Key facts

Location
Sector 63, Gurugram3.5 km from Sohna Elevated Corridor (NH-248A), in a straight linePrices and what changed
Registered
6 Sep 2018
Registered by
BLACKBERRY REALCON PRIVATE LIMITEDthe company that filed it, for Blackberry Realtime
Timeline
  1. 6 Sep 2018Registered with HARERAHARERA, read 4 Nov 2026
  2. 31 Dec 2018Registration valid toHARERA, read 4 Nov 2026

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 63, GurugramSector 63, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Sohna Elevated Corridor (NH-248A)3.5 km
  • Delhi–Gurugram–SNB RRTS7.4 km
  • Dwarka ExpresswayOpen, 17 Aug 20259.4 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 1

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it.

Questions buyers ask

Is Paras Square registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/281/2018/13, registered on 6 Sep 2018. Ended 31 Dec 2018. The register shows it as: Registration expired.

The source ↗
How is the connectivity around Paras Square?From the records · Map pin and road lines, read 6 Sep 2026

Paras Square is in Sector 63, Gurugram; the site address declared to HARERA is Sector-63a, Gurgaon. In a straight line it is about 3.5 km from Sohna Elevated Corridor (NH-248A), 7.4 km from Delhi–Gurugram–SNB RRTS and 9.4 km from Dwarka Expressway.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building Paras Square?From the records · HARERA, read 4 Nov 2026

Paras Square is a Blackberry Realtime project, registered by its company BLACKBERRY REALCON PRIVATE LIMITED.

The source ↗Blackberry Realtime's projects and court record
What protections do I have as a buyer?General guidance

Under the RERA Act, a registered project has to keep most of the money buyers pay in a separate bank account for that project, sell by carpet area, and stick to the plans it registered unless enough buyers agree to a change. If possession is late, a buyer can ask HARERA for interest or a refund. How this applies to your own purchase depends on your agreement, so ask a lawyer before you sign.

The records

What the registers hold for Paras Square: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/281/2018/13: Registration expired. Ended 31 Dec 2018.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Land licence 23 OF 2013 is on the DTCP register: Licence ended, LC-IX linked; the register prints its validity to 16 May 2017.DTCP, read 3 Nov 2026
The court record of Blackberry Realtime’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Registration expired

    Ended 31 Dec 2018. HARERA Gurugram, read 4 Nov 2026. Source

  • Amber flag: Licence 23 OF 2013 validity ended

    Named in this project’s application. Valid to 16 May 2017. The register links a completion certificate (LC-IX), dated 24 Jan 2020, against this licence. DTCP Haryana register, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 49 HARERA files, with the dates we read them
Registration no.
GGM/281/2018/13
Registration date
6 Sept 2018
Registration valid till
31 Dec 2018

Declared by the promoter to HARERA

Land area
2.2 (Acre) (8,903.08 sq m)
FAR
3.84 proposed of 3.84 permissible
licence
23 OF 2013
Estimated project cost
₹156.00 crore
Declared inventory · 6 types

Declared inventory

  • APARTMENT/SHOPS/OTHER BUILDINGS Type RETAIL · 174 units · 52,985.31 sq m carpet
  • APARTMENT/SHOPS/OTHER BUILDINGS Type STUDIO 870 · 44 units · 18,920 sq m carpet
  • APARTMENT/SHOPS/OTHER BUILDINGS Type 2BR (1225) · 4 units
  • APARTMENT/SHOPS/OTHER BUILDINGS Type STUDIO 800 · 31 units · 2,303.92 sq m carpet
  • APARTMENT/SHOPS/OTHER BUILDINGS Type 1BR (975) · 56 units · 5,072.48 sq m carpet
  • APARTMENT/SHOPS/OTHER BUILDINGS Type 2BR (1935) · 7 units · 907.13 sq m carpet
Statutory approvals, as declared · 2

Statutory approvals, as declared

  • I. LICENSE COPY LC-V ISSUED BT DTCP — declared: already been obtained (17 May 2013)
  • II. RENEWAL OF LICENSE NO. 23 OF 2013 — declared: already been obtained (16 Oct 2017)
On file with HARERA · 49 files

On file with HARERA (49)

Plans

Site plan

3 files
Site Plan28 Feb 2020Site Plan28 Feb 2020Approved Site Plan14 Jan 2020

Layout plan

1 file
Latest Layout Plan14 Jan 2020

Zoning plan

1 file
Zoning Plan28 Feb 2020

Demarcation plan

1 file
Demarcation Plan28 Feb 2020

Building plans

8 files
Typical, Terrace, Mumty Plan28 Feb 2020Building Plan Approval Letter- Square28 Feb 2020Section- 0228 Feb 2020

Floor plans

8 files
Third Floor Plan28 Feb 2020Ground Floor Plan28 Feb 2020First Floor Plan28 Feb 2020

Services

Sewerage and drainage

2 files
Service Estimate Plan-Storm Water28 Feb 2020Service Estimate Plan-Sewerage Scheme28 Feb 2020

Water supply

1 file
Service Estimate Plan-Water Supply28 Feb 2020

Roads

1 file
Service Estimate Plan-Road Work28 Feb 2020

Service plans

2 files
Service Plan Estimates-Approval Letter28 Feb 2020Service Plans on the Layout14 Jan 2020

Approvals and clearances

Occupation certificate (OC)

1 file
Occupation Certificate20 Mar 2026

Completion certificate (CC)

1 file
Completion Certificate20 Mar 2026

DTCP licence

4 files
LOI -Square28 Feb 2020LC-IV- Square28 Feb 2020Renewal License Copy14 Jan 2020Licence Copy with Land Schedule14 Jan 2020

Environment clearance

1 file
Environment Clearance- Square28 Feb 2020

Fire safety

1 file
Fire NOC- Square28 Feb 2020

Other NOCs and clearances

2 files
Airport Clearance- Square28 Feb 2020Forest NOC-Square28 Feb 2020

Sales papers

Allotment and sale agreements

2 files
Builder Buyer Agreement14 Jan 2020Allottment Letter14 Jan 2020

Money

Accounts and finance

3 files
Authorized Signatories for Bank- Square28 Feb 2020CA Certificate on the Application’s Figures14 Jan 2020Non-Default Certificate from a CA14 Jan 2020

The promoter’s papers

Declarations and affidavits

2 files
Rep-I Paras-Square28 Feb 2020The Promoter’s Declaration on Affidavit14 Jan 2020

Other filings

Other filings

4 files
RERA Certificate- Square28 Feb 2020Areas28 Feb 2020Toilet Details28 Feb 2020RERA Brief Synopsis--Square28 Feb 2020

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

23 OF 2013 · Blackberry Realcon Pvt. Ltd. · GURGAON-MANESAR

Licence valid to 16 May 2017

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 14 Jan 2020 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

23 OF 2013: 3 parcels, 2.2 acres in all, in Behrampur (hadbast 80), tehsil Wazirabad.

The licence register prints the same licensed area, 2.2 acres.

  • 29//19 min1 kanal 12 marla
  • 29//208 kanal
  • 30//168 kanal

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Behrampur (hadbast 80), tehsil Wazirabad. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 29//19 min.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate, commercial property
₹2,53,440 per sq yd

Sector 63, collector rates effective 1 Apr 2026, Wazirabad tehsil. 2 tehsil lists price this sector; this is the higher. Source

Stamp duty is charged on the higher of the price and the collector rate value. The rate is the government's floor for duty, not a valuation: Bhumiq does not say what a property is worth.

Worked out on this page. Not saved or sent.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

3 files
Site Plan28 Feb 2020Site Plan28 Feb 2020Approved Site Plan14 Jan 2020

Layout plan

1 file
Latest Layout Plan14 Jan 2020

Building plans

8 files
Typical, Terrace, Mumty Plan28 Feb 2020Building Plan Approval Letter- Square28 Feb 2020Section- 0228 Feb 2020Elevation 2 & 428 Feb 2020Section-0328 Feb 2020Section-0128 Feb 2020

Floor plans

8 files
Third Floor Plan28 Feb 2020Ground Floor Plan28 Feb 2020First Floor Plan28 Feb 2020Second Floor Plan28 Feb 2020Basement-02 Plan28 Feb 2020Basement-03 Plan28 Feb 2020

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (49 in all), none is a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1041 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Blackberry Realtime

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.