WATERSIDE RESIDENCES THE FOREST RESERVE

by Krisumi Corporation · Sector 36A, Gurugram

Not on our price list yet

Possession 30 Jun 2031 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 36A, Gurugram0.3 km from Dwarka Expressway, in a straight line
Carpet area
1,191–3,787 sq ft
In m²about 111–352 m², as declared
Registered by
KRISUMI CORPORATION PVT. LTD.the company that filed it, for Krisumi Corporation
Timeline
  1. 23 Jan 2025Layout and building plans approveddeclared to HARERA, read 1 Oct 2026
  2. 30 Jun 2031Possession, as declareddeclared to HARERA, read 1 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

298homes, 1,191 to 3,787 sq ft of carpet area
  • 1,000–1,500 sq ft1,191 sq ft3
  • 1,500–2,000 sq ft1,503–1,996 sq ft287
  • 3,000 sq ft and above3,050–3,787 sq ft8

Carpet area per home, as declared to HARERA (read 1 Oct 2026), in sq ft.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside5.174 acres in all, by use
  • Roads3.169 acres · 61%
  • Apartment buildings0.78 acres · 15%
  • Parks and playgrounds0.56 acres · 11%
  • Other uses0.507 acres · 10%
  • Parking0.158 acres · 3%

The land-use table of the HARERA application, declared to HARERA, read 1 Oct 2026. The share is of the land the table itemises.

In each home
  • KitchenLaminated wood / engineered wood / vitrified tiles / stone / marble / granite / vitromite / quartz
  • LiftsMitsubishi / schindler / KONE / OTIS / equivalent
  • FloorsLaminated wood / engineered wood / vitrified tiles / stone / marble / granite
  • WallsOBD / SEMI acrylic / acrylic emulsion / vitrified tiles
  • BathroomsD tiles / stone / marble / granite / vitromite / quartz 4 bathroom fittings reputed make of CP fittings & sanitary WARE
  • WindowsMS / aluminium / UPVC / glass
  • Main doorFIRE resistant flush door
  • Electrical fittingsModular / switch box and fittings

The developer’s specifications in the HARERA application, declared to HARERA, read 1 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 36A, GurugramSector 36A, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Dwarka ExpresswayOpen, 17 Aug 20250.3 km
  • Delhi–Gurugram–SNB RRTS2.3 km
  • Sohna Elevated Corridor (NH-248A)6.4 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 7 projects in Bhumiq’s records, by what HARERA’s record shows
  • OC or CC dispatched: 1
  • Registered, no OC or CC yet: 6

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it; asking rates from the Bhumiq team price list, 16 Sep 2026.

Questions buyers ask

Is WATERSIDE RESIDENCES THE FOREST RESERVE registered with HARERA?From the records · HARERA, read 3 Nov 2026

HARERA lists it as GGM/944/676/2025/47. Valid to 30 Jun 2031.

The source ↗
What is the possession timeline for WATERSIDE RESIDENCES THE FOREST RESERVE?From the records · HARERA, read 3 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 30 Jun 2031. Its registration runs to 30 Jun 2031; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around WATERSIDE RESIDENCES THE FOREST RESERVE?From the records · Map pin and road lines, read 6 Sep 2026

WATERSIDE RESIDENCES THE FOREST RESERVE is in Sector 36A, Gurugram; the site address declared to HARERA is Sector- 36a. In a straight line it is about 0.3 km from Dwarka Expressway, 2.3 km from Delhi–Gurugram–SNB RRTS and 6.4 km from Sohna Elevated Corridor (NH-248A).

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building WATERSIDE RESIDENCES THE FOREST RESERVE?From the records · HARERA, read 3 Nov 2026

WATERSIDE RESIDENCES THE FOREST RESERVE is a Krisumi Corporation project, registered by its company KRISUMI CORPORATION PVT. LTD..

The source ↗Krisumi Corporation's projects and court record

The records

What the registers hold for WATERSIDE RESIDENCES THE FOREST RESERVE: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/944/676/2025/47: Registered. Valid to 30 Jun 2031.HARERA, read 3 Nov 2026 · See it on HARERA ↗
  • Land licence 39 OF 2013 is on the DTCP register, valid to 3 Jun 2031.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 23 Jan 2025, building plans 23 Jan 2025.Declared to HARERA, read 1 Oct 2026
The court record of Krisumi Corporation’s companies is on the developer’s page →

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 47 HARERA files, with the dates we read them
Registration no.
GGM/944/676/2025/47
Registration valid till
30 Jun 2031
Declared possession
30 Jun 2031

Declared by the promoter to HARERA

Land area
5.1743 (Acre) (20,939.65 sq m)
FAR
the application prints 350, which is not a ratio
licence
39 of 2013 dated 4.6.2013, 85 of2014 dated 8.8.2014 , 166 of 2023 dated 18.10.2023 and 71 of 2024 dated 28.06.2024
Estimated project cost
₹1429.83 crore
Cost of land
₹785.30 crore
Layout plan, declared approved (field 5a)
23 Jan 2025
Building plans, declared approved
23 Jan 2025
Construction to start
1 Jun 2025
Completion declared for
30 Jun 2031
Declared inventory · 11 types

Declared inventory — 11 types declared, first 8 shown

  • Apartment/Shops/Other Buildings · 3 units · 158.35 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 2 units · 185.47 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 2 units · 185.47 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 139 units · 185.47 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 2 units · 319.72 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 2 units · 351.86 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 3 units · 110.68 sq m carpet · 1 tower · one flat
  • Apartment/Shops/Other Buildings · 2 units · 139.67 sq m carpet · 1 tower · one flat
Statutory approvals, as declared · 2

Statutory approvals, as declared

  • I. AIRPORT HEIGHT CLEARANCE — declared: already been obtained
  • II. ENVIRONMENT CLEARANCE — declared: applied for but yet to receive
On file with HARERA · 47 files

On file with HARERA (47)

Plans

Site plan

3 files
Site Plan7 May 2025C12 -Phase 5-6 Site Plan Green7 May 2025Approved Site Plan28 Feb 2025

Layout plan

1 file
Latest Layout Plan28 Feb 2025

Zoning plan

1 file
Zoning7 May 2025

Demarcation plan

1 file
Super Imposed Demarcation Plan7 May 2025

Building plans

4 files
C9 -Phase 6 Structural Drawing7 May 2025C7 -Phase 6 Elevation7 May 2025C8 -Tower 4.1 Section7 May 2025A18 - BR III7 May 2025

Floor plans

3 files
C10 -Phase 5-6 Parking Plan7 May 2025C5 -Phase 6 Floor Plans7 May 2025C6 -Phase 6 Floor Plans7 May 2025

Services

Electricity

1 file
A20 - Electrical Assurance7 May 2025

Service plans

3 files
A26 - 33.38125 Acre Assurances7 May 2025A19 -Service Estaimate Application7 May 2025Service Plans on the Layout28 Feb 2025

Approvals and clearances

DTCP licence

5 files
License A1 - 33.38125 Acre7 May 2025LOI A2 - 33.38125 Acre7 May 2025A3 -LC IV7 May 2025

Other NOCs and clearances

1 file
A21 - Forest- 33.38125 Acre7 May 2025

Land records

Land records

6 files
A7 - Mutation Sihi, Harsaru 33.38125 Acres7 May 2025A12(B) -33.38125 Acres NEC Harsaru7 May 2025A8 - Jamabandi, Sihi, Harsaru 33.38125 Acres7 May 2025

Sales papers

Allotment and sale agreements

3 files
Allottment Letter7 May 2025Agreement for Sale7 May 2025Conveyance Deed7 May 2025

Brochure and specifications

1 file
Advertisement7 May 2025

Money

Accounts and finance

4 files
Cost Incurred Certificate-Ph-67 May 2025A6- Project Report Phase 67 May 2025Cost Estimates-Ph 67 May 2025Non-Default Certificate from a CA28 Feb 2025

Timeline and progress

Construction schedule

1 file
PERT Chart- Phase 67 May 2025

The promoter’s papers

Declarations and affidavits

3 files
Application Form7 May 2025Bank Undertaking Ph 67 May 2025The Promoter’s Declaration on Affidavit28 Feb 2025

Company papers

3 files
Prescribed Form ROC7 May 2025Mca ROC Details7 May 2025A13 - Prescribed Form ROC7 May 2025

HARERA’s orders

HARERA’s orders

1 file
Addendum to Coll Agreement7 May 2025

Other filings

Other filings

2 files
A9 - Village Harsaru, Sihi Map 33.38125 Acres7 May 2025Ndc7 May 2025

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The 4 DTCP licences named on the application

39 OF 2013 · Krisumi Corporation Pvt. Ltd. · GURGAON-MANESAR

Licence valid to 3 Jun 2031

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

85 OF 2014 · Krisumi Corporation Pvt. Ltd. · GURGAON-MANESAR

Licence valid to 7 Aug 2029

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

166 OF 2023 · Krisumi Corporation Pvt. Ltd. · GURGAON-MANESAR

Licence valid to 17 Aug 2028

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

71 OF 2024 · Krisumi Corporation Pvt. Ltd. · GURGAON-MANESAR

Licence valid to 27 Jun 2029

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 28 Feb 2025 · read 1 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 3 Nov 2026

Land under the 4 licences

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

39 OF 2013: 58 parcels, 25.1 acres in all, in Sihi (hadbast 108, tehsil Manesar) and Harsuru (hadbast 107, tehsil Harsaru).

The licence register prints the same licensed area, 25.1 acres.

  • 2//11/14 kanal 4 marlaSihi (108)
  • 2//11/31 kanal 11 marlaSihi (108)
  • 2//12/118 marlaSihi (108)
  • 2//12/22 kanal 10 marlaSihi (108)
Show the other 54 parcels
  • 2//12/57 marlaSihi (108)
  • 2//132 kanal 4 marlaSihi (108)
  • 2//15/11 kanalSihi (108)
  • 2//15/11 kanal 2 marlaSihi (108)
  • 2//16/22 kanal 10 marlaSihi (108)
  • 2//16/21 kanal 10 marlaSihi (108)
  • 2//184 kanal 10 marlaSihi (108)
  • 2//183 kanal 10 marlaSihi (108)
  • 2//19/11 kanal 7 marlaSihi (108)
  • 2//19/29 marlaSihi (108)
  • 2//19/31 kanal 4 marlaSihi (108)
  • 2//19/41 kanal 19 marlaSihi (108)
  • 2//19/51 kanal 1 marlaSihi (108)
  • 2//19/62 kanalSihi (108)
  • 2//208 kanalSihi (108)
  • 2//21/12 kanal 9 marlaSihi (108)
  • 2//228 kanalSihi (108)
  • 2//238 kanalSihi (108)
  • 2//25/14 kanalSihi (108)
  • 1//14/13 kanal 10 marlaSihi (108)
  • 1//15/11 kanal 7 marlaSihi (108)
  • 1//15/21 kanal 6 marlaSihi (108)
  • 1//15/33 kanal 2 marlaSihi (108)
  • 1//15/42 kanal 10 marlaSihi (108)
  • 1//16/11 kanal 11 marlaSihi (108)
  • 1//16/21 kanal 17 marlaSihi (108)
  • 1//17/1/12 kanal 8 marlaSihi (108)
  • 1//25/19 marlaSihi (108)
  • 1//25/22 kanal 13 marlaSihi (108)
  • 2//141 kanal 5 marlaSihi (108)
  • 2//177 kanal 15 marlaSihi (108)
  • 2//175 marlaSihi (108)
  • 2//248 kanalSihi (108)
  • 7//1/24 kanalSihi (108)
  • 7//108 kanalSihi (108)
  • 7//11/13 kanal 2 marlaSihi (108)
  • 7//12/11 kanal 2 marlaSihi (108)
  • 7//2/24 kanalSihi (108)
  • 7//98 kanalSihi (108)
  • 8//310 marlaSihi (108)
  • 8//57 kanal 10 marlaSihi (108)
  • 8//510 marlaSihi (108)
  • 8//67 kanal 10 marlaSihi (108)
  • 8//610 marlaSihi (108)
  • 122//188 kanalHarsuru (107)
  • 122//228 kanalHarsuru (107)
  • 122//238 kanalHarsuru (107)
  • 122//246 kanal 18 marlaHarsuru (107)
  • 132//1/22 kanal 2 marlaHarsuru (107)
  • 132//28 kanalHarsuru (107)
  • 132//3/14 kanal 2 marlaHarsuru (107)
  • 132//918 marlaHarsuru (107)
  • 132//99 marlaHarsuru (107)
  • rectangle 8, kila 37 kanal 10 marlaSihi (108)

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

85 OF 2014: 5 parcels, 2.3813 acres in all, in Sihi (hadbast 108), tehsil Manesar.

The licence register prints the same licensed area, 2.38 acres.

  • 1//14/21 kanal 12 marla
  • 1//16/52 kanal 8 marla
  • 1//17/25 kanal 2 marla
  • 1//24/2/25 kanal 19 marla
Show the other 1 parcel
  • 1//25/34 kanal

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

166 OF 2023: 9 parcels, 2.9 acres in all, in Harsuru (hadbast 107, tehsil Harsaru) and Sihi (hadbast 108, tehsil Manesar).

The licence register prints the same licensed area, 2.9 acres.

  • 122//13/216 marlaHarsuru (107)
  • 122//13/31 kanal 12 marlaHarsuru (107)
  • 122//19/22 kanalHarsuru (107)
  • 122//20/22 kanalHarsuru (107)
Show the other 5 parcels
  • 122//218 kanalHarsuru (107)
  • 132//1/15 kanal 15 marlaHarsuru (107)
  • 132//3/22 kanal 1 marlaHarsuru (107)
  • 2//12/38 marlaSihi (108)
  • 2//12/412 marlaSihi (108)

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

71 OF 2024: 3 parcels, 3 acres in all, in Harsuru (hadbast 107), tehsil Harsaru.

The licence register prints the same licensed area, 3 acres.

  • 122//158 kanal
  • 122//168 kanal
  • 122//178 kanal

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 18 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village you want: Sihi (hadbast 108, tehsil Manesar) or Harsuru (hadbast 107, tehsil Harsaru). The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 2//11/1.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate

No one collector rate can be matched to this project's type.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

3 files
Site Plan7 May 2025C12 -Phase 5-6 Site Plan Green7 May 2025Approved Site Plan28 Feb 2025

Layout plan

1 file
Latest Layout Plan28 Feb 2025

Building plans

4 files
C9 -Phase 6 Structural Drawing7 May 2025C7 -Phase 6 Elevation7 May 2025C8 -Tower 4.1 Section7 May 2025A18 - BR III7 May 2025

Floor plans

3 files
C10 -Phase 5-6 Parking Plan7 May 2025C5 -Phase 6 Floor Plans7 May 2025C6 -Phase 6 Floor Plans7 May 2025

Among the uploads Bhumiq read from HARERA's page on 1 Oct 2026 (47 in all), none is a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/3358 · read 1 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Krisumi Corporation

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.