MANGLAM MULTIPLEX PRIVATE LIMITEDthe company that filed it, for Manglam Multiplex
Timeline
  1. 16 Aug 2022Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 28 Feb 2027Possession, as declareddeclared to HARERA, read 29 Oct 2026

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside4 acres in all, by use
  • Other usesas the form names them: Area under commercial units1.953 acres · 49%
  • Parks and playgrounds1.036 acres · 26%
  • Roads1.011 acres · 25%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningProvision in retail & common area NON a/C
  • Lifts3 NOS passenger & 5 NOS service lifts
  • FloorsBARE R.C.C. SLAB
  • WallsLavel plast / white putty
  • WindowsAluminium frame
  • Main doorAluminium and glass for retail
  • Electrical fittingsLED type fittings in common area only
  • Wi-Fi and broadbandBroad BAND provided

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 65, GurugramSector 65, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Sohna Elevated Corridor (NH-248A)2.4 km
  • Delhi–Gurugram–SNB RRTS5.8 km
  • Dwarka ExpresswayOpen, 17 Aug 20257.7 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 4 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 3
  • Other register states: 1

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it.

Questions buyers ask

Is M3M ROUTE65 registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/605/337/2022/80. Valid to 28 Feb 2027.

The source ↗
What is the possession timeline for M3M ROUTE65?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 28 Feb 2027. Its registration runs to 28 Feb 2027; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around M3M ROUTE65?From the records · Map pin and road lines, read 6 Sep 2026

M3M ROUTE65 is in Sector 65, Gurugram; the site address declared to HARERA is Village Maidawas, Sector-65, Gurugram, Haryana. In a straight line it is about 2.4 km from Sohna Elevated Corridor (NH-248A), 5.8 km from Delhi–Gurugram–SNB RRTS and 7.7 km from Dwarka Expressway.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building M3M ROUTE65?From the records · HARERA, read 4 Nov 2026

M3M ROUTE65 is a Manglam Multiplex project, registered by its company MANGLAM MULTIPLEX PRIVATE LIMITED.

The source ↗Manglam Multiplex's projects and court record

The records

What the registers hold for M3M ROUTE65: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/605/337/2022/80: Registered. Valid to 28 Feb 2027.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 84 OF 2022 is on the DTCP register, valid to 5 Jul 2027.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 16 Aug 2022, building plans 16 Aug 2022.Declared to HARERA, read 29 Oct 2026
The court record of Manglam Multiplex’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Amber flag: Registration ends soon

    Valid to 28 Feb 2027. HARERA Gurugram, read 4 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 37 HARERA files, with the dates we read them
Registration no.
GGM/605/337/2022/80
Registration valid till
28 Feb 2027
Declared possession
28 Feb 2027

Declared by the promoter to HARERA

Land area
4.00 (Acre) (16,187.43 sq m)
FAR
1.69 proposed
licence
84 of 2022 dated 06-07-2022
Estimated project cost
₹229.13 crore
Cost of land
₹33.67 crore
Layout plan, declared approved (field 5a)
16 Aug 2022
Building plans, declared approved
16 Aug 2022
Construction to start
31 Aug 2022
Completion declared for
28 Feb 2027
Declared inventory · 1 type

Declared inventory

  • Apartment/Shops/Other Buildings · 727 units · 18,531.37 sq m carpet · total for 727 flats, about 25.5 m² each
Statutory approvals, as declared · 7

Statutory approvals, as declared

  • I. LICENCE — declared: already been obtained (6 Jul 2022)
  • II. ZONING PLAN — declared: already been obtained (6 Jul 2022)
  • III. LOI — declared: already been obtained (8 Apr 2022)
  • IV. ARAVALI NOC — declared: already been obtained (7 Jul 2018)
  • V. FOREST NOC — declared: already been obtained (4 Jul 2018)
  • VI. BUILDING PLAN APPROVAL — declared: already been obtained (16 Aug 2022)
  • VII. ENVIRONMENT CLEARANCE — declared: already been obtained (17 Feb 2020)
On file with HARERA · 37 files

On file with HARERA (37)

Plans

Site plan

2 files
Superimposed Demarcation on Site Plan29 Aug 2022Approved Site Plan27 Aug 2022

Layout plan

1 file
Latest Layout Plan16 Aug 2022

Zoning plan

1 file
Zoning Plan2 Aug 2022

Demarcation plan

1 file
Demarcation Plan16 Aug 2022

Building plans

4 files
Structural Plans29 Aug 2022BR-Iiiapproved Building Plan27 Aug 2022Elevations27 Aug 2022Sectional Plan27 Aug 2022

Floor plans

2 files
Floor Plans27 Aug 2022Parking Plans27 Aug 2022

Services

Sewerage and drainage

2 files
Plan for Sewerage Scheme29 Aug 2022Plan for Storm Water Scheme29 Aug 2022

Water supply

1 file
Plan for Water Supply Scheme29 Aug 2022

Electricity

1 file
Electricity Supply and Street Light Plans29 Aug 2022

Roads

1 file
Plan for Road Scheme29 Aug 2022

Landscape and green areas

1 file
Landscape Plans29 Aug 2022

Approvals and clearances

Completion certificate (CC)

2 files
CC uploaded21 Jan 2026CC uploaded21 Jan 2026

DTCP licence

2 files
LOI6 Aug 2022Licence Copy with Land Schedule2 Aug 2022

Environment clearance

1 file
Environment Clearance16 Aug 2022

Fire safety

5 files
Fire Plan Ground Floor29 Aug 2022Fire Plan First Floor29 Aug 2022Fire Plan Second Floor29 Aug 2022

Land records

Land records

2 files
Entry of License in Revenue Records17 Aug 2022NEC5 Aug 2022

Money

Accounts and finance

6 files
Project Report29 Aug 2022CA Certificate on the Application’s Figures6 Aug 2022Non-Default Certificate from a CA6 Aug 2022

Timeline and progress

Construction schedule

1 file
PERT Chart -Manglam 4 Acres27 Aug 2022

The promoter’s papers

Declarations and affidavits

1 file
The Promoter’s Declaration on Affidavit9 Aug 2022

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

84 OF 2022 · Manglam Multiplex Pvt Ltd · GURGAON-MANESAR

Licence valid to 5 Jul 2027

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 17 Aug 2022 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

84 OF 2022: 6 parcels, 4 acres in all, in Madabass (hadbast 85), tehsil Badshahpur.

The licence register prints the same licensed area, 4 acres.

  • 21//13/14 kanal
  • 21//13/24 kanal
  • 21//188 kanal
  • 21//19/14 kanal 11 marla
Show the other 2 parcels
  • 21//238 kanal
  • 30//3/1/13 kanal 9 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Madabass (hadbast 85), tehsil Badshahpur. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 21//13/1.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate

No one collector rate can be matched to this project's type.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

2 files
Superimposed Demarcation on Site Plan29 Aug 2022Approved Site Plan27 Aug 2022

Layout plan

1 file
Latest Layout Plan16 Aug 2022

Building plans

4 files
Structural Plans29 Aug 2022BR-Iiiapproved Building Plan27 Aug 2022Elevations27 Aug 2022Sectional Plan27 Aug 2022

Floor plans

2 files
Floor Plans27 Aug 2022Parking Plans27 Aug 2022

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (37 in all), none is a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/2053 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Manglam Multiplex

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.