AASHIYARA-II

by Renuka Traders · Sector 37C, Gurugram

Not on our price list yet

Possession 8 Dec 2025 · as the developer declared it to HARERA

About this project

Key facts

Location
Sector 37C, Gurugram2.5 km from Dwarka Expressway, in a straight line
Carpet area
646 sq ft
In m²about 60–60 m², as declared
Registered by
RENUKA TRADERS PRIVATE LIMITED.the company that filed it, for Renuka Traders
Timeline
  1. 2 Aug 2021Layout and building plans approveddeclared to HARERA, read 29 Oct 2026
  2. 8 Dec 2025Possession, as declareddeclared to HARERA, read 29 Oct 2026

Homes on offer

The homes the developer declared to HARERA, by size.

276homes, 646 to 646 sq ft of carpet area
  • Under 1,000 sq ft646 sq ft276

Carpet area per home, as declared to HARERA (read 29 Oct 2026), in sq ft. Left out: 11 rows of a single unit, because the form lists homes, shops and other buildings in one table.

Amenities and specifications

How the land is set aside and what comes in each home, as the developer declared them to HARERA.

How the land is set aside2.531 acres in all, by use
  • Roads0.75 acres · 30%
  • Parking0.669 acres · 26%
  • Apartment buildings0.647 acres · 26%
  • Other uses0.192 acres · 8%
  • Electricity sub-station0.148 acres · 6%
  • Sewage and waste treatment0.125 acres · 5%

The land-use table of the HARERA application, declared to HARERA, read 29 Oct 2026. The share is of the land the table itemises.

In each home
  • KitchenOil bound distemper
  • LiftsAs per ISI standard
  • FloorsTiles
  • WallsOil bound distemper
  • BathroomsISI marked CP fitting water closet and WASH basin
  • WindowsAluminum powder coated/MS sections with 4-5 MM annealed ISI marked glass
  • Main doorBoth side laminated flush doors
  • Electrical fittingsISI marked switches and sockets

The developer’s specifications in the HARERA application, declared to HARERA, read 29 Oct 2026, in its words.

Location and connectivity

Where it is and what is near it. Every distance is a straight line, not a travel time.

Sector 37C, GurugramSector 37C, Gurugram (placed by sector) · openstreetmap.orgOpen in Google Maps
Roads and rail lines
  • Dwarka ExpresswayOpen, 17 Aug 20252.5 km
  • Delhi–Gurugram–SNB RRTS2.6 km
  • Sohna Elevated Corridor (NH-248A)4.5 km

Distances run in a straight line from the map point to each line on OpenStreetMap (read 6 Sep 2026). A stage shows only where an authority’s page states one, dated by that page.

Map data © OpenStreetMap contributors.

The builder

Its 2 projects in Bhumiq’s records, by what HARERA’s record shows
  • Other register states: 2

Other projects nearby

8 of Bhumiq’s projects within 3 km of the map point, nearest first, in a straight line.

Distances between the two map points, in a straight line; a project Bhumiq places only by its sector is measured to that sector’s point. Stage as Bhumiq’s team recorded it; possession as each developer declared it.

Questions buyers ask

Is AASHIYARA-II registered with HARERA?From the records · HARERA, read 3 Nov 2026

HARERA lists it as GGM/485/217/2021/53. The register’s record shows an end date of 8 Dec 2025. The register shows it as: Registration lapsed.

The source ↗
What is the possession timeline for AASHIYARA-II?From the records · HARERA, read 3 Nov 2026

When it registered the project, the developer declared that it would hand over homes by 8 Dec 2025. Its registration runs to 8 Dec 2025; a developer that needs longer has to ask HARERA for an extension. This is the developer's own date, not a promise from HARERA.

The source ↗
How is the connectivity around AASHIYARA-II?From the records · Map pin and road lines, read 6 Sep 2026

AASHIYARA-II is in Sector 37C, Gurugram; the site address declared to HARERA is Sector-37c, Village-Gharoli Khurd. In a straight line it is about 2.5 km from Dwarka Expressway, 2.6 km from Delhi–Gurugram–SNB RRTS and 4.5 km from Sohna Elevated Corridor (NH-248A).

The source ↗
What will I pay on top of the price?General guidance

You pay stamp duty and a registration fee when the sale deed is registered. In Haryana the stamp duty rate depends on where the home is and whose name it is registered in. A home still being built also carries GST; a finished home sold after its completion certificate carries none. Developers may also charge for parking, club membership, preferential location (PLC) and a maintenance deposit. Ask for the full cost sheet in writing before you pay a token.

Work out the stamp duty
Who is building AASHIYARA-II?From the records · HARERA, read 3 Nov 2026

AASHIYARA-II is a Renuka Traders project, registered by its company RENUKA TRADERS PRIVATE LIMITED..

The source ↗Renuka Traders's projects and court record

The records

What the registers hold for AASHIYARA-II: registration, licence, court, land, approvals and files, each with the register it comes from and the day Bhumiq read it.

  • HARERA registration GGM/485/217/2021/53: Registration lapsed. The register’s record shows an end date of 8 Dec 2025.HARERA, read 3 Nov 2026 · See it on HARERA ↗
  • Land licence 9 OF 2020 is on the DTCP register: Licence lapsed; the register prints its validity to 8 Mar 2025.DTCP, read 3 Nov 2026
  • Plans approved, as the developer declared: layout plan 2 Aug 2021, building plans 2 Aug 2021.Declared to HARERA, read 29 Oct 2026
The court record of Renuka Traders’s companies is on the developer’s page →

Flagged on the record

These are dates and statuses the registers print, as of the day Bhumiq read them. They are not a rating of the project.

  • Red flag: Licence 9 OF 2020 lapsed

    Named in this project’s application. Valid to 8 Mar 2025; the register’s note: “Merged With LC-3014B”. DTCP Haryana register, read 3 Nov 2026. Source

  • Amber flag: Registration lapsed

    The register’s record shows an end date of 8 Dec 2025. HARERA Gurugram, read 3 Nov 2026. Source

Not checked yet: the land owner records (jamabandi) and complaints at HARERA.

Homes sold and leftFrom the developer's quarterly reports to HARERA
Registration, licence, land and approvals in fullFrom the registers, with 35 HARERA files, with the dates we read them
Registration no.
GGM/485/217/2021/53
Registration valid till
8 Dec 2025
Declared possession
8 Dec 2025

Declared by the promoter to HARERA

Land area
2.53125 (Acre) (10,243.61 sq m)
FAR
2.37 proposed of 2.37 permissible
licence
License No. 09 of 2020
Estimated project cost
₹70.48 crore
Cost of land
₹4.15 crore
Layout plan, declared approved (field 5a)
2 Aug 2021
Building plans, declared approved
2 Aug 2021
Construction to start
1 Oct 2021
Completion declared for
8 Dec 2025
Declared inventory · 117 types

Declared inventory — 117 types declared, first 8 shown

  • Apartment/Shops/Other Buildings · 138 units · 59.985 sq m carpet · 2 towers · one flat
  • Apartment/Shops/Other Buildings · 138 units · 60 sq m carpet · 2 towers · one flat
  • Apartment/Shops/Other Buildings · 1 unit · 10.6 sq m carpet · under 25 m²: a shop or service unit the form does not label
  • Apartment/Shops/Other Buildings · 1 unit · 10.6 sq m carpet · under 25 m²: a shop or service unit the form does not label
  • Apartment/Shops/Other Buildings · 1 unit · 10.6 sq m carpet · under 25 m²: a shop or service unit the form does not label
  • Apartment/Shops/Other Buildings · 1 unit · 10.6 sq m carpet · under 25 m²: a shop or service unit the form does not label
  • Apartment/Shops/Other Buildings · 1 unit · 10.6 sq m carpet · under 25 m²: a shop or service unit the form does not label
  • Apartment/Shops/Other Buildings · 1 unit · 10.6 sq m carpet · under 25 m²: a shop or service unit the form does not label
Statutory approvals, as declared · 3

Statutory approvals, as declared

  • I. AIRPORTS AUTHORITY OF INDIA — declared: already been obtained (28 Jul 2021)
  • II. FOREST NOC — declared: already been obtained (18 Aug 2021)
  • III. ENVIRONMENT CLEARANCE — declared: applied for but yet to receive (19 Jul 2021)
On file with HARERA · 35 files

On file with HARERA (35)

Plans

Site plan

1 file
Approved Site Plan19 Aug 2021

Layout plan

1 file
Latest Layout Plan20 Aug 2021

Zoning plan

1 file
Zoning Plan17 Sept 2021

Demarcation plan

1 file
Demarcation Plan17 Sept 2021

Building plans

12 files
Building Plans - Residential Tower (T12) Terrance Plan17 Sept 2021Building Plans - Residential Tower (T13) Floor Plan17 Sept 2021Building Plans - Residential Tower T12 & T13 Elevation & Sections17 Sept 2021

Services

Sewerage and drainage

2 files
Service Plan - Drainage Layout20 Aug 2021Service Plan - Sewerage Layout20 Aug 2021

Water supply

2 files
Service Plan - Cold Water Supply20 Aug 2021Service Plan - Flushing & Irrigation Water Supply20 Aug 2021

Roads

1 file
Service Plan - Road Layout20 Aug 2021

Landscape and green areas

1 file
Building Plans - Green Area20 Aug 2021

Service plans

3 files
Service Plan - Coordination Layout20 Aug 2021Service Plans on the Layout20 Aug 2021Building Plans - Services20 Aug 2021

Approvals and clearances

DTCP licence

1 file
Licence Copy with Land Schedule19 Aug 2021

Fire safety

1 file
Service Plan - Fire Fighting20 Aug 2021

Other NOCs and clearances

2 files
Airport Authority of India (AAI)21 Aug 2021Forest NOC21 Aug 2021

Sales papers

Allotment and sale agreements

2 files
Draft Agreement to Sale23 Aug 2021Draft Allotment Letter20 Aug 2021

Money

Accounts and finance

2 files
Non-Default Certificate from a CA17 Sept 2021Cash Flow Statement19 Aug 2021

The promoter’s papers

Declarations and affidavits

2 files
Draft Application Form23 Aug 2021The Promoter’s Declaration on Affidavit20 Aug 2021

These are the copies HARERA holds. An approval belongs to the department that issued it, not to HARERA.

The DTCP licence named on the application

9 OF 2020 · RENUKA TRADERS PVT. LTD. · GURGAON-MANESAR

Licence valid to 8 Mar 2025

From the Town & Country Planning department’s licence register, read 3 Nov 2026.

A licence is permission to develop the colony; the HARERA registration above is permission to sell, and the two lapse separately.

declared in the registration application (Form REP-I), Gurugram bench · submitted 23 Aug 2021 · read 29 Oct 2026 · not verified by Bhumiq

source: https://haryanarera.gov.in/admincontrol/registered_projects/2 · fetched 3 Nov 2026

Land under the licence

The land the licence was granted over, as the Town & Country Planning department’s land schedule lists it. It does not say who owns the land now.

9 OF 2020: 4 parcels, 2.5188 acres in all, in Garauli khurd (hadbast 106), tehsil Kadipur.

The licence register prints the licensed area as 2.5313 acres.

  • 8//24/25 kanal 3 marla
  • 13//2/2/13 kanal 13 marla
  • 13//3/26 kanal 6 marla
  • 13//4/1/25 kanal 1 marla

The schedule also names who owned each parcel when the licence was granted. Bhumiq does not show those names.

From DTCP’s land schedule for this licence, read 23 Oct 2026. verify at source

Who owns this land today, or is it mortgaged?

The Bhumiq team checks it with you.

Check it yourself on jamabandi.nic.in
  1. Open jamabandi.nic.in, Haryana’s land records site, and choose Nakal.
  2. Pick district Gurugram, then the tehsil and the village: Garauli khurd (hadbast 106), tehsil Kadipur. The site lists villages in Hindi, so the hadbast number is the surer match.
  3. Pick the latest year, then a from the list here, such as 8//24/2.
  4. Type the CAPTCHA the site shows. The copy it opens names the owners as the revenue department last recorded them.

Bhumiq does not open it for you. The site asks a person to type its CAPTCHA, and the record belongs to the revenue department.

Collector rate

No one collector rate can be matched to this project's type.

Layouts & payment plan

Uploaded by the promoter to HARERA. These are the copies the regulator holds; an approval belongs to the department that issued it.

Site plan

1 file
Approved Site Plan19 Aug 2021

Layout plan

1 file
Latest Layout Plan20 Aug 2021

Building plans

12 files
Building Plans - Residential Tower (T12) Terrance Plan17 Sept 2021Building Plans - Residential Tower (T13) Floor Plan17 Sept 2021Building Plans - Residential Tower T12 & T13 Elevation & Sections17 Sept 2021Building Plans - Residential TOWER(T12) Floor Plan20 Aug 2021Approved Building Plans, Full Set20 Aug 2021Building Plans - Parking Area20 Aug 2021

Among the uploads Bhumiq read from HARERA's page on 29 Oct 2026 (35 in all), none is a floor plan or a payment plan.

source: https://haryanarera.gov.in/view_project/project_preview_open/1632 · read 29 Oct 2026

Talk to the Bhumiq team about payment plans

The call is with the Bhumiq team. You need a free account so we can call you back.

Run due diligence on Renuka Traders

Its court cases, its DTCP licences and the source of each fact, free once you sign in.

Open the developer profile

As of the fetch date shown, HARERA Gurugram records showed the facts above. Statuses change. Verify at the portal for transactions.