbast 107), tehsil Harsaru. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 44//12.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate, residential flat
₹7,000 per sq ft

Sector 89, collector rates effective 1 Apr 2026, Harsaru tehsil. Source

Stamp duty is charged on the higher of the price and the collector rate value. The rate is the government's floor for duty, not a valuation: Bhumiq does not say what a flat is worth.

Worked out on this page. Not saved or sent.

Lenders that list this project

  • PNB Housing Finance’s approved-projects list carries “ATS MARIGOLD”, by ATS REAL ESTATE BUILDERS PRIVATE LIMITED, code NCR-0617-746, approved 2017.

    PNB Housing Finance’s own page · read 26 Oct 2026 · www.pnbhousing.com ↗

A lender’s list prints no HARERA registration or licence number, so the Bhumiq team matched it to this project by its name and builder. A listing is the lender’s record of a project it has approved for home loans, not a loan offer.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan12 Dec 2019

Layout plan

1 file
Latest Layout Plan7 Feb 2020

Building plans

2 files
Building Plan Approval Letter (BR-III)27 Jul 2021Approved Building Plans, Full Set12 Dec 2019

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (31 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/940 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on ATS Real Estate Builders

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.