Possession 6 Feb 2030 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 56, Gurugram5.8 km from Sohna Elevated Corridor (NH-248A), in a straight line
Carpet area
1,385–3,646 sq ft
In m²about 129–339 m², as declared
Registered by
JHS ESTATE PRIVATE LIMITEDthe company that filed it, for Jhs Estate
Timeline
  1. 29 Jul 2024Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 6 Feb 2030Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

86homes, 1,385 to 3,646 sq ft of carpet area
  • 1,000–1,500 sq ft1,385 sq ft44
  • 1,500–2,000 sq ft1,577–1,842 sq ft40
  • 3,000 sq ft and above3,646 sq ft2

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside8,334 m² in all, by use
  • Apartment buildings3,415 m² · 41%
  • Roads2,338 m² · 28%
  • Shops and offices1,058 m² · 13%
  • Parks and playgrounds809 m² · 10%
  • Green belts499 m² · 6%
  • Other usesas the form names them: Guardroomandbasementandstaircasemumty, Rain water harvesting168 m² · 2%
  • Electricity sub-station47 m² · under 1%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • Air-conditioningVRV / VRF
  • KitchenWalls: plaster + DADO above counterup to 2FT high in vitrified tile
  • FloorsItalian/ imported marble/ vitrified tile/laminate wooden flooring/ antiskidvitrified
  • WallsPlaster + DADO up to 7FT in vitrifiedtile(only for toilets)
  • WindowsUPVC / aluminium framed single/doubleglazing unit as per HEAT LOAD and asper design
  • Main doorWooden frame with flush door withveneer / laminate finish (on both sides)& architraves
  • Electrical fittingsModular switches and sockets
  • Wi-Fi and broadbandThrough FTTH system

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 56, GurugramSector 56, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Sohna Elevated Corridor (NH-248A)5.8 km
  • Delhi–Gurugram–SNB RRTS6.2 km
  • Dwarka ExpresswayOpen, 17 Aug 202510.8 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 1 project in Bhumiq’s records, by what HARERA’s record shows
  • Registered, no OC or CC yet: 1

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it; asking rates from the Bhumiq team price list, 16 Sep 2026.

Questions buyers ask

Is TREVOC ROYAL RESIDENCES registered with HARERA?From the records · HARERA, read 4 Nov 2026

HARERA lists it as GGM/863/595/2024/90. Valid to 6 Feb 2030.

The source ↗
What is the possession timeline for TREVOC ROYAL RESIDENCES?From the records · HARERA, read 4 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 6 Feb 2030. Its registration runs to 6 Feb 2030; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around TREVOC ROYAL RESIDENCES?From the records · Map pin and road lines, read 6 Sep 2026

TREVOC ROYAL RESIDENCES is in Sector 56, Gurugram; the site address declared to HARERA is Sector 56, Urban Estate, Gurgaon Ii, Haryana. In a straight line it is about 5.8 km from Sohna Elevated Corridor (NH-248A), 6.2 km from Delhi–Gurugram–SNB RRTS and 10.8 km from Dwarka Expressway.

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building TREVOC ROYAL RESIDENCES?From the records · HARERA, read 4 Nov 2026

TREVOC ROYAL RESIDENCES is a Jhs Estate project, registered by its company JHS ESTATE PRIVATE LIMITED.

The source ↗Jhs Estate's projects and court record

The records

What the registers hold for TREVOC ROYAL RESIDENCES: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/863/595/2024/90: Registered. Valid to 6 Feb 2030.HARERA, read 4 Nov 2026 · See it on HARERA ↗
  • Plans approved, as the developer declared: layout plan 29 Jul 2024, building plans 29 Jul 2024.Declared to HARERA, read 29 Oct 2026
The court record of Jhs Estate’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 54 HARERA files, with the dates we read them
Registration no.
GGM/863/595/2024/90
Registration valid till
6 Feb 2030
Declared possession
6 Feb 2030

Declared by the promoter to HARERA

Land area
2.059 (Acre) (8,332.48 sq m)
FAR
4.12 proposed of 4.12 permissible
licence
Land allotted by HSVP through LOIEndst No.ZO002/EO018/UE029/LALOT/0000000385
Estimated project cost
₹589.78 crore
Cost of land
₹149.19 crore
Layout plan, declared approved (field 5a)
29 Jul 2024
Building plans, declared approved
29 Jul 2024
Construction to start
8 Aug 2024
Completion declared for
6 Feb 2030
Declared inventory · 5 types

Declared inventory

  • Apartment/Shops/Other Buildings · 2 units · 128.68 sq m carpet · 2 towers · one flat
  • Apartment/Shops/Other Buildings · 38 units · 171.11 sq m carpet · 2 towers · one flat
  • Apartment/Shops/Other Buildings · 2 units · 146.52 sq m carpet · 2 towers · one flat
  • Apartment/Shops/Other Buildings · 2 units · 338.68 sq m carpet · 2 towers · one flat
  • Apartment/Shops/Other Buildings · 42 units · 128.68 sq m carpet · 2 towers · one flat
Statutory approvals, as declared · 14

Statutory approvals, as declared

  • I. NO OBJECTION CERTIFICATE FOR HEIGHT CLEARANCE — declared: already been obtained (26 Feb 2024)
  • II. ASSURANCE FOR DRINKING WATER SUPPLY, SEWERCONNECTION AND STORM WATER CONNECTION — declared: already been obtained (7 Feb 2024)
  • III. NOC FOR USE OF TREATED WASTE WATER FORCONSTRUCTION ACTIVITIES — declared: already been obtained (13 Feb 2024)
  • IV. GRANT OF PERMISSION FOR TRANSFER OF TDR CERTIFICATES — declared: already been obtained (9 Apr 2024)
  • V. ASSURANCE CERTIFICATE OF DHBVN FOR POWER SUPPLY — declared: already been obtained (22 Feb 2024)
  • VI. GREEN RATING FOR INTEGRATED HABITAT ASSESSMENT — declared: already been obtained (22 Feb 2024)
  • VII. REQUEST FOR REDUCING OF MINIMUM SETBACKS — declared: already been obtained (20 Feb 2024)
  • VIII. SITE CO-ORDINATES IN WGS 84 AND SITE ELEVATIONCERTIFICATE — declared: already been obtained (13 Feb 2024)
  • IX. TREE CUTTING PERMISSION — declared: already been obtained (5 Feb 2024)
  • X. APPROVAL FOR NO ENCROACHMENT ON SITE, NOLITIGATION ON SITE, NO HT LINE PASSING OVER THE SITE,NO HARYANA CITY GAS DISTRIBUTION PIPELINE PASSINGOVER OR UNDER THE SITE, NO EFFECT OF PLPA ACT ONSITE, NO EFFECT OF ARAVALI NOTIFICATION, NO FORESTLAND ON SITE, NO EFFECT OF NATURAL CONSERVATIONZONE. — declared: already been obtained (2 Feb 2024)
  • XI. SITE PLANS — declared: already been obtained (29 Jul 2024)
  • XII. ENVIRONMENT CLEARANCE — declared: already been obtained (29 Jul 2024)
  • XIII. FIRE FIGHTING SCHEME — declared: already been obtained (28 Aug 2024)
  • XIV. MINING PERMISSION — declared: already been obtained (20 Aug 2024)
On file with HARERA · 54 files

On file with HARERA (54)

Plans

Site plan

5 files
Site Plan with Mep4 Sept 2024Superimposed Plan4 Sept 2024Superimposed Plan4 Sept 2024

Layout plan

1 file
Latest Layout Plan1 Aug 2024

Zoning plan

1 file
Application to Issue Certified Copy of Revised Zoning Plan4 Sept 2024

Demarcation plan

1 file
Demarcation Plan4 Sept 2024

Building plans

7 files
Tower A and B Elevation A4 Sept 2024HSVP Building Plan Approval4 Sept 2024Tower A and B Section B4 Sept 2024

Floor plans

15 files
Tower A - Lower Pent House Floor Plan and Area Diagram4 Sept 20244th Floor Commercial and Area Diagram4 Sept 2024Podium 3 - 3rd Floor Plan and Area Diagram4 Sept 2024

Services

Sewerage and drainage

1 file
Assurance of Drinking, Sewer and Storm Connection4 Sept 2024

Electricity

2 files
Non Applicability of Power Line Shifting4 Sept 2024Power Assurance Letter4 Sept 2024

Service plans

2 files
Tower A - Service Floor4 Sept 2024Service Plans on the Layout1 Aug 2024

Approvals and clearances

DTCP licence

2 files
LOI4 Sept 2024Licence Copy with Land Schedule1 Aug 2024

Environment clearance

1 file
Environment Clearance4 Sept 2024

Fire safety

1 file
Fire Fighting4 Sept 2024

Other NOCs and clearances

6 files
NOC from Debenture Trustee4 Sept 2024Airport Height Clearance4 Sept 2024Mining Permission4 Sept 2024

Land records

Land records

1 file
Sale Deed of the Land4 Sept 2024

Sales papers

Allotment and sale agreements

1 file
HSVP Allotment Letter4 Sept 2024

Money

Accounts and finance

2 files
CA Certificate-Quaterly Expenditure, Quaterly Cashflow and Quaterly Fund Flow4 Sept 2024Non-Default Certificate from a CA1 Aug 2024

The promoter’s papers

Declarations and affidavits

4 files
Affidavit for 4 2 L D4 Sept 2024Bank Undertaking4 Sept 2024Undertaking Free from Encumbrance4 Sept 2024The Promoter’s Declaration on Affidavit1 Aug 2024

Other filings

Other filings

1 file
Various Approvals4 Sept 2024

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

The promoter declared Land allotted by HSVP through LOIEndst No.ZO002/EO018/UE029/LALOT/0000000385. We could not read a licence number from that, so nothing is claimed about it here.

declared in the registration application (Form REP-I), Gurugram bench · submitted 1 Aug 2024 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 4 Nov 2026

Collector rate

No one collector rate can be matched to this project's type.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

5 files
Site Plan with Mep4 Sept 2024Superimposed Plan4 Sept 2024Superimposed Plan4 Sept 2024Site Plan with Green Area Calculation4 Sept 2024Approved Site Plan1 Aug 2024

Layout plan

1 file
Latest Layout Plan1 Aug 2024

Building plans

7 files
Tower A and B Elevation A4 Sept 2024HSVP Building Plan Approval4 Sept 2024Tower A and B Section B4 Sept 2024Terrace and Roof Plan4 Sept 2024Tower A and B Section C4 Sept 2024Tower A and B Section A4 Sept 2024Tower A and B Elevation B4 Sept 2024

Floor plans

15 files
Tower A - Lower Pent House Floor Plan and Area Diagram4 Sept 20244th Floor Commercial and Area Diagram4 Sept 2024Podium 3 - 3rd Floor Plan and Area Diagram4 Sept 2024Podium 1 - 1st Floor Plan and Area Diagram4 Sept 2024Type A and Type B Unit Plan4 Sept 2024Type C and Type D Unit Plan4 Sept 2024

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (54 in all), none is a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/3034 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Jhs Estate

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.

Ask Bhumiq about this developer, project or sector.

Plain-language answers on HARERA filings, DTCP licences, occupation certificates and court records, with their government sources and the dates they were read.